地下管道施工方案正式版

地下管道施工方案正式版
地下管道施工方案正式版

目录Catalogue

一、概述General description (2)

二、管沟开挖及管基础处理Trench excavation and foundation treatment ·3

三、钢管安装Steel pipe installation (11)

四、水压试验Hydraulic test (17)

五、管道防腐Pipe anticorrosion (21)

六、检查井、水封井和雨水口Inspection well, water closing well and inlet24

七、质量控制Quality control (26)

八、交工验收Take over (27)

九、劳动力需用计划Manpower schedule (28)

十、施工机具及手段用料需用计划Construction tools and material schedule29 十一、施工总体进度计划General construction schedule (31)

一、概述

一、Introduction

1.1、乙烯装置地下管道主要包括循环冷却给水管道SW、循环冷却回水管道RW、中间冷却给水管道IW、污染雨水及生产污水管道SD、高压消防水管道FW、清净雨水管道ND。管道材质有碳钢管、玻璃钢管。地下管道安装工程量见表1。

The underground piping of ethylene complex mainly refers to the installation of piping for recycling cooling water, industry water, firefighting water, sewage and rain water pipelines. The piping material includes steel pipe, cast iron pipe, and sand inclusion spiral glass fiber reinforced plastic pipe etc. The workload of installation of underground piping can refer to the Table 1.

地下管道安装工程量一览表表1

Table 1 List of quantity of underground piping installation

1.2、Reference:

1.2.1、设计图纸SEI DWG.NO 。(3102-7900-S-1~35)Design drawings

1.2.2、《给水排水管道工程施工及验收规范》。(GB 50268-97)<>

1.2.3、《埋地给水排水玻璃纤维增强热固性树脂夹砂管管道工程施工及验收规程》。

(CECS 129:2001)<

supply and sewerage engineering with underground glass fiber reinforced

thermosetting resin mortar pipes>>

1.2.4、《钢质管道聚乙烯胶粘带防腐层技术标准》。(SY/T0414-98)<

of polyethylene tape coating for steel pipeline>>

1.2.5、《给水排水管标准图集合定本S1》(上、下册2002版)<

sewerage pipelines standard collection of drawings >>

二、管沟开挖及管基础处理

二、Excavation of piping trenches and treatment of piping foundation

2.1、定位放线

Positioning setting-out

2.1.1、开工前业主主管部门应提供装置的坐标方格网和永久水准位置及高程数值,并把高程引至装置预先选择好的位置。

Before starting, construction personnel should ask for the coordinate grid net, permanent

benchmark and elevation of the equipment from the Owner’s authority department. The elevation should be led to the pre-selected location.

2.1.2、平面位置应以地下管道中心线及坐标进行放线,控制桩应设在管道敷设中心线两侧,距中心线不少于3m且便于观察的地方。沿管道铺设方向应设置临时水准点,且每隔200m不宜少于一个。

Plane locations should be set-out according to the center line and coordinate of the underground piping. Control piles should be set up at both sides of the center line of the piping, and at the location more than 3m away from the center line and easy for observation. At least one reference point should be setup each 200m according to the pipelines.

2.1.3、测量人员按施工要求,根据控制桩定出管线中心位置,沿管线沟槽开挖宽度在地面上撒灰线标明开挖边线。

Survey personnel determine the location of piping center according to control pipes based on construction requirements. Lime line is drawn on the ground along the excavation width to indicate the edge line of the excavation.

2.2、沟槽开挖Trench excavation

2.2.1、沟槽开挖时应根据所放白灰线进行,施工中采用反铲挖掘机,开挖时应在设计槽底高程以上保留200mm余量,防止超挖,余量用人工清挖。对于不宜采用机械开挖的部位采用人工开挖。

Trenches should be excavated as per the lime line set out. Reverse shoveling excavator is used in construction. 200mm margin should be reserved above the design bottom elevation. Over-excavation should be avoided and the margin should be excavated by man power. The location improper for machine excavation should be excavated by man power.

2.2.2、沟槽出现超挖或扰动情况时,应及时处理,用碎石回填压实,压实密度不低于天然地基。当沟槽底部为淤泥时,应比设计高程深挖300mm,然后用碎石回填到设计高程。槽底高程的允许偏差为±20mm。

The over excavation and disturbance of trenches should be treated in time. If the over excavation of dry trenches is within 150mm, it can be backfilled and compacted with original earth, and the compacting density should not be lower than that of the natural ground.

2.2.3、沟槽开挖时其两侧沟壁放坡坡度及底宽要求,应严格执行规范规定。当边坡无支撑且坡顶无负荷时,沟槽开挖坡度不低于1:1.0。如开挖放坡受限和土方转运有困难时,

应采用适当的方式支撑边坡,保证施工安全。管道沟槽底部的开挖宽度为:B=D1+2(B1+B2+B3)。其中D1为管道外缘宽度。B1为管道一侧的工作面宽度,具体见表2。B2为管道每一侧的支撑厚度(150—200㎜)。B3为现场浇灌混凝土管渠一侧防护板的厚度。The width of the trench bottom and the sloping of the trench walls should strictly accord with code regulations. The slope of trench excavation is no less than 1:1.0 when no slope bracing and no loading on the top of slope. Proper slope bracing should be used if there is difficulty in excavation and earth delivery to ensure construction safety. The bottom width of pipe groove is B=D1+2(B1+B2+B3). The D1 is the outside width and the B1 is the working width of one side, the detail in table 2. The B2 is the support thick of each side (150~200mm). The B3 is the thick of protection plate which is located one side of the pouring concrete pipe duct.

管道一侧的工作面宽度(mm)表2 Working face width of the piping (mm)……………Table 2

2.2.4、管沟开挖出的泥土等,堆在管沟的一侧,堆放高度不宜超过1.5m,且距沟边缘不宜小于0.8m。对于2#路和4#路等,如果现场泥土无法堆放,需将泥土及时运出现场,堆放到甲方指定位置,待管道安装试压完毕后,再运进现场进行回填。当原土不满足回填条件时,应采用满足设计要求的新土进行回填。

The earth excavated should be stacked on one side of the trench and the stacking height should not exceed 1.5m and the distance to the edge of the trench should not be less than 0.8m。The earth should be stacked according to the requirement of the contract, which is excavated form 2# or 4# road. After the piping pressured test, the earth should be backfilled into the site. If the original earth is not according to the requirement, the qualified earth should be backfilled.

2.2.5、当沟槽挖深较大时,应合理确定分层开挖的深度。采用机械挖槽时,沟槽分层的深度应按机械性能确定。The depth of laying-excavated should be ensured according to the

mechanical character.

2.2.6、施工时,应合理安排施工顺序。考虑到装置路面的修复和管廊混凝土柱子浇注进度,需将3#、7#路下的埋地管道进行先期施工。对于6#路下的埋地管道,考虑到将来要走重型机械,可能对已施工完毕的消防管线造成破坏,需进行特殊保护。应采取在道路上铺设钢板的预防措施,钢板的厚度应不应低于30mm,所铺设的范围应为路面下有地下管道的部分,共计两段。然后可以施工裂解炉周围和2#、4#和9#路附近的埋地管道。最后施工受其他工程影响而暂时无法施工的部分。For the road repair and schedule of the concrete column pouring, the underground piping in 3# and 7# road should be constructed in advance during the construction. Special protect should be used for the underground piping in 6# road because the pressed caused by heavy machines. The steel plate (thick more than 30mm) should be paved on the road.

2.3、施工排水drainage

2.3.1、沟槽开挖中,对于沟槽内地表积水的排除,尤其是2#路、4#路两边管沟受路基下地表水影响较大,可采用盲沟或积水坑排水法,使用潜水泵抽水。针对本装置内地下水位较高,故需采用井点降水法,当采用井点降水时应使地下水位降至沟槽地面以下不小于0.5m。井点孔的直径应为井点孔外径加2倍过滤层厚度(一般为10-15cm)。

Drainage scheme should be determined according to the underground water level. If piping foundation is above the underground water level, blind trench or catch pit can be used for draining pond in trench with submerged pump. Well point method should be used for the drainage.

2.3.2、井点管的安装应居中,并保持垂直。填滤料时,应对井点管口临时封堵。滤料应沿井点管外四周均匀灌入;灌填高度应高于地下水静水位。The well point pipe would be placed in the middle and kept uprightness. During the feeding, temporary capping are used for the mouth of the well point pipe. Filling the material following the side of well point pipe and the height would higher than the level of underground stationary water.

2.3.3、轻型井点的集水总管底面及水泵基座的高程宜尽量降低。滤管的顶部高程,宜为井管处设计动水位以下不小于0.5m。The collector pipes bottom of the light-duty well point and the basement of water pump would be reduced in most cases. The difference in height for the filter pipe top and water level of well pipe would be more than 0.5m .

2.3.4、井壁管长度的允许偏差应为±100mm;井点管安装高程的允许偏差应为±

100mm。The scope of allowable deviation for the well end pipe length is ±100mm and the scope of allowable deviation for the well point pipe height is ±100mm.

2.3.5、施工排水终止抽水后,排水井及拔除井点管所留孔洞,应立即用砂、石等材料填实;地下水静水位以上部分,可采用粘土填实。After drainage, the holes and drain well would be filling with sand, rock and etc. The clay soil would be used for the part on the level of underground stationary water.

2.3.6、井点管的制作,可以采取下面的制作方法。集水管的规格宜为φ89×4.5,长度不宜超过100m。在集水管上每隔1.0m焊接一条φ60×4的支管,支管长度宜为200mm~300mm。井点管规格宜为φ60×4,长度为5~6m,具体长度视沟槽深度而定。井点管底部800mm范围内均匀钻φ8的孔,孔与孔的纵向间距宜为100mm,沿管子四周均匀分布三列,列与列的孔应彼此错开。井点管底部用木楔堵死。滤管钻孔范围四周用滤网缠绕,滤网可选择50~80目,搭接量为20 mm~30 mm。井点管与集水管用塑料管连接,集水管的支管应朝上。最后集水管与真空泵相连,由真空泵将水排出。The fabrication method for well point pipe as follow: the specification of collector pipe isφ89×4.5 and the length is less than 100m. One branch pipe (φ60×4) would be welded on the collector pipe every 1.0m and the length scope of branch pipe is 200mm~300mm. The specification of well point pie isφ60×4 and the length scope is 5~6m and the detail length are ensured according to the depth of groove. The holes (φ8) are evenly distributed at the bottom of the well point pipe. The space between the holes is 100mm in longitudinal. Wood key would be used to block up the bottom of the well point pipe. Filter screen would be used to wrap the hole of filter pipe and the lap is 20mm ~ 30mm. The plastic pipe is used to connect the well point and the collector. At last, connect the collector pipe and vacuum pump and drain by the pump.

