施工临时用电方案计算书
临时用电电力计算书
2、确定用电负荷:(1)、混凝土输送泵Kx = 0.3 Cosφ = 0.7 tgφ = 1.02 Pjs= 0.3×75 = 22.5 kWQ js = Pjs× tgφ=22.5×1.02 = 22.95 kvar(2)、强制式混凝土搅拌机Kx = 0.75 Cosφ = 0.85 tgφ = 0.62 Pjs= 0.75×60 = 45 kWQ js = Pjs× tgφ=45×0.62 = 27.89 kvar(3)、配料机Kx = 0.7 Cosφ = 0.3 tgφ = 3.18 Pjs= 0.7×0.3 = 0.21 kWQ js = Pjs× tgφ=0.21×3.18 = 0.67 kvar(4)、平板式振动器Kx = 0.3 Cosφ = 0.7 tgφ = 1.02 Pjs= 0.3×2.2 = 0.66 kWQ js = Pjs× tgφ=0.66×1.02 = 0.67 kvar(5)、插入式振动器Kx = 0.3 Cosφ = 0.7 tgφ = 1.02 Pjs= 0.3×1.6 = 0.48 kWQ js = Pjs× tgφ=0.48×1.02 = 0.49 kvar(6)、插入式振动器Kx = 0.3 Cosφ = 0.7 tgφ = 1.02 Pjs= 0.3×0.8 = 0.24 kWQ js = Pjs× tgφ=0.24×1.02 = 0.24 kvar(7)、交流电焊机Kx = 0.35 Cosφ = 0.4 tgφ = 2.29将J c =50%统一换算到J c1 =100%的额定容量P n = Sn×Cosφ= 76×0.4=30.4kWP e = n×(Jc/Jc1)1/2×Pn = 1×(0.5/1)1/2×30.4 = 21.5 kWP js = Kx×Pe=0.35×21.5 = 7.52kWQ js = Pjs× tgφ=7.52×2.29 = 17.24 kvar(8)、备用Kx = 0.7 Cosφ = 0.7 tgφ = 1.02 Pjs= 0.7×20 = 14 kWQ js = Pjs× tgφ=14×1.02 = 14.28 kvar(9)总的计算负荷计算,总箱同期系数取 Kx = 0.9 总的有功功率P js = Kx×ΣPjs= 0.9×(22.5+45+0.21+0.66+0.48+0.24+7.52+14) = 81.553kW总的无功功率Q js = Kx×ΣQjs=0.9×(22.95+27.89+0.67+0.67+0.49+0.24+17.24+14.28)= 75.996 kvar总的视在功率S js = ( Pjs2+Qjs2)1/2 = (81.5532+75.9962)1/2 = 111.473 kVA总的计算电流计算I js = Sjs/(1.732×Ue) = 111.473/(1.732×0.38) = 169.371 A3、1号干线线路上导线截面及分配箱、开关箱内电气设备选择:在选择前应对照平面图和系统图先由用电设备至开关箱计算,再由开关箱至分配箱计算,选择导线及开关设备。
临时用电电负荷计算书
临时用电电负荷计算书1.4.1镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar1.4.2镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar1.4.3镝灯K x = 0.6 Cosφ= 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar1.4.4镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar1.4.5塔式起重机K x = 0.2 Cosφ = 0.6 tgφ = 1.33将J c =40%统一换算到J c1 =25%的额定容量P n = 48kWP e = n×(J c/J c1)1/2×P n = 1×(0.4/0.25)1/2×48 = 60.72 kWP js = K x×P e =0.2×60.72 = 12.14kWQ js = P js× tgφ=12.14×1.33 = 16.19 kvar 1.4.6混凝土输送泵K x = 0.3 Cosφ = 0.7 tgφ = 1.02P js = 0.3×32.2 = 9.66 kWQ js = P js× tgφ=9.66×1.02 = 9.86 kvar 1.4.7插入式振动器K