管井降水施工方案范本
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
管井降水施工方案
管井降水施工方案
The construction scheme of tube well dewatering
-----柬埔寨安达都会广场项目 ------VCLP PROJECT CAMBODIA
编制单位:Sinoma HanDan Construction Co.,Ltd
编制:
compiled:__________________
审批:
Verified: __________________
批准:
Approved: __________________
日期:
Date : __________________
安达广场基坑降水施工方案
Construction Scheme for Foundation Pit Drawdown of VATTANAC
Park
一、降水设计方案
I. Drawdown design scheme
1.1、设计参数
1.1. Design data
本工程降水井采用直径300mm波纹管滤管,管井共20根井深22米,井口外露500mm。
300mm corrugated filter pipe is adopted as the drawdown well and there are total 20 wells of 22m deep each. The wellhead exposes by 500mm.
1.2、降水井平面布置
1.2. Layout of drawdown well
降水井布置详见降水管井平面布置图。
The arrangement of drawdown well is shown on the layout of drawdown well.
二、施工准备
II. Construction preparation
2.1、测量放线
2.1. Surveying and setting out
测量放线依据现场测量控制点,标高采用水准仪,并根据井点布置图采用全站仪放线定位。放线经复核后报管理公司确认方可进行施工。
The surveying and setting out shall be based on the field survey control points and optical level shall be used for measuring the elevation. In addition, the total station instrument shall be used for the setting out and positioning according to the layout of well points. Setting out shall be performed after re-recheck and being reported to the management company for confirmation.
2.2、施工用电、用水配置
2.2 Electricity and water for construction
1、施工用电直接从配电房接入,50kVA能完全满足降水用电负荷。
1. The electricity for construction shall be directly connected from the switchgear room, and 50kVA can fully meet the drawdown load requirements.
2、依据用水设备和施工经验,需用水量10m3/h直径50mm
管,就能满足施工用水。
2. Depending on the water equipment and based on the construction experience, the pipe of diameter 50mm with a water flow rate of 10m3/h can meet the construction requirements.
2.3、打井机械及井点设备
2.3. Well drilling rig and well point equipment
打井机械可根据工期要求变更。井点设备是由井点管、连接管、排水主管及抽水设备等组成。具体如下:
The well drilling rig may very according to the schedule requirement. The well point equipment consists of well point pipe, connecting pipe, drain header and pumping equipment. The details are as follows:
机械设备表
List of mechanical equipment
2.4、抽水设备的型号