2.3.7、井点排水施工具体步骤如下:井点管应安装在沟槽一侧不影响挖沟的部位。首先选好井点位置,接着用高压水枪进行钻孔,然后将井点管安放进去,固定好位置。紧接着沿井点管四周均匀填入滤料,滤料的装填按2.3.2条的要求进行,最后将集水管和井点管,真空泵相连,即可开泵排水。排水渠道应由监理现场指定。The construction step of well point drainage as follow: the well point pipe would be installation on the side which are non-effect for groove. Select the well point position at first and drill hole by high-press monitor, put the well point pipe in the hole and fixed the position, then feeding equality following the well point pipe side, the detail requirement see 2.3.2. drainage after connecting the collector pipe,

well point pipe and vacuum pump and the drainage channel are designated by supervision.

2.4、沟槽支撑Support for groove

2.4.1、当沟槽深度超过1.5米或边坡靠近路边,放坡会导致土方挖掘量过大时,可采取增设支撑的形式对边坡进行加固。当撑板采用木材时,其构件规格宜符合下列规定:If the depth of groove is more than 1.5m or the side slope near the road, the side slope need reinforced and adding supports are adopted. If the support plate is wood, the specification of component according to the following item.

撑板厚度不宜小于50mm,长度不宜大于4m;横梁或纵梁宜为方木,其断面不宜小于150mm×150mm;横撑宜为圆木,其稍径不宜小于100mm;同时每根横梁或纵梁不得少于2根横撑,横撑的水平间距宜为1.5m~2.0m,横撑的垂直间距不宜大于1.5m。The thick of support plate is more than 50mm and the length is more than 4m. The beam or longitudinal beam is rectangular timber and the section is more than 150mm×150mm. The waling would be round wood and the diameter is more than 100mm. Tow walings are needed for each beam or longitudinal beam and the level interval is 1.5m~ 2.0m and the vertical interval is less than 1.5m.

2.4.2、撑板支撑应随挖土的加深及时安装。在软土或其他不稳定土层中采用撑板支撑时,开始支撑的开挖沟槽深度不得超过1.0m;以后开挖与支撑交替进行,每次交替的深度宜为0.4~0.8m.The bracing would be installed along with the excavation. The depth of excavation is no more than 1.0m when the bracings are used in the soft soil. Then the excavation and bracing executed by turns, the suitable depth is 0.4~0.8m.

2.4.3、撑板的安装应与沟槽槽壁紧贴,当有空隙时,应填实。横梁应水平,纵梁应垂直,且必须与撑板密贴,连接牢固;横撑应水平并与横梁或纵梁垂直,且应支紧。The bracing installation would cling with the wall of groove. The beam would be level, and the longitudinal beam would be vertical and cling with the bracing and connected firmed.

2.4.4、上下沟槽应设安全梯,不得攀登支撑。The safety ladders would be placed at the grooves and climbing the support are forbidding.

2.4.5、支撑的拆除应与回填土的填筑高度配合进行,且在回填后应及时回填。多层支撑的沟槽,应待下层回填完毕后再拆除其上层槽的支撑。Remove the bracing and backfill soil would be executed by turns. Remove the top bracing after backfill the bottom layer.

2.5、管基处理Treatment of piping foundation

2.5.1当沟槽挖到设计高程后,按设计要求底层应铺设300mm厚的碎石层,并夯实,

密实度=94%。When the height of groove is the design height, pave broken stones layer (Thick is 300mm) and compaction, the compaction rate is 94%.

2.5.2、然后铺设一层中砂粗砂,厚度要求为距管底不小于100mm,顶部高程为管中心。对于玻璃钢管线,需浇注1800带型混凝土基础,混凝土标号为C30。最小厚度为距管底不小于100mm。混凝土顶部高程为管中心。在浇注混凝土时,应先浇注管道底部基础,同时在承插口部位预留出工作坑。当底部基础浇注完毕,满足设计高程且强度达到使用要求后,再进行玻璃钢管安装。管道固定好位置后,进行管道两边基础浇注。在浇注时,应确保管道与基础之间充分进行填充,不得有间隙。当混凝土强度达到设计要求时,然后再进行后续回填工程。Then paving the thick sand, the thick requirement is no less than 100mm, the top height is the center of pipe. For glass steel pipeline, the 1800 concrete would be pouring as foundation, the concrete class is C30. the min thick is no less than 100mm. The top height of concrete is the center of pipe. Pouring the foundation of pipe first and obligate working pit at the same time. When the pouring are finished and the height and the strength is qualified, install the glass steel pipe. Pouring the foundation of pipe when the pipe is location. When the strength of concrete is qualified, executed the backfill soil.

2.5.3、混凝土带型基础两边空隙用中砂粗砂回填,回填高度为管中心,并夯实。Backfill and compaction middle sands into the interval of concrete foundation. The backfill height is the center of the pipe.

2.6、工作坑开挖Excavation of operating pit

2.6.1、在沟内施焊的钢管管口部位及玻璃钢管承插口处,应在沟底挖工作坑,为防坑内存水,可在焊接作业及焊缝检验结束后用虚土回填。

At the location of steel piping joints that will be welded in the trench, welding operating pit should be excavated at the trench bottom. To avoid ponding in the pit, it can be backfilled with loose earth after welding works and welded joint inspection is finished.

2.6.2、现场各焊接管口处的试压检查坑应能满足管道试压检查和防腐补口需要,一般选择尺寸为800×800×300mm,在试压作业前挖妥。

To satisfy the requirements of piping pressure test and anti-corrosion opening, the pressure test inspection pit at welded piping nozzles should be excavated before pressure test. The general size is 800×800×300mm.

2.6.3、玻璃钢管工作坑尺寸见表3

The dimension of fiber glass pipe working pit see the following table 3.

接口工作坑开挖尺寸Dimension(mm)表3 table 3

D1为管外径(mm)D1 is the external diameter of the pipe.

2.7、沟槽回填Trench backfill

2.7.1、对于压力管道,当水压试验及严密性试验合格且焊口外防腐补漏、补口合格后,对于玻璃钢管道,当每道接口严密性试验合格及带型基础强度满足要求,以及其它隐蔽项目经共检合格后,应及时回填沟槽。For pressure pipe, after the hydraulic pressure test and leakage test, outside of crater anticorrosion, repaired mouth is qualification. For glass steel pipe, backfill trench in time after the leakage test, strength and the hidden item are qualification.

2.7.2、沟槽回填应按照设计图纸要求进行,最底下一层采用中砂粗砂回填,回填高程为管中心。第二层用原土回填,回填土最大颗粒不大于40mm,回填高程为高于管顶200mm。第三层用原土回填,回填土夯实的压实系数大于96%,回填高程应为地面高度。Trench backfill according to the requirement of design drawing. The bottom backfilled by medium sand or thick sand, the height of backfill is the center of pipe. The second layer backfilled by original soil, the max particle of backfill earth is less than 40mm and the height is 200mm higher than the top of pipe. The third layer is backfilled by original soil and the compaction factor is more than 96%, the height of backfill is the ground level.

2.7.3、管腔两侧沟腔填土应对称运入和夯实,且需分层夯实,不得使管道发生位移和损伤。Symmetry compaction in layers and backfill soil to the both side of pipe. Avoid the pipe moved and damaged.

2.7.4、对于过路管道或套管,回填时,应用中砂或粗砂回填到高于管道或套管顶部300mm处。For the pass by pipe and sleeving, backfill the medium sands or thick sands until the

height is 300mm higher than the top of pipe and sleeving.

三、钢管安装Installation of steel piping

3.1、钢管、钢管件、阀门检验Inspection of steel piping, fitting and valve

3.1.1、钢管、钢管件、阀门的材质、规格、压力等级应符合设计文件要求,必须有出厂合格证书。

The material, specification and pressure of steel piping, fittings and valves should accord with requirements of the design documents. They must be attached with quality certificates and the contents and data in the quality certificates should accord with requirements of current national standards.

3.1.2、阀门规格、型号、压力等级应符合设计规定,且外观检验合格。阀门到货后,需对阀门逐一进行试压,阀门以公称压力的1.5倍进行强度试验。以公称压力进行严密性试验,以无泄漏、无渗漏为合格。

The material, specification and pressure grade of valves should accord with the design regulations and the appearance should be examined. Pressure test should be done one by one after the valves delivered. Strength test with 1.5 times of nominal pressure should be done on valves. Tightness test with nominal pressure should be done and the valves are qualified if no leakage and seepage is found.

3.1.3、由于部分管沟离道路较远,且地基土质松软,如2#路和950管廊等处,吊车和运输车无法将管材,石料等运到沟边,因此需要进行二次倒运管材。使用50吨履带式吊车,下面铺设钢板进行倒运。石料及沙土采取铺钢板,然后用挖掘机进行倒运。Secondary convey are needed because some grooves are far away from the loose road, such as 2# road and 950 pipe rack. Steel plate are paved for the 50t crawler crane convey the stones and the excavator convey the sands.

3.2、钢管安装Installation of steel piping

3.2.1、钢管安装前应逐根测量,要选用管径相差最小的管子进行组对连接。并应先检查管子的防腐层,合格后方可安装。防腐层若有外伤,补伤完毕并检查合格后方可安装。

Steel piping should be measured one by one before installation. The pipes whose diameter difference is smallest should be joined. The anti-corrosion layer of the piping should be examined first and only qualified piping can be installed. If anti-corrosion layer is damaged, it

should be repaired and examined before installation.

3.2.2、钢管进行单根下管,吊装时必须事先对吊车能力及地面承载能力进行计算核实。

Single steel piping can be laid. If longer piping assembled by groups of pipes needs to be laid down, the crane capacity, stiffness of steel piping and ground carrying capacity must be calculated and verified in advance.

3.2.3、钢管单根下管时可用尼龙兜带吊装下管,长管段下管时可使用外套橡胶管的钢丝绳兜捆,为防止变形应采用多吊点抬吊。

Single steel piping can be laid down using nylon kicking strap. The longer piping can be wrapped and bound with steel wire rope shielded by rubber pipes.

3.2.4、钢管运到现场时,宜沿沟边摆放布置,不宜过于集中,若因条件限制时应尽量缩短二次倒运距离。运输过程中应严格保护好管道防腐层,运到现场的钢管应下垫上隔保护好。

Steel piping should be laid along the side of the trench when it is transported into the site. It should not be laid too centralized. If necessary, the distance for secondary delivery should be shortened as much as possible. Mat should be set up under the steel piping and separation material should be set up on it for good protection.

