福州地铁四号线公铁过江通道方案研究
合集下载
相关主题
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
[关键词] 城市轨道交通ꎻ公铁ꎻ越江通道
Route Selection of The Crossing river channel for Fuzhou Metro Line 4
Abstract: With the rise of constructions of rail transitꎬthe conflicts between railway channel and highway crossing - river channel are con ̄ stantly occurred������ Fuzhou Metro Line 4 is an important part of the loop line in metro line networkꎬwhich shares the same channel with Qian ̄ heng crossing - river channel from Aofenglu station to Jiangbiancun station������ Based on vertical and horizontal designꎬsurrounding environ ̄ mentꎬconditions of station and difficulty of engineeringꎬthe route scheme of the crossing - river channel was discussed and evaluated������ Key words: Urban Rail Transitꎬ Urban highway and railwayꎬCrossing - river channel
根据规划资料ꎬ前横过江通道通过规划前横大桥连接ꎮ 在与规划前横过江通道业主对接后ꎬ业主倾向于修建过江隧
作者简介:吴忻源(1991. 8 - ) ꎬ女ꎬ硕士研究生ꎬ助理工程师ꎮ
图 1 地铁 4 号线与前横过江通道走向示意图
道ꎮ 结合意见ꎬ分别对公铁共通道方案和地铁绕避公路通道 方案进行了四个方案的研究ꎬ其中公铁共通道方案又分为公 路桥梁方案、公铁隧道合建方案和公铁隧道分建方案ꎮ 如图 2 所示为前横过江通道与四个方案所对应的地铁线路的位置 关系ꎮ 方案一为公路桥梁方案ꎬ地铁隧道沿公路桥梁侧并行 过江ꎻ方案二为公铁隧道合建方案ꎬ公路和地铁布置在同一隧
块ꎬ于金浦路与江边路交叉口设江边村站ꎮ
■市政交通
福建建设科技 2018������ No������ 4
5 7
福州地铁四号线公铁过江通道方案研究
吴忻源( 中铁第四勘察设计院集团有限公司城地院 湖北武汉 430063)
[摘 要] 随着轨道交通建设的兴起ꎬ公路和轨道交通过江通道冲突的问题不断产生ꎮ 福州地铁 4 号线是福州线网中心城 区组合环的重要组成线路ꎬ连通闽江两岸ꎬ其鳌峰路站至江边村站越江段与规划前横过江通道重合ꎮ 本文主要针对过江通道的线 路走向ꎬ结合公铁通道平纵、周边环境、设站条件、工程难度等进行了技术经济比较与评价ꎮ
前横过江通道位于鳌峰大桥下游约 710m、鼓山大桥上游 约 1������ 7km 处ꎬ江面宽约 460mꎮ 该过江通道工程北起国货东 路ꎬ经光明 港、 鳌 江 路 后 过 江ꎬ 南 至 林 浦 路 交 叉 口ꎬ 总 长 约 3������ 157kmꎬ定位为城市主干道ꎮ 主要目的为缓解闽江两岸趋 近饱和的过江交通需求ꎬ分流鳌峰大桥区域过江交通ꎬ连接起 海峡金融街及福州自贸区ꎬ以区域性服务功能为主ꎮ 过闽江 段为规划阶段ꎮ
0 引言 2015 年 12 月ꎬ省发改委批复了« 福州市城市轨道交通第
二期建设规划» (2015 ~ 2021 年) ꎬ本轮建设规划批复的线路 有:4 号线一期、5 号线一期和 6 号线共 89������ 3kmꎬ61 座车站ꎮ