x = 0.3 Cosφ = 0.7 tgφ = 1.02P js = 0.3×1.5 = 0.45 kWQ js = P js× tgφ=0.45×1.02 = 0.46 kvar 1.4.8蛙式夯土机K x = 0.5 Cosφ = 0.55 tgφ = 1.52P js = 0.5×3 = 1.5 kWQ js = P js× tgφ=1.5×1.52 = 2.28 kvar1.4.9木工圆锯K x = 0.3 Cosφ = 0.6 tgφ = 1.33P js = 0.3×1.5 = 1.65 kWQ js = P js× tgφ=1.65×1.33 = 2.2 kvar1.4.10木压刨板机K x = 0.3 Cosφ = 0.6 tgφ = 1.33P js = 0.3×3 = 0.9 kWQ js = P js× tgφ=0.9×1.33 = 1.2 kvar1.4.11水泵K x = 0.75 Cosφ = 0.8 tgφ = 0.75P js = 0.75×7.5 = 1.625 kWQ js = P js× tgφ=1.62×0.75 = 4.22 kvar 1.4.12灰浆搅拌机K x = 0.5 Cosφ = 0.55 tgφ = 1.52P js = 0.5×3 = 1.5 kWQ js = P js× tgφ=1.5×1.52 = 2.28 kvar 1.4.13镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar 1.4.14镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar 1.4.15镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar 1.4.16镝灯K x = 0.6 Cosφ = 0.7 tgφ = 1.02P js = 0.6×2×1.1 = 1.32 kWQ js = P js× tgφ=1.32×1.02 = 1.35 kvar 1.4.17钢筋调直机K x = 0.3 Cosφ = 0.7 tgφ = 1.02P js = 0.3×1.5 = 1.65 kWQ js = P js× tgφ=1.65×1.02 = 1.68 kvar 1.4.18钢筋切断机K x = 0.3 Cosφ = 0.7 tgφ = 1.02P js = 0.3×1.5 = 1.65 kWQ js = P js× tgφ=1.65×1.02 = 1.68 kvar 1.4.19钢筋弯曲机K x = 0.3 Cosφ = 0.7 tgφ = 1.02P js = 0.3×3 = 0.9 kWQ js = P js× tgφ=0.9×1.02 = 0.92 kvar1.4.20套丝切管机K x = 0.3 Cosφ = 0.6 tgφ = 1.33P js = 0.3×1 = 0.3 kWQ js = P js× tgφ=0.3×1.33 = 0.4 kvar1.4.21塔式起重机K x = 0.2 Cosφ = 0.6 tgφ = 1.33将J c =40%统一换算到J c1 =25%的额定容量P n = 51.5kWP e = n×(J c/J c1)1/2×P n = 1×(0.4/0.25)1/2×51.5 = 70.2 kW P js = K x×P e =0.2×70.2 = 14.04kWQ js = P js× tgφ=14.04×1.33 = 18.72 kvar1.4.22办公室K x = 0.2 Cosφ = 0.6 tgφ = 1.33P js = 0.2×20 = 4 kWQ js = P js× tgφ=4×1.33 = 1.33 kvar1.4.23临时照明K x = 0.3 Cosφ = 0.7 tgφ = 1.02P js = 0.3×4 = 1.2 kWQ js = P js× tgφ=1.2×1.02 = 1.22 kvar1.4.24灰浆搅拌机K x = 0.5 Cosφ = 0.55 tgφ = 1.52P js = 0.5×3 = 1.5 kWQ js = P js× tgφ=1.5×1.52 = 2.28 kvar1.4.25交流电焊机K x = 0.35 Cosφ = 0.4 tgφ = 2.29将J c =50%统一换算到J c1 =100%的额定容量P n = S n×Cosφ = 9×0.4=3.6kWP e = n×(J c/J c1)1/2×P n = 