3.2.5、钢管对口时应保持内壁平齐。用300mm直尺在接口周围贴靠,错口的允许偏差为0.2倍壁厚,且不得大于2mm。

Before assembling two steel pipes, the perimeters of the two ends and the verticality of the end faces should be verified first. The two inner walls should be in same level when the two pipes are assembled. The allowable deviation measured with ruler at the joint should not be larger than 2mm.

3.2.6、焊接钢管组对时环向焊缝距支架净距不应小于100mm;直管段两相邻环向焊缝的间距应不小于200mm;管道任何位置不得有十字形焊缝。

The net distance between the circumferential welding joints and the support should not be less than 100mm。The spacing between two neighbor ring-direction welding joints in the straight piping section should not be less than 200mm.。Cross welding joint is not allowed at any location.

3.2.7、对于有开管口要求的管段,组装前应核准管口开口位置,其开口部位不得有焊缝,否则应旋转或更换钢管,任何管口均不得开在焊缝和管件上。

For piping sections in which nozzle will be provided, the locations of the nozzles should be

verified before they are joined. Welding joint is not allowed in the opening, or the steel piping should be rotated or replaced. Any nozzle should not be on the welding joints and fittings.

3.2.8、钢管组对完毕,检查合格后方可进行定位点焊,点焊应采用同正式焊接相同的焊接材料和焊接工艺规范。点焊施焊应对称进行,其焊接厚度应与第一层焊接厚度相同。点焊长度为50~60mm,数量为5点,且沿管道周围均匀分布,不得在纵焊缝处点焊。

After the steel piping is assembled and examined, tack welding for positioning can be carried out. The welding material and welding process for tack welding should be the same as that of the formal welding. Tack welding should be performed symmetrically, and the welding thickness should be the same as that of the first layer of welding.

3.2.9、钢管安装完毕后应将两端管口进行封闭,防止杂物及非作业人员随便进入管内,造成管内污染。做好槽边雨水径流疏导路线的设计及槽内排水措施,防止雨季沟槽积水发生漂管现象。一般采取在沟槽底部挖排水沟,同时在沟槽下游设积水坑,然后用潜水泵排水的方法。

After steel piping is installed and tack welding is finished, the piping should be backfilled in time. Backfilling should be carried out from both sides at the same time to 0.5m above the piping top. The nozzles at two ends of the steel piping should be sealed after installation to prevent rubbish or non working personnel from entering that may cause pollution inside of the piping.

3.3、焊接及检验Welding and inspection

3.3.1、管口焊接前应先修口,管端端面的坡口角度、钝边、间隙应符合焊接工艺规程要求。具体要求见附表1

Groove should be prepared before welding the pipe nozzle. The groove angle, root face and spacing at the end face should accord with requirements of welding technology procedures. See the detail in table 1:

3.3.2、管口内外侧钢管表面应将油垢、泥土、杂物全部清理干净,并应用砂轮将管口边缘及坡口两侧各不小于10mm的范围内的钢管表面打磨出金属光泽。

The oil, earth, and rubbish on the outer and inner surface of the piping nozzle should be removed and cleaned. The nozzle edge and the steel piping surface within not less than 10mm scope at the both sides of the groove should be polished to have metal luster with the grinding wheel.

3.3.3、施焊人员必须持有由劳动部门颁发的焊工合格证,其材质类别及项目代号应与

施焊位置相同,且在有效期内。

The welding personnel must hold permits issued by the labor department. The material and job code should be the same as that needed. The permit should be valid.

3.3.4、钢管材质为Q235-B,选用J422(E4303)酸性碳素结构钢焊条,采用手工电弧焊焊接,焊条规格为Φ3.2mm、Φ

4.0mm

Steel piping material to be used is Q235-B. J422(E4303) acidic carbon structural steel welding rod is used. Manual arc welding is used. The specification of the welding rod is Φ3.2mm,Φ4.0mm.

3.3.5、焊接材料必须有出厂合格证书,使用前应按要求进行烘干并恒温保存。焊条要用专用焊条筒携带到施工现场,并应一次使用完毕。使用时随用随拿,剩余焊条应送回烘干室,重新烘干后方可使用。表面锈蚀、焊药脱落的焊条不得使用。

The welding material must be attached with quality certificates and is dried as required and stored at constant temperature before being used. The welding rods should be carried to the construction site with special welding rod carrier and should be used up in one time. The welding rod should be taken out from the carrier for use, and left ones should be sent back to drying and can be used only being dried. The welding rods whose surface is rust and flux is flaked cannot be used.

3.3.6、管口焊接时,焊接工作宜一次完成,若因故不能一次焊接完毕,下次焊接前应按坡口处理要求重新处理合格后方可继续焊接。

The welding of piping nozzle should be finished in one time. If cannot, the groove should be re-treated according to the requirements before continuing the welding.

3.3.7、厚壁管道采用多层焊接,每层焊接接头处应认真打磨,且各层的焊接接头处应相互错开,盖面焊肉要波纹整齐、表面光滑、结合良好。

Multiplayer welding is used for thick wall piping. The welding joints at each layer should be polished carefully and the welding joints at different layer should be staggered. The cover welding should be of orderly ripple, smooth surface and good combination.

3.3.8、当风力大于5级、下雨天气及相对湿度大于90% 时,无有效保护措施不得施焊。

When wind force is greater than Grade 5, and in rainy days or the relative humidity is heavier than 90%, welding is not allowed without protective measures.

3.3.9、由于受材料到货计划影响,部分支线、阀门和三通无法在施工阶段到货,必将影响安装。采取的措施是先安装主线,然后进行试压回填。待其他材料到货后,再用人工开挖管沟,最后进行支线、阀门和三通安装。Because the delay of material supply, some branches, valves and tees would not supplied in construction period, install the main pipeline first and then backfill for pressure test. When the other materials are supplied, excavate groove by manpower and install the branches, the valves and the tees at last.

3.4、焊缝检验Inspection of welding joints

3.4.1、管口焊接完毕,应及时清除表面的渣皮及两侧的飞溅物。焊缝的外观检查应在水压试验之前进行,焊缝的外观质量应符合如下规定:

After the piping nozzle is welded, the slag crust on the surface and the splashed dregs on both sides should be removed in time. The appearance inspection should be done before the hydrostatic test. The appearance quality of the welding joint should accord with the following regulations:

①、焊缝和热影响区表面不得有裂纹、气孔、弧坑和夹碴等缺陷;表面光滑、均匀,焊缝和母材应平缓过渡;

Cracks, gas porosity, arc pit and slag are not allowed in the welding joints or on the surface of heat affected zones. The surface should be smooth and even. The welding joints should gradually join with the base metal.

②、焊缝宽度应焊出坡口边缘2~3mm;

The welding joint should be extended 2~3mm out of the edge of the groove;

③、焊缝高出母材高度应小于2.5mm;

The height of the welding joint above the base metal should be less than 2.5mm;

④、焊缝咬边深度应小于或等于0.5mm,焊缝两侧咬边总长不得超过焊缝长度的10%,且连续长度应不大于100mm;

The depth of the weld undercut should be less than or equal to 0.5mm. The total length of both sides of welding undercuts should not exceed 10% of the length of the welding joint, and the continuous length should not be larger than 100mm;

⑤、错边量应不大于2mm;

The displacement should not be larger than 2mm;

⑥、焊缝不得低于母材。

The welding joint should not be lower than the base metal.

3.4.2、不方便进行二次试压的管线,可以对焊缝进行100%超声波无损检测(UT),角焊缝进行100%表面着色(PT)处理(执行JB4730-94,Ⅱ合格)。探伤不合格的焊缝应返修,返修次数不得超过三次。

The butt welding joints (circular joints) on the pipe should be done with NDT as per the design requirements. Unqualified welding joints should be repaired, and the times of repairing should not exceed 3 times.

3.5、夹砂缠绕玻璃钢管安装Installation of sand inclusion spiral glass fiber reinforced plastic piping

3. 5.1、夹砂缠绕玻璃钢管安装前,应按设计要求进行检查,管道不得有任何损坏痕迹。The pipe would be inspected according to the requirement of design before the sand inclusion spiral glass fiber reinforced plastic piping is installed to ensure no any damage.

3.5.2、夹砂缠绕玻璃钢管安装前,应检查管道的承口、插口与密封圈接触的表面,表面应平整、光滑、无滑痕、无气孔。The surface of pipe socket and seal ring would be inspected before the sand inclusion spiral glass fiber reinforced plastic piping is installed to ensure the surface is level off, smooth, no slip mark and no air vent.

3.5.3、安装时,管道水压试验用的进水口及锁键槽摆在管道顶端。插口端与承口变径处在轴向应有一定间隙、DN300~1500mm管的间隙应控制在5~15mm。“O”型圈应紧密贴合在承口和插口的内外壁之间,且“O”型圈不能发生扭转。安装时应先将橡胶圈套入插口上的凹槽内,然后沿橡胶圈四周依次向外拉并慢慢放回凹槽,以保证橡胶圈受力均匀没有扭曲。During the installation, the inlet and lock key socket for the piping hydraulic test are placed on the top of the pipe. The clearance located between the end of socket and the socket reducer in axial. The clearance is 5~15mm between the DN300~1500mm pipes. The O type ring would be installed in the inside wall and outside wall and could not be torsion. First, trap the rubber ring into the channel of socket and to ensure no torsion.

3.5.4、在检查确认无损的情况下,依据厂家画出的插进深度限位线,将卡具卡紧在两管上,保证两管在同一条直线上,将装入“O”型圈的插口压入承口,压入深度符合限位线要求即可。然后用钢板条插入承口和插口之间的环状空隙,沿圆周检查一圈,确定橡胶圈槽内深度是否一致,否则应重新连接。Install the clip on the two pipes and the plus of O type ring into the socket, the depth according to the limited line. Plus the steel rod in to the clearance

of the sockets and check the round to ensure the depth according to the depth of the channel of rubber ring.

3.5.5、再次检查锁键槽是否对正,然后将尼龙棒慢慢插入管道的锁键槽内,至尼龙棒沿锁键槽环绕管道一周,在安装完毕前,最好保留尼龙棒的剩余长度。Recheck the lock key channel and plug the nylon stick into the lock key channel slowly and surround the piping. Keep the spare length before the installation is completed.

3.5.6、由于玻璃钢管道尺寸和位号已由玻璃钢管生产厂家定好,因此安装时,必须严格按照厂家给定的位号进行安装。The glass steel pipe would be installed according to dimension and item made by manufacture to avoid mistake.

3.6、阀门安装Installation of valves.

3.6.1、阀门安装前应按设计要求核对型号、规格,并应按介质流向确定阀门的安装方向,填料压盖的压紧螺栓要留有余量。阀门安装时,应处于关闭状态,阀杆及传动装置位置符合设计要求,且动作灵活。

The model and specification of valves should be verified before installation, and the installation direction should be determined according to the flowing direction of the medium. Allowance should be reserved for the pressure bolts in the cover of the filling material. The valves should be shut down when they are installed. The location of valve rod and transmission apparatus should accord with the design requirement and be agile.