福州地铁四号线一期工程全长 28������ 4kmꎬ线路起于橘园站ꎬ 终于帝封江站ꎬ途经鼓楼、晋安、台江、仓山片区ꎬ连接起福州旧 中心城区、鳌峰金融中心、东部办公区、海峡国际会展中心等重 要节点ꎬ建成后与 1、2、5 号线在城市中心区形成“十字 + 环” 的 布局ꎬ重要程度高ꎬ计划于 2018 年实施ꎮ 线路于鳌峰路站至江 边村站段下穿闽江ꎬ该处与规划前横过江通道产生冲突ꎬ考虑 到地铁工程的永久性及 4 号线的建设时序ꎬ需于 4 号线工程可 行性研究阶段同步研究 4 号线和前横路过江通道方案ꎮ 1 工程概况
绕前横过江通道ꎬ沿独立的路由走行ꎮ
通布置在一孔内ꎬ采用双管 15m 直径盾构ꎮ 上层布置为单向
2������ 1 公铁共通道方案
3 车道道路ꎬ下层布置轨道交通(B 型车)ꎬ如图 3 所示ꎮ
2������ 1������ 1 公路采用桥梁方案
线路出鳌峰路站后拉开线间距( 净距为 15m) ꎬ公铁合建
4 号线于闽江北侧出鳌峰路站后ꎬ继续经鳌江路过江ꎬ于 规划前横南路东侧上岸ꎬ拐入金浦路ꎬ于金浦路和江边路口设 江边村站ꎮ 4 号线和前横过江通道的地理位置如图 1 所示ꎮ
根据交通量预测ꎬ前横过江通道设计为双向 6 车道ꎬ设计 车速 50km / hꎮ 4 号线采用 B 型车ꎬ最高行驶速度为 80km / hꎮ 2 线路走向方案研究
该方案线路出远洋路站后下穿光明港沿规划道路中间向
过江ꎬ双洞隧道之间留有联络通道ꎮ 过江后线路向东下穿规
南ꎬ在鳌峰路与鳌江路交叉口北侧设鳌峰路站ꎬ出站后线路在
划地块ꎬ于金浦路与江边路交叉口设江边村站ꎮ
规划前横大桥下游下穿闽江ꎬ过江后线路拐向东ꎬ下穿规划地
根据水文数据ꎬ该段闽江江底标高约为 - 7������ 7mꎮ 如图 4
5 8
福建建设科技 2018������ No������ 4
■市政交通
图 2 过江方案线路走向比选示意图
道孔洞内ꎬ沿前横过江通道路由过江ꎻ方案三为公铁隧道分
2������ 1������ 2 公铁隧道合建方案
建方案ꎬ公铁隧道相隔一定距离并行过江ꎻ方案四地铁隧道避
该方案公路wenku.baidu.com江通道采用隧道形式ꎬ城市道路与轨道交
Route Selection of The Crossing river channel for Fuzhou Metro Line 4
Abstract: With the rise of constructions of rail transitꎬthe conflicts between railway channel and highway crossing - river channel are con ̄ stantly occurred������ Fuzhou Metro Line 4 is an important part of the loop line in metro line networkꎬwhich shares the same channel with Qian ̄ heng crossing - river channel from Aofenglu station to Jiangbiancun station������ Based on vertical and horizontal designꎬsurrounding environ ̄ mentꎬconditions of station and difficulty of engineeringꎬthe route scheme of the crossing - river channel was discussed and evaluated������ Key words: Urban Rail Transitꎬ Urban highway and railwayꎬCrossing - river channel
根据规划资料ꎬ前横过江通道通过规划前横大桥连接ꎮ 在与规划前横过江通道业主对接后ꎬ业主倾向于修建过江隧
作者简介:吴忻源(1991. 8 - ) ꎬ女ꎬ硕士研究生ꎬ助理工程师ꎮ
