目录Catalog

一、编制依据及说明Compilation Basis and Description (2)

1.1 编制依据Compilation Basis (2)

1.2 采用的规范、规程和标准名称Used norms, procedures and standard

names (2)

1.3 编制说明Compilation instructions (3)

二、施工方案Construction Plan (3)

2.1 工艺流程Process (3)

2.2 模板支设T emplate supporting (4)

2.3 有粘结预应力钢绞线制作与安装Bonded pre-stressed steel strand

production and installation (4)

2.4 混凝土浇筑Concrete pouring (6)

2.5 有粘结预应力钢绞线张拉Bonded pre-stressed steel strand stretching (7)

2.6 封锚Sealing anchor (9)

三、施工部署Construction Deployment (9)

3.1施工部署总体指导思想Overall guidelines of construction deployment (9)

3.2工期保证体系Schedule assurance system (10)

3.3实现计划管理的保证措施Assurance measures for scheduled

management (12)

3.4安全管理措施Security management measures (12)

四、技术质量保证措施Technology quality assurance measures (13)

4.1 组织保证措施Organization assuring measures (13)

4.2技术交底T echnical clarification (14)

4.3技术准备T echnical preparations (14)

4.4材料准备Material preparation (14)

4.5预应力施工材料的装运和存放Pre-stressed construction material

transporting and storing (16)

预应力分项工程施工方案

Pre-stressed Sub-project Construction Program

第一章编制依据及说明

Chapter 1 Compilation Basis and Description

1.1编制依据Compilation Basis

工程施工技术文件;Project technical documents;

工程建筑施工图(我公司设计方案图);

Engineering construction drawing (company’s designed program graph);

国家、行业及地方有关政策、法律、法令、法规。

National, industrial and local relative policies, laws, decrees and regulations.

国家强制性技术质量标准、施工验收规范、规程。

National mandatory technical quality standards, construction and acceptance codes and regulations.

工艺标准及操作规程。

T echnologic standards and operating procedures.

1.2采用的规范、规程和标准名称Used norms, procedures and standard

names

《混凝土结构工程施工及验收规范》GB50204—2002

" Concrete structures construction and acceptance specification"

《混凝土质量控制标准》GB50164—95

"Concrete quality control standards"

《钢筋焊接及验收规范》JGJ18—96

" Steel welding and acceptance specification "

《混凝土外加剂应用技术规范》GB50119

"T echnical specifications of concrete admixture"

《钢筋混凝土工程施工操作规程》YSJ403—89

"Practice standards for concrete construction"

《钢绞线、钢丝束有粘结预应力筋》JG3006—93

"Steel strand, wire bonded pre-stressed beams"

《预应力混凝土用钢绞线》GB/T5224

" Steel strand for pre-stressed concrete "

《预应力筋用锚具、夹具和连接器应用技术规程》JGJ85—92

"Anchorage/grip and connector application technical regulations for pre-stressed"

《预应力用液压千斤顶》JG/T5028—93

"Pre-stressed with hydraulic jacks"

1.3 编制说明Compilation Basis

针对本工程实际情况,在施工组织中我们把施工总体目标、项目施工方法、工程质量保证措施、安全文明施工保证措施、推广应用新工艺、新技术、新设备等在本工程施工组织设计中作为重点阐述,其他常规性施工项目的施工方法仅作了一般性阐述,以体现本施工组织设计的全面性、可行性、科学性和针对性。

According to the actual situation of the project, we focus on the construction overall goal/ project construction methods/ quality assurance measures/ safe and civilized construction measures/ promoting the application of new technology/ new technology and new equipment in the construction organizations and make detailed description about them. As for other conventional construction methods, we just make only general discription, to reflect the comprehensive nature of the construction design, feasibility, scientific and relevant characters.

在本施工组织设计中,我们编制了推广应用新工艺、新技术、新设备计划。在科技进步领域里以实现不断进取,推广生产力发展。

In the construction method statement, we compile with promoting the use of new technology, new technology, new equipment plans, to achieve continuous progress in the field of science and technology and promote development of productive forces.

第二章施工方案

Chapter 2 Construction Plan

2.1工艺流程Process

预应力分项工程中有粘结预应力梁工艺流程为:

Bonded pre-stressed beam process in pre-stressed sub-project is as follows.