3.6.2、阀门伸缩器应同阀门一块安装,安装时伸缩器的定位装置按厂家要求进行调整。

The valve compensator should be installed together with the valve. The positioning apparatus of the compensator should be adjusted as required by the manufacturer.

四、水压试验Hydrostatic test

4.1试压前的准备Preparation

4.1.1、钢管水压试验的管段长度不得超过1000m,试压前应对管段内部进行清理,将泥土及杂物彻底清理干净。

The length of the steel pipe for hydrostatic test cannot exceed 1000m. Yhe inside of the pipe should be cleaned and the earth and rubbish should be completely removed.

4.1.2、试压管段的两端应焊接盲板。试压管段不得采用闸阀做堵板,不得带消火栓、消防水炮和其它易损件进行试压。

Both ends of the test pipe should be welded with pipe sections with blind plate. The pressure test is forbidden with the wearing parts, such as gate valve, hydrant, etc.

4.1.3、试压管段的排水应设在管段的低点,在管段的高点应设排气阀。

The drainage for test pipe section should be set up at the lowest point of the section and air release valve should be set up at the highest point of the section.

4.1.4、试压用压力表采用弹簧管式压力表,压力表的量程为试验压力的1.5倍,精度等级为1.5级,表盘公称直径为150mm,压力表应经检测合格,并在有效期内。且压力表不少于2块。一块放在试压泵处,一块放在远离试压泵处。

The pressure meter used in test adopts corrugate pipe pressure meter whose range is 1.5 times of the test pressure and precision is Grade 1.5. The nominal diameter of the meter panel is 150mm. The pressure meter should be qualified through inspection and valid. At least two pressure meters are needed and one for the hydraulic test pump and the other far away the pump.

4.1.5、试压管段应在低点注水,以利气体排出。

Water should be poured in from the lower points for air releasing. The piping should be dipped in water for 24 hours after being fully filled and then hydrostatic test can be carried out.

4.1.6、水压试验前,除接口外管道两侧及管顶以上不小于500mm,应及时进行回填土,水压试验合格后,应及时剩余部分回填土。Backfill soil in time before the hydraulic test and backfill the other soil after hydraulic test is qualification.

4.2、压力管道水压试验Hydrostatic test for pressure piping

4.2.1对于生活给水管道,在进行水压试验时,应用洁净水进行。对于其它管道,可就近采用从装置临时给水网引水进行水压试验。由于2#路、3#路和4#路管道距离临时给水点较远,因此需要接橡胶临时管进行管道注水,距离超过200米。

Clean water should be used for the hydrostatic tests for all piping sections. If this condition cannot be met, water should be obtained from the water resource designated by the Party A and imported into the test piping section through temporary piping. The rubber temporary pipe are used for the poured water because the 2# road, 3# road and 4# road are far away from the water supply station.

4.2.2、管道水压试验压力为P+0.5且不小于0.9 MPa,其中P为工作压力(MPa)。根据设计图纸所给消防管线工作压力范围为0.8~1.2Mpa,故取最高值试验压力为1.7Mpa。The pressure of pipe hydraulic test is P+0.5 and more than 0.9Mpa, the P is working pressure (MPa).

According to the design drawing, the pressure scope of waterproof pipeline is 0.8~1.2Mpa, the max value test pressure is 1.7Mpa.

4.2.3、试压时采用电动试压泵分级升压,首先升压到0.3MPa进行管道焊口及支墩的检查;无异常现象时再升压到工作压力,对管道系统进行检查;无异常现象时,再升压到试验压力。The motor-operated test pump is used to increase the pressure in stages. First increase the pressure to 0.3MPa and examine the welding joints and pier of the piping; if no abnormal phenomenon is found, increase the pressure to the working pressure and examine the piping system and piers, if still no abnormal phenomenon is found, increase the pressure to the test pressure.

4.2.4、水压升到试验压力后,保持恒压10min,检查焊口及管道系统无异常变形及漏水现象,则管道强度试验合格。水压试验合格后,应立即卸压,将管道里的水排出,然后进行沟槽回填。

When the hydraulic pressure is increased to the test pressure, it should be kept for 10min, and examine whether there is abnormal deformation or leakage in the welding joints and piping system, if no, the piping strength is qualified. Relief pressure after the hydraulic test is qualified, drainage the water from the pipe and backfill the trench.

4.2.5、管道严密性试验采用注水法。在进行严密性试验时,不得有漏水现象。且实际渗水量应小于允许渗水量。压力管道严密性试验允许渗水量见表5the hydraulic pressure test are used for the pipe leakage test. The actual quantity of water seepage would less than the allowed quantity of water seepage. The allowed quantity of water seepage see the following table:

压力管道严密性试验允许渗水量表4 The allowed quantity of water seepage of pressure pipe leakage test table 4

4.2.6、水压试验时,严禁对管道及接口进行敲打或补修,缺陷处应做出标记,卸压后方可修补,修补后的部位经检验合格后,应重新进行管段水压试验。

Knocking or reparation of the piping and joints is strictly forbidden during the hydrostatic test. Mark should be made in the defect location. Reparation can be done only after the pressure is relieved. After the reparation is examined, hydrostatic test should be done again for that piping section.

4.2.7、管道试验升压前管道内的气体应排尽,若升压过程中,发现弹簧管压力表表针摆动、不稳,且升压较慢时,应重新排气后升压。

The air in the piping should be completely discharged before increasing the pressure. If it is found that the point of the corrugate pipe pressure meter swings and is unstable and the pressure increase is implemented too slowly, air should be released again and then pressure is increased.

4.2.8、由于消防管线系统大,加上受工期、到货时间和其它作业影响,故无法进行整体试压,必须分段进行试压。对于部分支线受材料到货计划影响,可能暂时无法安装,因此无法带支线进行试压,根据实际情况,可以考虑二次试压。对于可以进行二次试压的管线,可以先进行主线试压,待主线试压完毕后,进行管沟回填。当支线材料到货后,进行支线安装,然后通水进行整体试压。Subsection pressure test would be executed because the waterproof pipelines system is large and working period and material supplied. Secondary pressure test would be executed because the part of branch material supplied. The pressure test of main pipeline could be executed first and then backfill the trench. Execute the integer pressure test after the branch pipes are installed completely.

4.2.9、分段试压的划分如下:400-FW-1184202、400-FW-1184203、400-FW-1184205、400-FW-1184207、400-FW-1184208、DR7和DR8、DR9和DR10单独进行试压。

人工挖孔探明地下管线施工方案

A3.1施工组织设计/方案报审表

城西干道水西门隧道(K4+470-K4+550)支护桩工 程 水西门隧道(K4+470~K4+550)支护桩工程人工挖孔探明地下管线施工方案 编制人: 审核人: 审批人:

施工单位:南京第二道路排水工程有限责任公司 日期:2012年4月27日 水西门隧道(K4+470~K4+550)支护桩工程 人工挖孔探明地下管线施工方案 一、工程概况 城西干道水西门隧道(水西门大街交叉口以南K4+470~K4+550)支护桩工程,位于水西门大街路口以南部分,其区域内管线错综复杂,为支护桩施工带来不便。位于K4+504处为一已探明的中国移动光缆,现已知,中国移动光缆附近有埋深约6米的中国电信光缆,为确定其具体位置,现拟人工挖孔探明此处地下管线。二、施工规划 根据电信公司提供的管线信息结合此处的管线图纸,大致确定了光缆的平面位置。现拟以孔径1.3米、深约6米、24砖墙护壁的人工挖孔,探明管线具体位置及深度。 三、施工方案 施工流程: 桩位放样→井口清理及开挖→安装提升架→人工挖孔→分层开挖→24砖墙护壁→缩径开挖→24砖墙护壁→挖至管线处 1、从管线图可知,孔位大致在已知的中国移动电缆附近,故在

中国移动光缆南北向各挖一个孔。 2、此处地下深0.5米至6.1米处为粉质粘土,底部还夹有淤泥质土,不利于开挖,应分层开挖、护壁,每层高不超过1.5米。 3、挖孔采用从上到下逐层用镐、锹进行开挖,遇坚硬土或大块孤石采用锤、钎破碎,挖土顺序为先挖中间后挖周边。孔内挖出的土采用提升设备垂直运输到地面,堆积到指定地点,防止污染环境。 四、注意事项 1、应随时注意检查卷扬机、支腿、钢丝绳、挂钩(保险钩)、提桶超高限位装置等,应对护壁的状况进行检查,发现问题及时采取措施。 2、挖孔人员上下孔井,必须使用安全爬梯;井下需要工具,应该用提升设备递送,禁止向井内抛掷。井孔上、下应有可靠的通话联络,如对讲机等。 3、井下操作人员连续工作时间不宜超过4h,应及时轮换。 4、现场施工人员必须佩带安全帽、安全带,安全带接绳由孔上人员负责随作业而加长,井下有人操作时,井上配合作业人员必须坚守岗位,不得擅离职守。 5、孔底如需抽水时,必须在全部井下作业人员上地面后才能进行。 6、井孔内一律采用12V 安全电压和防水带罩灯照明,井上现场可用24V 低压照明。现场用电均须安装漏电保护装置。 7、孔内应经常检查有害气体浓度,当二氧化碳浓度超过0.3%,其他有害气体超过允许浓度时,均应设置通风设备。 五、文明施工 1、加强现场文明施工和材料、机具、设备的堆码,保持场地清洁。

循环水管道内外壁防腐工程施工方案

循环水管道内外壁防腐工程施工方案 一、编制说明 本施工方案是依据国家颁布的现行标准及我公司以往的施工经验编制而成,是对防腐施工工艺、质量、安全等方面所作的阐述与说明,它将是指导我方施工,并与业主紧密配合的依据,亦是接受贵公司监督的基础资料。为配合给贵公司安全、优质、高效的完成该项工程,我们精心策划,强化管理,合理选材,严密施工,以期达到延长设备使用寿命,减少设备维修次数,降低运营成本的目的,从而增强企业的社会效益和经济效益。 1.1编制依据 1)《涂装前钢材表面锈蚀等级和除锈等级》(GB 8923—88); 2)《涂覆涂料前钢材表面处理方法总则》(GB/T 18839.1-2002); 3)《工业设备、管道防腐蚀施工及验收技术规范》HGJ229—90; 4)《涂料粘度测定法》GB1723—79; 5)《漆膜附着力测定法》GB1720—79; 6)《质量管理标准体系》(GB/T 19001-2000); 7)公司在同类工程施工的经验; 8)根据甲方的有关规定及要求。 1.2编制原则 1.2.1以技术为先导,以全面质量管理覆盖式控制施工全过程,创造优质工程,降低工程成本,缩短施工工期。 1.2.2认真履行合同,为业主提供优质、满意的服务。 二、施工准备 2.1人员准备 2.1.1管理技术人员 主要管理技术人员在工程指定开工时间提前到达现场,安排施工材料、机械进场,抽检、调试。熟悉施工场地及施工环境,认真研究熟悉所承包工程范围内设计要求。准备一切相关开工资料填报工作。做好与甲方的交接和协调工作,熟悉厂规厂纪。