图 1 地铁 4 号线与前横过江通道走向示意图
道ꎮ 结合意见ꎬ分别对公铁共通道方案和地铁绕避公路通道 方案进行了四个方案的研究ꎬ其中公铁共通道方案又分为公 路桥梁方案、公铁隧道合建方案和公铁隧道分建方案ꎮ 如图 2 所示为前横过江通道与四个方案所对应的地铁线路的位置 关系ꎮ 方案一为公路桥梁方案ꎬ地铁隧道沿公路桥梁侧并行 过江ꎻ方案二为公铁隧道合建方案ꎬ公路和地铁布置在同一隧
块ꎬ于金浦路与江边路交叉口设江边村站ꎮ
■市政交通
福建建设科技 2018������ No������ 4
5 7
福州地铁四号线公铁过江通道方案研究
吴忻源( 中铁第四勘察设计院集团有限公司城地院 湖北武汉 430063)
[摘 要] 随着轨道交通建设的兴起ꎬ公路和轨道交通过江通道冲突的问题不断产生ꎮ 福州地铁 4 号线是福州线网中心城 区组合环的重要组成线路ꎬ连通闽江两岸ꎬ其鳌峰路站至江边村站越江段与规划前横过江通道重合ꎮ 本文主要针对过江通道的线 路走向ꎬ结合公铁通道平纵、周边环境、设站条件、工程难度等进行了技术经济比较与评价ꎮ
前横过江通道位于鳌峰大桥下游约 710m、鼓山大桥上游 约 1������ 7km 处ꎬ江面宽约 460mꎮ 该过江通道工程北起国货东 路ꎬ经光明 港、 鳌 江 路 后 过 江ꎬ 南 至 林 浦 路 交 叉 口ꎬ 总 长 约 3������ 157kmꎬ定位为城市主干道ꎮ 主要目的为缓解闽江两岸趋 近饱和的过江交通需求ꎬ分流鳌峰大桥区域过江交通ꎬ连接起 海峡金融街及福州自贸区ꎬ以区域性服务功能为主ꎮ 过闽江 段为规划阶段ꎮ
0 引言 2015 年 12 月ꎬ省发改委批复了« 福州市城市轨道交通第
二期建设规划» (2015 ~ 2021 年) ꎬ本轮建设规划批复的线路 有:4 号线一期、5 号线一期和 6 号线共 89������ 3kmꎬ61 座车站ꎮ
福州地铁四号线一期工程全长 28������ 4kmꎬ线路起于橘园站ꎬ 终于帝封江站ꎬ途经鼓楼、晋安、台江、仓山片区ꎬ连接起福州旧 中心城区、鳌峰金融中心、东部办公区、海峡国际会展中心等重 要节点ꎬ建成后与 1、2、5 号线在城市中心区形成“十字 + 环” 的 布局ꎬ重要程度高ꎬ计划于 2018 年实施ꎮ 线路于鳌峰路站至江 边村站段下穿闽江ꎬ该处与规划前横过江通道产生冲突ꎬ考虑 到地铁工程的永久性及 4 号线的建设时序ꎬ需于 4 号线工程可 行性研究阶段同步研究 4 号线和前横路过江通道方案ꎮ 1 工程概况
绕前横过江通道ꎬ沿独立的路由走行ꎮ
通布置在一孔内ꎬ采用双管 15m 直径盾构ꎮ 上层布置为单向
2������ 1 公铁共通道方案
3 车道道路ꎬ下层布置轨道交通(B 型车)ꎬ如图 3 所示ꎮ
2������ 1������ 1 公路采用桥梁方案
线路出鳌峰路站后拉开线间距( 净距为 15m) ꎬ公铁合建
4 号线于闽江北侧出鳌峰路站后ꎬ继续经鳌江路过江ꎬ于 规划前横南路东侧上岸ꎬ拐入金浦路ꎬ于金浦路和江边路口设 江边村站ꎮ 4 号线和前横过江通道的地理位置如图 1 所示ꎮ
根据交通量预测ꎬ前横过江通道设计为双向 6 车道ꎬ设计 车速 50km / hꎮ 4 号线采用 B 型车ꎬ最高行驶速度为 80km / hꎮ 2 线路走向方案研究
该方案线路出远洋路站后下穿光明港沿规划道路中间向
过江ꎬ双洞隧道之间留有联络通道ꎮ 过江后线路向东下穿规
南ꎬ在鳌峰路与鳌江路交叉口北侧设鳌峰路站ꎬ出站后线路在
划地块ꎬ于金浦路与江边路交叉口设江边村站ꎮ
规划前横大桥下游下穿闽江ꎬ过江后线路拐向东ꎬ下穿规划地
根据水文数据ꎬ该段闽江江底标高约为 - 7������ 7mꎮ 如图 4
5 8
福建建设科技 2018������ No������ 4
■市政交通
图 2 过江方案线路走向比选示意图
道孔洞内ꎬ沿前横过江通道路由过江ꎻ方案三为公铁隧道分
2������ 1������ 2 公铁隧道合建方案
建方案ꎬ公铁隧道相隔一定距离并行过江ꎻ方案四地铁隧道避
该方案公路wenku.baidu.com江通道采用隧道形式ꎬ城市道路与轨道交