1×(0.5/1)1/2×3.6 = 2.55 kWP js = K x×P e =0.35×2.55 = 0.89kWQ js = P js× tgφ=0.89×2.29 = 2.04 kvar1.4.26总的计算负荷计算,总箱同期系数取 Kx = 0.9总的有功功率P js = K x×ΣP js =0.9×(1.32+1.32+1.32+1.32+12.14+9.66+0.45+1.5+1.65+0.9+1.62+1.5+1.32+1.32+1.32+1.32+1.65+1.65+0.9+0.3+14.04+4+1.2+1.5+ 0.89) = 63.108 kW总的无功功率Q js = K x×ΣQ js=0.9×(1.35+1.35+1.35+1.35+16.19+9.86+0.46+2.28+2.2+1.2+4.22 +2.28+1.35+1.35+1.35+1.35+1.68+1.68+0.92+0.4+18.72+1.33+1. 22+2.28+2.04) = 71.362 kvar总的视在功率S js = ( P js2+Q js2 )1/2 = (63.1082+71.3622)1/2 = 98.296 kVA总的计算电流计算I js = S j s/(1.732×U e) = 98.296/(1.732×0.38) = 149.35 A1.1.一号二级箱导线、分箱、设备选择:在选择前应对照平面图和系统图先由用电设备至开关箱计算,再由开关箱至分配箱计算,选择导线及开关设备。
施工现场临时用电计算书
施工现场临时用电计算书计算书1、总用电量计算(依据公式) :(1) P1①井塔吊和木工设备K x = 0.5 , Cos© = 0.7 ;P js =44.4KW木工机具:7.5 KW44.4+7.5=51.9 KW(2) P2供搅拌机、砂浆机和A楼施工用电K x = 0.5 ,Cos© = 0.7 ;P js =10.5KWA楼照明=50 KW10.5+50=60.5 KW(3) P3 两台人货电梯用电K x = 0.5 ,Cos© = 0.7 ;P js =20kW(4) P4 B 楼施工用电K x = 0.5 ,Cos© = 0.7 ;P js = 50kW(5) P5②#塔吊K x = 0.5 ,Cos© = 0.7 ;P js = 44.4kW(6) P6 钢筋切断、对焊、调直和弯曲等机组K x = 0.5 , Cos© = 0.7 ;P js = 89.93kW(7) 总的负荷计算,功率因数= 0.7 ,系数取=0.5。
总的有功功率P js= (51.9 +60.5 +20+50+44.4+89.93+A、B 楼照明和移动机具225.1) = 541.83kW计算变压器容量= K x 541/0.7=386kVAljs=0.5X 541KW/1.732X 0.38 X 0.7=588A2、选择变压器根据计算的总的容量选择ZBW-450/10 型三相电力变压器,它的容量为450kVA>386kVA X 1.1(增容系数)能够满足使用要求,其高压侧电压为10kV 同施工现场外的高压架空线路的电压级别一致。
3、选择总箱的进线截面及进线开关(1) 选择导线截面:上面已经计算出总计算电流l js = 588A ,查表得室外埋设线路40° C时选择240伽2,其安全载流量为592A,能够满足使用要求。
由于供电箱至动力总箱距离短,可不校核电压降的选择。
施工现场临时用电专项方案的计算书和验算依据
施工现场临时用电专项方案的计算书和验算依据1.临时用电计算用电验算依据:根据公式(1)计算出导线上的允许电流,查表可得满足电流要求的配电导线截面积,根据公式(2)计算满足要求的导线电压降所需最小截面积,取两者之间的大值作为配电导线的截面积。
1)按导线允许电流选择三相五线制低压线路上的电流可按下式计算ϕCOS U PI ⨯⨯=1131000(1)式中:l I —线路工作电流值(A )。
l U —线路工作电压值(V ),三相五线制低压时,380l U V =。
P —计算用电量(kVA )。
cos ϕ—用电设备功率因数,取0.7。
2)按允许电压降校核三相五线制低压线路导线截面积可按下式计算 max min ε⨯⨯=∑C LP S (2)式中:min S —导线截面积(mm 2)。
L —变压器低压开关据现场距离(m ),取100L m =。
C —材料内部系数,根据电压和电流种类取用,取46.3C =。
max ε—导线电压降(%),一般工地临时用电网络取7。
P —计算用电量(kVA )。