2.1.2施工人员 施工人员将在指定开工时间前3天到达施工现场,搭设临时设施,接受管理、技术人员对施工技术要求、安全文明施工的交底与培训,做好材料、施工对象的各项防护措施和接受学习甲方的有关施工安全教育培训。 本次工程施工人员配备表 2.1.3施工现场施工管理组织机构网络 2.1.4主要管理人员职责 (1)项目副经理:协助项目经理贯彻执行公司的质量方针,按《质量管理手册》和《程序文件》中的规定,协助项目经理组织和协调所承担项目的工作,做好施工过程的质量管理、环境管理、施工进度控制、安全文明施工管理,做好项目经理的助手,确保质量目标的实现。密切关注项目的进展情况,对计划执行的偏差、潜在的问题以及那些对项目效益可能产生影响的不利因素,向项目经理汇报,并拿出调整方案。协助项目经理考核评价项目主要责任人。行使项目经理委托的职权。 (2)现场施工负责人:在项目经理的领导下,现场经理全面负责现场的所有施工活动,包括施工方案、质量控制、进度控制、安全文明管理。负责定期向项目经理汇报项目实施情况。对现场施工进行全过程指导,负全面责任。作为项目经理在施工现场与业主及有关方面的联络人。 (3)技术负责人(总工程师):按公司规定权限审核技术文件,负责项目质保体系运行的日常工作,对工程重大质量事故负有直接责任。负责组织施工技术交底,审定工程采用的技术质量标准。检查施工保证措施和技术规范的执行情况,并参加项目考核评定工作。审核项目中乙方应材料采购的技术条件。 (4)安全员:根据公司安全管理规定、业主及当地安全法规要求,编制现场安全规定、各种应急预案,并负责监督实施及演练。组织对现场安全隐患和安全违章的日常检查。主持安全事故处理和事故产生的原因分析,确定现场违反安全标准的范围,采取补救措施,消除安全隐患。在安全问题上与现场经理、业主安全部门、人员保持密切的联系。 (5)质检员:规划和建立现场质量控制程序和质量检验的措施。制定现场检验程序,包括通知程序和检验结果报告程序。监督现场质量的控制工作,以确保现场的工作符合标准、规范的要求。参加有关质量控制会议。向现场负责人汇报相关范围内的工作情况。 (6)材料员:负责组织编制材料领取计划,并送交现场负责人审批。负责领取材料的保管、贮存和签发工作,并按施工计划及时组织到施工现场,包括相应的装卸、运输等。提供所购材料必要的、符合档案管理要求的证明材料,如质保书、合格证、试验报告、使用手册等。负责现场材料、设备的保管、贮存和签发。 2.2材料准备

厂区室外地埋管道安装施工方案

目录 1 工程概况及工程量 2 编制依据 3 施工准备及作业条件 4 施工方法及工艺要求 5 质量标准及要求 6 职业健康安全与环境保证措施及文明施工要求 7 附录

1、工程概况及工程量 工程概况 山西临县低热值煤2×350MW超临界发电机组新建工程厂址位于山西省吕梁市临县城庄镇境内。临县位于山西省中西部,地势北高南低,东高西低,海拔高度在~。本期工程建设规模为700MW,拟安装2×350MW超临界循环流化床空冷机组,建设场地留有扩建条件,由山西京能吕临发电有限公司负责建设、运营和管理。江西省火电建设公司承建的B标段主要工程范围为2#机组及水工、化水系统建筑安装工程。 地质情况 厂址所在区域地貌单元属中低山区的黄土丘陵区,黄土冲沟发育,地形较破碎,本区域地面标高一般为~。厂址处于黄土丘陵区中的河谷地带,地处湫水河支流的Ⅰ~Ⅱ阶地,岩土层上部以第四系全新统冲洪积的黄土状粉土、卵石、砂层为主,厚度~;下部以中更新统粉质粘土夹姜结石透镜体为主,下伏三叠系中下统砂页岩及石炭-二叠系煤系地层。城庄沟右岸河滩原为古河道,经上世纪七十年代前后改河造地,场地土类型为中硬场地土,场地类别为Ⅱ类;地下水类型为松散层孔隙潜水和基岩裂隙水,厂址的松散层孔隙水水位一般3~5m,由于下层粘性土的隔水作用,该浅层地下水为区域性的上层滞水,季节性变幅1~2m。 工程量 主要工程量

2、编写依据 山西临县低热值煤2×350MW超临界发电机组新建工程勘测结果 华北电力设计院地埋部分管道安装图 《工程建设施工企业质量管理规范》GB/T 50430-2007 《电力建设施工技术规范第 5 部分:管道及系统》DL —2012 《电力建设施工质量验收及评价规程第5部分:管道及系统》DL/T —2009《焊接工艺评定规程》DL/T 868—2004 《火力发电厂焊接技术规程》DL/T 869—2012 《电力建设施工质量验收及评价规程第7部分:焊接》DL/T —2014 《火力发电厂工程测量技术规程》DL/T 5001-2004 《起重机械安全规程第 1 部分:总则》GB -2010 《建筑工程质量验收统一标准》GB50300-2001 《建筑防腐蚀工程施工及验收规范》GB 50212-2002 《电力建设安全工作规程第一部分:火力发电厂》DL 《电力建设安全施工管理规定》电建[1995]671号 《施工工艺纪律》(第三版)江西省火电建设公司 《给水排水管道工程施工及验收规范》GB50268-2008 《建筑施工土石方工程安全技术规范》JGJ180-2009

厂区室外管道施工方案

一、工程概况及编制依据 1.工程概况: 神华国能哈密煤电有限公司4×660MW机组新建工程。位于哈密大南湖煤矿北邻约一公里处。新建工程为4台机组,本方案为3#机组厂区给排水管道安装工程使用。(本工程施工以设计院设计图纸为施工技术依据,以本作业指导书中内容及其中所涉及相关的国家标准、规范,用于指导该项施工的全过程)。 1.2 工程量和工期 1.2.1 工程量 1.2.2 施工工期 计划施工日期为2013年09月01日至2014年07月 2. 编制依据

2.1、《厂区室外给排水管道安装图》 2.2、《电力建设施工质量验收及评定规程》DL/T5210.1-2012 2.3、《建筑给水排水及采暖工程施工质量验收规范》(GB 50242-2002) 2.4、《建筑防腐蚀施工及验收规范》(GB 50212-2002) 2.5、《建筑防腐蚀施工质量验收规范》(GB 50224-2010)《电力建设施工质量验收及评价规程第1部分:土建工程》(DL/T5210.1-2012) 2.6、《电力建设施工质量验收及评价规程第一部分:土建工程》(DL/T5210.1-2012)第5章、第19章;《砌体结构工程施工质量验收规范》(GB50203-2011) 2.7、《混凝土和钢筋混凝土排水管》GB11836-99 2.8、《电力建设安全工作规程第1部分:火力发电厂》(DL50009.1-2002) 2.9《砌体工程施工质量验收规范》(GB 50203-2011) 2.10《建筑地基基础工程施工质量验收规范》(GB 50202-2002) 2.11《给水排水标准图集》05S5182、《给水排水标准图集》02S403 2.13、《给水排水标准图集》02S701、《给水排水标准图集》03S401 2.15、《给水排水标准图集》04S516、《给水排水标准图集》01S502 2.17、《给水排水标准图集》04S519 、2.18、电力建设安全健康与环境管理工作规定 二、施工准备 1、技术准备: 现场技术人员应先熟悉图纸,进行图纸会审,根据图纸结合现场实际情况编写详细的、切实可行的施工方案,然后逐级进行技术交底、安全交底,并组织施工班组开会进行技术交底,并全员签字,使交底工作真正落实到实处。 2、现场准备:施工各级人员紧密配合主体施工进度。 3、各种机具准备到位,施工各个工种人员配备齐全。

(完整版)地下的管道施工方案设计

1、工程概述 1.1本方案为项目地下管道施工方案。整个项目各专业工程密集交叉进行, 为确保地下管道施工质量、进度及安全,特编制本施工方案。 1.2工程特点 本工程与土建、地上安装交叉作业密集,大口径管道较多,防腐要求严格,工程量大,工期紧。 1.3主要工程量 主要工程量汇总表1.3 1.4编制依据 1.4.1地下管道施工图纸; 1.4.2《石油化工给水排水管道工程施工及验收规范》(SH3533-2003 ; 1.4.3《石油化工设备和管道涂料防腐技术规范》(SH3022-2008。 2、施工工序 本工程施工工序按图2.1进行。

3、施工准备 3.1熟悉图纸,做好设计图纸会审,编制施工方案,组织施工人员进行技术交底培训; 3.2认真学习施工规范,施工人员要掌握设计规定的有关规范和技术要求; 3.3根据现场实际情况,做好人、机、材的进场工作安排,对所有入场机具进行检查并维修,确保机具能正常使用且全部到位; 3.4所有入厂施工人员必须接受安全教育,特殊工种必须持有效证件上岗; 3.5管道试压用水排放要符合环境、卫生要求,按业主指定点排放; 图2.1 地下管道施工工序图 3.6施工用电严格服从业主用电管理制度,配电柜要符合用电安全技术规范要求,必须一机一闸一保护,确保用电安全。 4、材料检验 4.1材料检验的一般规定 4.1.1管道组成件(管子、管件、法兰、垫片、紧固件、阀门、防腐保温材料等)必须

