力学英文翻译

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

Tunnels , Galleries and Cavities

Predicting geologic formations and the hydrogeology to be encountered along a tunnel is the major task of the geologist.

(1)Lotschberg ( Switzerland ) . The 14.6 km long away tunnel (1913) was designed to across the river Kander well beneath the normal water level. Construction ran straight into alluvium which filled the old river bed well below the present river;several workers were killed.The gallery was sealed off and was by-passed by a tunnel about 1 500 m long. Lack of systematic geologic prospection before the construction was the direct cause of this disaster.

(2)Mauvoision ( Switzerland ) . The site of the proposed 237 m high arth dam of Mauvoisin , at that time the highest arch dam in the world , was examined most carefully from the geological point of view . The depth of alluvium filling the narrow gorge at the site was measured seismologically . To enable a direct geological survery to be made , it was decided to drive a gallery deep into the rock abutment on the left-hand side of the gorge . This gallery was planned to pass beneath the gorge and to extend into the right-hand abutment . In addition to a first-hand inspection of the rock , water from several springs was analyzed . Later , the geological gallery was used for grouting a deep grout curtain under the dam . When the narrow gorge was reached the gallery unexpectedly penetrated into

alluvium , which suddenly gave under the pressure of water . The gallery was flooded and four engineers were killed .

It is most likely that wrong interpretations were placed on the wave reflections in the narrow triangular-shaped gorge .

(3)Malgovert ( France ) . Immediately after the Second World War , France power stations were nationalized . Electricite de France was created to administer the whole French electric generating system , with the exception of the power stations on the river Rhone itself , which were entrusted to the Compagnie Nationale du Rhone , in Lyons . Electricite de France immediately realized that there was an acute shortage of power in post-war France , and possible schemes were hastily examined . A plan proposed for the upper valley of the Isere was found to be too modest .A new scheme was designed for a 180 m high arch dam at Tignes and the first power house at Les Brevieres . The Malgovert tunnel , 9.5 miles long , was driven from the portals and through twelve adits .

On the downstream section ( started in January 1948 ) , between adits 13 and 16 , it had been decided to try the full-face method suggested by the geologists . Two large jumbos , both carring 8 DA-35 Ingersoll-Rand drifters , were available and an American Conway 75 shovel . Forty-eight holes were needed for the full heading . As work proceeded ( 1949 ) , the quality of the ground

相关文档
最新文档