具有制造厂的质量证明书,其材质、规格、型号应符合设计文件 的规定,并应按国家现行标准100%进行外观检查,不合格者不得使用; 4.1.2焊接材料必须有质量证明书; 4.1.3法兰和盲板的密封面应平整光洁,不得有毛刺及径向沟槽; 4.1.4螺栓、螺母的螺纹应完整,无伤痕、毛刺等缺陷,螺纹应配合良好。 4.2钢管检验 4.2.1无裂纹、缩孔、夹渣、折迭、重皮等缺陷,锈蚀、机械损伤等缺陷不超过壁厚负 偏差; 4.2.2钢板卷管周长及圆度允许偏差,应符合表 4.2.2的规定; 钢板卷管周长及圆度允许偏差(mm 表4.2.2 4.2.3钢管卷管的端面与轴线垂直度允许偏差,应为管外径的1%且不大于3mr p 直线度允许偏差为1mm/m 4.3阀门检验 4.3.1阀门外观检查,其零部件应齐全完好,填料压盖螺栓应留有压缩裕量。传动装置 和操作机构应动作灵活、可靠、无卡涩。 4.3.2至惯阀门应从每批(同制造厂、同规格、同型号)中抽查10%且不小于 一个,进行壳体压力试验和密封试验,若有不合格再抽查20%如仍有不 合格则应逐个试验; 4.3.3阀门的壳体试验压力为阀门公称压力的 1.5倍,达到试验压力后,保压 时间5分钟,以阀体材料无渗漏为合格;密封试验压力为阀门的公称压力,以阀瓣密封不漏为合格; 4.3.4试验合格的阀门,必须及时排尽内部积水,关闭阀门,封闭出入口,做出合格标 记; 4.3.5公称压力小于1Mpa且公称直径大于或等于600mm勺闸阀和蝶阀,当制造厂有 压力和密封试验证明时,可不单独进行压力试验和阀板密封试验,宜采用色印等

脱硫塔内壁玻璃鳞片内防腐工程施工方案

第四章分部分项主要施工方法 第一节基本要求 1、经会审和批准的设计文件和施工图纸齐备,施工人员熟悉各有关图纸资料,了解整个工程的施工方案、工艺要求、质量标准。 2、施工所需的设备、仪器、工具、部件、材料等应提前准备就绪,施工现场有障碍物时应提前清除。 第二节施工开展程序 本工程为防腐工程,主要采用人工、机械施工、人工配合的施工方法。因为当地天气等特殊情况,考虑到工期和进度,我们将针对实际施工面积合理调配机具。在甲方规定工作日内彻底施工完毕。 第三节施工工艺流程 确保工程施工保质、有序的进行,工程按期竣工,对作业流程要严格控制。并制定相应的质量保证措施和安全措施。 在施工过程中,施工方法的选择很重要。首先必须严格按图施工,同时还必须以现场实际情况作为作业指导。对施工班组、人员进行科学合理的任务分配,详细的技术交底。层层落实责任,各班组严格控制施工质量和工程进度,上道工序没达到要求的情况下不得进行下道工序的施工。 第四节施工机械设备情况说明 4.1、拟投入主要施工设备表

4.2、拟配备试验和检测仪器设备表 第五节除锈方案 5.1 喷砂除锈 各种喷砂设施、材料准备就续后,启动空气压缩机用干燥洁净白布, 测试喷嘴及压缩空气气流,确认无油污、无水份后开始喷砂除锈。 5.2 喷砂操作工艺 在开车前先装满下室的砂,然后开压缩机,打开阀站(5)利用压缩空气顶住活门(2),这时即可打开阀门(4)和旋塞(3),开始喷砂操作。同时装上室的砂。待下室的砂即将用完进即进行加砂,打开阀门(6),利用压缩空气顶住活门(1 )。同时上室内压力迅速增加。到上下室外压力相等时,上室的砂因自重压开

厂区室外污水、雨水管道施工方案

施工方案 第一节工程概况 本工程位山西新华化工有限责任公司综合技术改造项目厂区生活污水、雨水管道改造工程,施工内容为厂区内的污水、雨水管道改造,材料选用HDPE高密度聚乙烯双壁波纹管、De300MM及以上钢带增强聚乙烯双壁波纹管采用电热熔带加热熔挤出焊接组合方式,De300mm以下双壁波纹管采用橡胶密封圈承接连接。 管道基础为原土夯实,管底铺中细砂100mm,腋角部分及管顶200mm以下铺中细砂,从管底基础至管顶以上0.7m范围内,必须用人工回填,严禁用机械推土回填。 第二节施工要求 一技术要求 1、开工前由项目经理部对施工班组作好各级技 术准备和技术交底工作并做好记录,施工员、测量工 要熟悉图纸,领会施工方案的作业要求,建立现场水 准测量网。 2、专职测量工要配合施工员进行质量控制,要 及时复撒灰线,及时控制开挖标高。

3、施工员、测量工换班时,要认真进行书面交 接,确保开挖质量。 4、防陷措施,开挖施工中应采取防陷措施。当 遇软弱基础时,应铺垫30~50cm厚碎石垫层。 5、基坑开挖时,应做好坑外排水工作,避免雨 水流入基坑。基坑顶做出排水坡度,以防雨水流入基 坑。 6、冬季施工 二、安全要求 开工前要做好各级安全教育和安全交底工作,制定切实可行的安全和文明施工责任制,组织所有施工 人员施工前安全知识培训,土方外运时,为了确保安 全,在出入口处应设安全岗,配备专人指挥车辆。车 辆必须经冲洗干净才准许放行,为解决施工人员上、 下基坑,应用?48钢管搭设靠梯,梯宽700mm,靠梯 两侧设置900mm高扶手栏杆。夜间应用红色安全灯. 第二节施工准备 一准备工作 1 施工全过程要做到“六落实”即施工负责人、施工员、质量员“三位一体”人员落实;施工方案、施工技术

供热管道施工方案

热 力 管 道 维 修 施 工 方 案 编制人: 审核人: 批准人: 目录第一章工程概况及施工部署 第一节工程概况 第二章施工准备 第一节现场准备 第二节临时设施准备 第三章施工方案及主要施工方法 第一节开挖沟槽 第二节管道安装 第三节管道接口

第四节水压试验 第四章确保安全、文明施工的技术措施 第一节安全管理措施 第二节安全技术措施 第三节文明施工的技术措施 第一章工程概况 工程概况 热力管道维修安装、管网改造总长度为双向(45)米,管径从Φ50*6,管道采用地沟式敷设。 总工期:7天,计划开工日期:年月日,计划竣工日期:年月日质量要求:管道外表面做除锈后聚胺酯发泡,外表面为聚乙烯外皮。管材要求:管道为无缝钢管。 第二章施工准备 第一节现场准备 1、做好施工现场的“三通一平”,施工场地应按拉坡方式进行平 整,形成内高外低,防止雨水倒灌。 2、设置一预制场地,将工程所需预制构件集中预制,集中供应, 便于控制构件质量和便于操作。 3、做好现场临时设施和办公场所的搭建,根据施工现场实际情况 进行合理的施工平面布置。 第二节临时设施准备 一、临时供电

1、概述 现场临时供电按《工业与民用供电系统设计规范》和《施工现场临时用电安全技术规程》设计并组织施工,供配电系统采用TN-S按零保护系统,按三级配电,两级保护设计施工,PE线与N线严格分开使用,接地电阻不大于4欧姆,施工现场所有防雷装置冲击接地电阻不大于30欧姆,开关箱内漏电保护器额定漏电动作电流不大于30毫安,额定漏电动作时间不大于秒。 2、用电线路接入施工现场,用电从建设单位提供的变压器接入,施工现场、电缆统一入闸箱,再接分箱供各专业施工用电,以保证供电安全,干线电缆选用XV型橡皮绝缘电缆。施工配电箱采用统一制作的标准铁质电箱,箱、电缆编号与供电回路对应。 二、临时用水 施工现场用水从沿线相关单位自来水引入点接入。现场用水主要为生活用水、施工用水、消防用水,引入一路Φ25水管,供施工现场及生活区使用。 第三章施工方案及主要施工方法 第一节开挖沟槽 (一)、开挖 1、施工准备: (1)、土方开挖前,根据设计和施工技术规范要求,凡在施工区影响工程质量的软弱土质、淤泥、腐殖土、垃圾、废弃的回 填土及地下、地上障碍物,应全部清除和处理完毕。

地下管线保护专项施工方案

浙建监A2 地下管线保护专项施工方案报审表 工程名称:104国道(瓯海段)拓宽工程一期投资施工一体化项目编号:A2

本表一式三份,经项目监理机构审核后,建设单位、监理单位、承包单位各存一份。 104国道(瓯海段)拓宽工程一期投资施工一体化项目

编制人: 审核人: 审批人: 温州市兴海市政建设有限公司 二0一四年八月十日 目录 一、工程概况1 二、施工区域原有管线的保护处理程序1 三、地下管线处理前的准备工作1 1、收集地下管线资料1 2、实地勘踏2 四、各类管线防护措施2 1.探沟开挖2 2、管线开挖3

3、管线保护方法3 4、管线事故的处理3 五、管线保护责任制5

地下管线保护方案 一、工程概况 工程名称:104国道(瓯海段)拓宽工程一期 工程地点:瓯海大道——南白象加油站 合同工期:18个月 工程内容:道路、桥梁、给排水管道、电力管沟、路灯、交通设施、绿化工程等。 建设单位:温州市瓯海区广化路和双南线道路建设办公室 设计单位:武汉市政工程设计研究院有限责任公司、温州市城建设计院 监理单位:浙江明康工程咨询有限公司 本工程由于道路管线交错复杂,老路东侧移动管线、电信管线、架空管线、军用光缆、DN600给水总管、雨水管道、污水管道,老路西侧有联通管线、铁通管线、网通管线、中广有线电视、架空管线、军用光缆、雨水管道、污水管道等众多地下管线。施工前,进一步探明管线具体布局,做好现有管线的防护工作尤为重要。因此,经项目部各部门研究制定本管线保护方案。 二、施工区域原有管线的保护处理程序 收集管线资料实地勘踏开挖探沟情况报告人工开挖保护 三、地下管线处理前的准备工作 1、收集地下管线资料 向业主及监理单位的相关人员仔细咨询了解施工区域内的地下管 线的种类、用途、数量、走向、埋置深度,地上架空电线杆位置、数量、埋置深度等。并请业主提供相关的图纸资料,以此作为制定地下管线防护措施的依据。

水处理池内壁防腐工程施工方案

×××污水处理厂水处理工程 水处理池内壁防腐工程 施工方案 工程名称:污水四期扩建项目中水池内壁防腐工程建设单位:××× 施工单位:××× 编制人: 编制日期:2018年5月12日

1、工程概况 1.1设备名称: (1)污水四期扩建项目中脱硫水调节池、离交水调节池,离子水调节池 (2)高浓调节池及配水井的内部防腐 1.2工艺参数 (1)操作温度:常温 (2)操作压力:常压 (3)介质:弱配 1.3施工范围及衬里技术要求: 总面积:2200平方米 环氧树脂防腐(5布7油)环氧胶泥打底 防腐设施名称与规格 1.4工期要求: 1.5质量要求:优良。 2、编制依据及原则 2.1编制依据 2.1.1《工业建筑防腐蚀设计规范》GB50046-2008; 2.1.2《建筑防腐蚀T程施T及验收规范》GB50212-2014; 2.1.3《手糊法玻璃钢设计技术条件> CD130A19-85; 2.1.4《玻璃钢化工设备设计规范》HG/T20696-1999。 2.1.5《砖板衬里化上设备> HGT 20676-1990。 2.1.6 《×××污水处理厂四期扩建防腐工程招标文件》 2.1.7涂料的性能指标符含GD-CS-YB-SPE-014《站内露空管道及设备外防腐技术规格书》 2.1.8外观应均匀、无气泡、无裂痕等缺陷。涂层针孔检测应执行SY/T0063《管道防腐层检测试验方法标准》 2.2编制原则 2.2.1采用较为先进的设备、机械、用具。

2.2.2建立科学合理有效的施工管理机制,精选具有丰富的施工经验的管理人员参与该项工程的各项施工管理工作。 2.2.3对各项施工工艺、施工工序都严格按照国家的标准、规范进行。 2.2.4建市全面、规范、标准的施T质量保证体系、HSE保证体系及工期保证体系。 2.2.5配置全面、完善、科学的物资采购机构、机械设备管理机构。 2.2.6所有参与施工的技术人员均有3年以上的施工经验。 3、施工现场组织机构 4、施工准备 做好防腐施工前的准备是整个工程的主要内容之一,是施工生产中的一个重要阶段,也是关系整个工程能否顺利地连续施工,保证工程质量和施工经济效益的重要前提。施工准备范围可分为阶段性施工准备和作业性施工准备两个方面,而施工技术准备是在施工准备全过程中。 4.1技术准备 4.1.1防腐工程施工,要具有齐全的施工方案和设计文件。 4.1.2提出明确的防腐蚀施工技术说明,对原材料、半成品、成品提出明确的技术规范和标准。 4.1.3施工单位要结合工程情况,提出施工方案和技术交底,并应具有书面资料。

厂区采暖管道施工方案

1.工程概况及特点 工程概况 采暖管道供回水温度为(110-70℃),工作压力,热源接自主厂房采暖供热站。 本工程采取分区域施工,并行管道同沟一次开挖先深后浅施工,避免重复开挖作业。 工程特点 1.2.1使用大型施工机械较多,施工面积大,施工难度较大。 .⒉系统复杂,管径大材料运输及安装较困难。 1.2.3各个系统与土建施工配合多,施工周期紧。 1.2.4系统较复杂,需分段进行水压试验。 2.编制依据 《电力建设施工质量验收及评定规程》第1部分:土建工程 《电力建设安全工作规程》 《建筑给水排水及采暖工程施工质量验收规范》GB50242-2002 工程建设标准强制性条文(房屋建筑工程部分)(2009)版

绿色施工导则建质[2007]223号 北京电力建设公司编制的《河北建投沙河电厂2×600MW空冷机组C标段建筑施工组织设计》 北京电力建设公司质量体系文件 各系统施工图纸。 3.施工应具备的条件 设计图纸已具备,并经过图纸会检和设计交底,施工方案已经编制并审批通过。施工技术人员向班组作了图纸和施工技术交底,填写了施工技术交底记录。 材料供应及时准确到位,规格品种应符合设计要求,并具有出厂合格证,施工力量,机具等能保证正常施工。 室外管线施工的场地已具备施工条件。 对所有施工人员进行三级安全教育,特殊工种培训合格,持证上岗。 施工临时用水、电设施已具备,涉及冬、雨季施工保护措施已完善。 4.施工主要机械及材料准备 主要施工机械需用计划表(表1)

施工主要材料需用计划表及要求 4.2.1施工材料要求 4.2.1.1所有材料及设备进场时,必须经过施工技术人员、质量员检验并报监理、业主许可后方可使用。

2021年地下管线保护专项施工方案

GDAQ21101 欧阳光明(2021.03.07) 地下管线保护专项施工方案 工程名称:************************工程 编制人: 审核人: 审批人: 总承包单位:*******有限公司 年月日 目录 一、编制依据及原则 (3) 二、工程概况 (3) 三、管线保护原则 (4) 四、组织程序 (4) 五、组织措施 (4) 六、施工措施 (5) 七、应急处置措施 (6) 八、地下管线保护目标 (6) 九、地下管线保护责任制 (6) 十、调查分析 (6)

十一、保护措施 (7) 十二、交通配合组织方案 (9) 十三、应急预案 (9) 十四、附件 (10) 1、应急小组人员及联系电话 (11) 2、应急处置工作相关联系电话 (11) 一、编制依据及原则 (1)编制依据 1.根据********工程设计图纸; 2.我施工单位现有的施工技术、施工管理和机械设备配备能力; 3.《**市地下管线管理办法》。 (2)编制原则 1.在熟悉施工设计图纸、场地水文地质情况及施工现场管线调查的基础上采用先进、合理、经济、可行的施工保护方案; 2.施工进度、劳力资源等安排均衡、高效; 3.严格贯彻“安全第一”的原则; 4.保护环境、保护文物,文明施工。 二、工程概况 ************************************。 三、管线保护原则 所有管线尽量就地保护,能不迁移的尽量不动。对必须迁移的管线,应编制详实可行的施工方案,并征得管线主管部门的同意后,方可进行。 四、组织程序

向地方相关部门、业主、监理单位的相关人员仔细咨询了解施工区域内的地下管线的种类、用途、数量、走向、埋置深度等。如有可能,请他们提供相应的图纸资料,以此作为制定地下管线处理方案的依据。工程开工前,先会同管网埋设、管理部门进行确认,必要时进行试挖确认,并在上面作好标记,以便施工时确定保护措施。施工进场后,还须与有关管理部门协商、研究,进一步摸清地下管线的情况,做好管线位置标志,并刨验以确定其准确位置。在此基础上,与有关部门研究制定更为具体、完善、切实可行的改移及防护措施。 五、组织措施 (1)项目部设专人负责地下管线调查及保护事宜,采取走访所有管线单位,委托专业物探单位探测地下管线,开工动土前,对动土位置开设样洞,摸清地下管线的全部走向,设立管线档案,并在所有施工图上用红线标明。 (2)施工中发现不明管线应及时报告相关单位,并会同相关管线单位专业人员实地鉴定确定相关施工方法和处理办法,不准擅自处理。 (3)施工过程中若发现管线有异常现象或管位有差异可能对地下管线的安全和维修产生影响时,应立即停止施工,同时与相关管线单位联系,落实保护管线的安全措施后方可连续施工。 (4)探沟开挖 ①探沟开挖必须采用人工探挖,探挖为十字形,探挖深度为2m,宽0.8m,用铁锨轻轻挖掘,不得用镐。开挖时重点放在燃气管线、电缆井、过路保护管、过路盖板、用电设施、给水管线附近。发现土质发生变化时应改用木钎将覆盖物清除干净,以保证不损坏地下管线。

管道内防腐施工方案

输气管道内防腐(机械施工) 施 工 组 织 方 案 河南蓝天防腐安装有限公司 2014年3月

目录 1、工程概况 2、编制依据 3、准备工作 4、涂料 5、管段、管件工厂预制 6、施工质量检验 7、施工条件 8、质量保证体系 9、安全文明施工保证体系 10、项目施工管理网络 11、施工计划进度 附件1:管道内防腐施工总体工艺流程 附件2:管段、管件工厂预制施工平面布置附件3:设备机具及检测仪器

抽油管道内防腐施工组织设计 1、工程概况 本施工方案仅适用于抽油管道内防腐工程。 根据设计及规范要求,管道内防腐采取如下工艺:内壁表面处理采取喷砂除锈方式,除锈等级达到Sa2.5级,油漆设计采用环氧树脂涂料,施工方式为离心喷涂,二层环氧树脂底漆,二层氟碳漆面漆,厚度要求:单层漆膜干膜厚度30-40μm,四层干膜总厚度120-160μm。 2、编制依据 1、现行的施工及验收规范、质量检验标准 A. GB8923-88 《涂装前钢材表面锈蚀等级和除锈等级》 B. SH3022-1999 《石油化工设备和管道涂料防腐蚀技术规范》 C. HGJ229-91 《工业设备、管道防腐蚀工程施工及验收规范》 D. SY/T 5308-87 《石油钻采机械产品用涂漆通用技术条件》 2、我公司长期承建防腐工程施工的成功经验。 3、准备工作 3.1组织工程技术人员熟悉设计要求及施工技术规范,编制作业指导书; 3.2对施工人员进行安全技术交底及培训; 3.3设备机具进场安装、调试至运转正常; 3.4根据设计要求,原材料采购到位,如有必要须抽查复检合格。 4、涂料 管道内壁防腐采用环氧涂料,双组份,严格按照厂家产品使用说明书进行配料及使用,甲乙组份须混合均匀,充分搅拌,熟化10-30分钟再进行施工,必须在规定混合时效内用完,根据实际用量配料,一次不应多配,在使用过程中发现漆料开始变稠胶凝则不可再用,亦不可稀释再用,须重新配制新料。 5、管段、管件工厂预制 5.1表面处理

厂区室外雨水排水管道安装施工方案概论

华润雪花啤酒《辽阳》有限公司 厂 区 雨 污 分 离 工 程 施 工 方 案 盘锦晨宇建安有限公司 2015年8月5日

目录 一、工程概况 (3) 二、编制依据 (4) 三、施工劳动力组织及机具 (4) 四、主要施工方法及措施 (4) 五、质量保证措施 (8) 六、安全施工保证措施 (9) 七、季节性施工措施 (11) 八、附表:危害辨识及危险性评价 (14) 九、高温季节(防暑)施工应急预案 (15)

厂区雨(污)水室外排水管道安装 施工方案 一、工程概况 本工程为华润雪花啤酒(辽阳)有限公司;厂区室外雨水排水管道安装工程。 主要技术交底:生活污水及生产污水排至污水提升站,清洁雨水排至站外市政管网。生产、生活污水排水管采用¢300、24m;承插混凝土排水管(Ⅱ级)管道采用承插连接,配套专用橡胶圈,雨水排水管采用DN300管道约355米,DN500管道约146米,下做200mm厚砂石垫层基础;雨水管道均采用承插混凝土排水管(Ⅱ级),胶圈接口,基础做法同06S516;基础采用120°混凝土基础;雨水管径小于等于DN300的雨水支管,采用?1000mm圆形砖砌雨水检查井,见02S515-12;雨水管径大于DN500的雨水支管,采用?1250mm圆形砖砌雨水检查井,见02S515-15;雨水管径大于等于DN1000的雨水干管,当支管小于等于DN400时,直线采用矩形直线混凝土检查井,见02S515-33,90°转弯采用扇形混凝土检查井(90°),见02S515-60;雨水管管径大于等于DN1000的雨水干管,当支管等于DN600时,采用矩形90三通混凝土检查井,见02S55-35;水封井ZS5-ZS13做法参见02S515-25。 排水井一览表:

厂区采暖管道施工方案

动力管道施工专项方案 1.工程概况及特点 1、工程名称 中船重工邯郸高新技术产业基地汉光光电科技园项目—动力管道。 2、建设地点 邯郸市经济开发区,和谐大街与新兴路交叉口东北角,中船重工邯郸高新技术产业基地汉光光电科技园院内。 3、采暖管道供回水温度为(95/70℃),工作压力0.8MPa,热源接自主厂区锅炉房。本工程采取分区域施工,并行管道同沟一次开挖先深后浅施工,避免重复开挖作业。 4、工程特点 4.1使用大型施工机械较多,施工面积大,施工难度较大。 4.⒉系统复杂,管径大材料运输及安装较困难。 4.3管道与其他管道交叉点多,施工难度大。 4.4系统较复杂,需分段进行水压试验。 2.编制依据 2.1《城镇供热直埋热水管道技术规程》(CJJ/T81-2013) 2.2《城镇供热直埋蒸汽管道技术规程》(CJJ104-2005) 2.3《建筑给水排水及采暖工程施工质量验收规范》(GB50268-2008) 2.4厂区采暖管道设计图纸。 3.施工应具备的条件 3.1设计图纸已具备,并经过图纸会审和设计交底。 3.2施工技术人员要向班组作图纸和施工技术交底。

3.3材料供应及时准确到位,规格品种应符合设计要求,并具有出厂合格证,施工力量,机具等能保证正常施工。 3.4室外管线施工的场地已具备施工条件。 3.5对所有施工人员进行三级安全教育,特殊工种培训合格,持证上岗。 3.6施工临时用水、电设施已具备使用条件。 4.施工主要机械及材料准备 4.1主要施工机械需用计划表(表1) 4.2施工主要材料需用计划表及要求 4.2.1施工材料要求 4.2.1.1所有材料进场时,必须经过施工技术人员、质量员检验并报监理认可后方可使用。 4.2.1.2所有材料及设备必须具有出厂合格证明,检测报告,规格、型号符合要求。 4.2.1.3压力设备必须具有专业部门提供的各种检测资料及厂家压力设备生产许可证。 5.主要施工方法及步骤 5.1工艺流程: 安装准备(材料准备)→测量放线、管沟开挖及验槽→基础(垫层)施工→管道布管及下

明挖管道施工方案

第一章工程概况 概述:道路场地位于都江堰市经济开发区,北起成灌铁路,南至都汶高速,范围为都江堰都紫荆城2号路2号道路工程,设计起点00+00,设计终点9+05.236,起点接紫荆城1号路,全线总长905.236m。雨水管管径为d500~800,长度约为900m,污水主管管径为d400、d600,长度约为900m,雨水、污水管道坡度均为0.3% 第二章施工准备 2.1准备工作 ①施工全过程做到“六落实”即施工负责人、施工员、质安员“三位一体”人员落实;施工方案、施工技术措施落实;施工机械设备、检测手段落实。对现场有关管理人员、班组长、操作人员的技术交底及施工规范、质量验收标准交底落实,各级人员的岗位职责落实,安全质量奖惩制度落实。 ②在开工之前,我们将查明施工区域内原有地下管线的埋设情况,并以书面报告的形式提出具体的解决办法,报请监理工程师批准后方可开工。对管道施工所经路线的障碍物进行初步清除,为以后的测量放线定位工序提供较好施工条件。 2.2测量放样 进行施工放样测量前测量人员先校核施工图纸,按施工图纸提供的排水工程的位置和标高,定出沟槽中线及井位并引出水准基准点,作为整个排水工程的控制点。每次测量均要闭合,按规范严格控制闭合误差。测量管沟中心轴线、标高;并放出管沟基槽边线,在边线设置小木桩。沟渠放线,每隔20m设中心桩,必要时设置控制桩。沟槽放线抄平后,应绘制沟槽纵断面图。沟槽测量工作应有正规的测量记录本,认真详细记录,必要时应附示意图,并应将测量的日期、工作地点、工作内容以及公司镜、记录、对点、拉练、扶尺等参加测量人员的姓名记录,测量放样记录以书面形式上报监理工程师,

厂区室外管道施工方案

厂区室外管道施工 方案 1

一、工程概况及编制依据 1.工程概况: 神华国能哈密煤电有限公司4×660MW机组新建工程。位于哈密大南湖煤矿北邻约一公里处。新建工程为4台机组,本方案为3#机组厂区给排水管道安装工程使用。(本工程施工以设计院设计图纸为施工技术依据,以本作业指导书中内容及其中所涉及相关的国家标准、规范,用于指导该项施工的全过程)。 1.2 工程量和工期 1.2.1 工程量 1.2.2 施工工期 计划施工日期为 09月01日至 07月 2. 编制依据 2.1、《厂区室外给排水管道安装图》 2.2、《电力建设施工质量验收及评定规程》DL/T5210.1-

2.3、《建筑给水排水及采暖工程施工质量验收规范》(GB 50242- ) 2.4、《建筑防腐蚀施工及验收规范》(GB 50212- ) 2.5、《建筑防腐蚀施工质量验收规范》(GB 50224- )《电力建设施工质量验收及评价规程第1部分:土建工程》(DL/T5210.1- ) 2.6、《电力建设施工质量验收及评价规程第一部分:土建工程》(DL/T5210.1- )第5章、第19章;《砌体结构工程施工质量验收规范》(GB50203- ) 2.7、《混凝土和钢筋混凝土排水管》GB11836-99 2.8、《电力建设安全工作规程第1部分:火力发电厂》(DL50009.1- ) 2.9《砌体工程施工质量验收规范》(GB 50203- ) 2.10《建筑地基基础工程施工质量验收规范》(GB 50202- ) 2.11《给水排水标准图集》05S5182、《给水排水标准图集》02S403 2.13、《给水排水标准图集》02S701、《给水排水标准图集》03S401 2.15、《给水排水标准图集》04S516、《给水排水标准图集》01S502 2.17、《给水排水标准图集》04S519 、2.18、电力建设安全健康与环境管理工作规定 二、施工准备 1、技术准备: 现场技术人员应先熟悉图纸,进行图纸会审,根据图纸结合现场实际情况编写详细的、切实可行的施工方案,然后逐级进行技术交底、安全交底,并组织施工班组开会进行技术交底,并全员签字,使交底工作真正落实到实处。 2、现场准备:施工各级人员紧密配合主体施工进度。

架空供热管道施工方案

架空供热管道施工方案 一、施工准备 (一)、技术准备 1、施工人员已熟悉掌握图纸,熟悉相关国家或行业验收规范和标准图等。 2、已有经过审批的施工组织设计施工方案,并向施工人员进行交底。 3、技术人员应向班组进行技术交底、质量安全交底,使施工人员掌握操作工艺。 (二)、材料准备 1、管材:管材应有产品合格证,管材不得弯曲、无锈蚀、无飞刺、重皮及凹凸不平等缺陷。 2、管件符合现行标准,有出厂合格证,无偏扣、乱扣、方扣、断丝和角度不准等缺陷。 3、各类阀门有出厂合格证,规格、型号、强度和严密性试验符合设计要求。丝扣无损伤,铸造无毛刺、无裂纹,开关灵活严密,手轮无损伤。 4、附属装置:减压阀、疏水器、过滤器、补偿器、法兰等应符合设计要求,应有产品合格证及说明书。 5、型钢、圆钢、管卡、螺栓、螺母、油、麻、垫、电焊条等符合设计要求。 (三)、机具、工具 1、主要机具

序号机具名称常用规格型号备注l 砂轮机JJK-1T、JJK-5T 2 角向磨光机S1MJ-100、S1MJ-125 3 电焊机BXl-300~500、BS-330 4 液压弯管机YW-2A、LWGl-10B 5 套丝机DNl5—80 6 切割机J3D-400 7 吊车8、16t 8 钢丝绳Ф8~20 9 滑轮3T、5T 10 电动试压泵Dsx-60 1l 经纬仪J2 12 水准仪DSZl0 序号工具名称常用规格型号备注1 套丝扳DNl5~80

1、施工所需临时设施及“三通一平”已经解决,现场各种预制场地已经落实。离现场较近,运输方便;在雨季不会积水。 2、管道、管件及阀门均已检验合格,具有技术资料,并与设计核对正确无误。

穿越地下管线、电缆施工方案

西气东输淮武支线管道工程第三标段线路工程 地下管线、光(电)穿越施工方案 编制: 审核: 审批: 中国石油天然气管道局西气东输淮武支线第三标段项目部 编制日期:2005年11月25日 一、编制依据

1.1 《西气东输管道工程线路施工及验收规范》Q/SY XQ2001-2001; 1.2 其它相关标准、规范。 二、一般技术技术要求 2.1 新建管道从电(光)缆及管道下方通过。 2.2 新建管道管顶与电(光)缆间的距离≥500mm。 2.3 新建管道与已建管道的间距应≥300mm。 2.4 电(光)缆用角钢保护。 2.5 电(光)缆上方300mm处铺红砖层保护电缆。 三、施工准备 3.1 在施工前对设计确定的地下障碍物,首先派专人复核(也可询问附近的村民或其它人员),确认无误后,对实际位置然后做好点示记,将障碍物的类型、深度、走向详细记录; 3.2 对没有确定的地下障碍物,可采取向当地有关部门多方询问的方法来给予确认,或争取到当地的地下障碍物分布图,将其反映到管线施工图上,最终落实到现场。。 3.3 在施工前(布管前),采用人工挖掘的方法将地下障碍物暴露出来,专人看护,特殊情况如光缆、通信线路等要及时通知主管部门现场监护。暴露出来的障碍物要采取必要的保护措施,如采取钢管做横担将光缆、电缆等吊起,在四周设置警示带,注明“通信光缆、严禁割断”等字样; 3.4 穿越段的预制:在主体管道组装焊接的同时将穿电缆等设施的管道预制出来,一般情况下预制管道长度比电缆与新建管道交叉段长20m。其施工方法与检验标准均与主体管道相同。 四、施工技术措施 4.1 开挖管沟 4.1.1 电(光)缆及管道周围3m以内管沟开挖 管沟开挖前应聘请地下设施的主管部门到现场监督指导施工,采用人工开挖,首先根据探测出的电缆位置,在其垂直方向挖长槽探沟,探沟为2×0.5m,用铁锨挖土,用平铲法挖土,边挖边清理散土,挖沟人员要时刻注意土层的变化,如果在坚硬的土层中出现软土或沙土层,很可能就是电缆(光缆)周围的软土层,挖土时就要格外的小心,一点一点地挖土,将电缆(光缆)周围3m之内的管沟全部挖出。

相关文档
最新文档