根据公式(1)及公式(2)计算配电线路截面面积,计算过程如下:(1)1#拌和站 按导线允许电流计算:A I l 1.4317.038036.1981000=⨯⨯⨯= 按允许电压降计算: 2min 3.6173.461006.198mm S =⨯⨯= (2)xxx 大桥、1#钢筋场地按导线允许电流计算:A I l 6.6717.038034.3091000=⨯⨯⨯= 按允许电压降计算: 2min 5.9573.461004.309mm S =⨯⨯= (3)xxx 、预制梁场、2#钢筋加工厂及2#拌和站 按导线允许电流计算:A I l 8.9307.038038.4281000=⨯⨯⨯= 按允许电压降计算: 2min 132.373.461008.428mm S =⨯⨯= (4)xxx 大桥 按导线允许电流计算:A I l 2.4577.038036.2101000=⨯⨯⨯= 按允许电压降计算: 2min 0.6573.461006.210mm S =⨯⨯= (5)xxx 隧道按导线允许电流计算:A I l 2.17747.038034.8171000=⨯⨯⨯= 按允许电压降计算: 2min 2.25273.461004.817mm S =⨯⨯= (6)xxx 大桥、3#拌和站及2#钢筋加工厂按导线允许电流计算:A I l 6.8237.038034.3791000=⨯⨯⨯= 按允许电压降计算: 2min 1.11773.461004.379mm S =⨯⨯= (7)xxx 隧道按导线允许电流计算:A I l 2.16227.038034.7471000=⨯⨯⨯= 按允许电压降计算: 2min 6.23073.461004.747mm S =⨯⨯= (8)xxx 大桥按导线允许电流计算:A I l 3.3217.038030.1481000=⨯⨯⨯= 按允许电压降计算: 2min 7.4573.4610001.148mm S =⨯⨯=。
施工临时用电缆计算计算书
施工临时用电缆计算计算书1. 计算标准根据国家相关规定和标准,临时用电缆计算需要考虑以下因素:- 用电负荷- 电缆的额定工作电压和额定电流- 电缆线路的长度和敷设方式- 线路的载流量- 线路的温度2. 计算步骤步骤一:确定用电负荷首先,需要确定施工现场的用电负荷。
根据实际需要供电的设备和用电器具,计算总负荷。
确保总负荷的合理分配和平衡。
步骤二:选择电缆类型根据用电负荷和工作环境的特点,选择合适的电缆类型。
考虑到施工现场的临时性负荷,选择适用于中等负荷和温度的电缆。
步骤三:计算电缆额定电流根据所选电缆的额定工作电压和额定电流参数,计算所需电缆线路的额定电流。
确保电缆的负荷能够满足实际用电需求。
步骤四:计算线路长度和敷设方式根据施工现场的布置和需要供电的区域,计算电缆线路的长度和敷设方式。
确保电缆的敷设合理,避免过长或过短的线路。
步骤五:计算线路的载流量和温度根据电缆的额定电流、线路长度和敷设方式,计算线路的载流量。
同时考虑线路周围的温度,确保电缆在正常运行温度范围内。
步骤六:评估计算结果根据以上计算,评估所得结果是否符合国家相关规定和标准。
如果结果符合要求,则可确定所需临时用电缆的规格和长度。
3. 结论本文档介绍了施工临时用电缆计算的计算标准和步骤。
根据实际情况和国家标准,通过逐步计算用电负荷、电缆类型、额定电流、线路长度和敷设方式、线路载流量和温度等参数,可以得到准确的临时用电缆规格和长度。
在进行计算时,请确保遵守国家相关规定,并保持独立的决策。
施工临时用电方案计算书
施工临时用电方案计算书1. 引言在工程施工过程中,临时用电是必不可少的一项工作。
临时用电方案的合理设计对保障施工工作的正常进行具有重要作用。
本文将针对施工临时用电方案进行计算和设计,以保证施工过程中的用电需求得到满足。
2. 计算方法临时用电方案的计算需要考虑以下几个方面:•施工现场的总用电负荷:–施工机械设备的用电负荷;–临时仓库、办公区等临时设施的用电负荷;–施工现场照明和通风设备的用电负荷;–其他特殊设备的用电负荷。
•用电功率的计算:–根据施工机械设备的参数,计算每台机械设备的用电功率;–根据临时设施的规模和使用情况,计算临时设施的用电功率;–根据照明和通风设备的数量和规格,计算照明和通风设备的用电功率;–根据特殊设备的参数,计算特殊设备的用电功率。
•用电容量的确定:–根据施工现场的总用电负荷和用电功率计算得出施工现场的总用电容量;–考虑到施工中可能出现的临时用电负荷增加的情况,应在总用电容量的基础上增加一定的安全裕度。
3. 临时用电方案计算示例下面是一个临时用电方案计算的示例,以便更好地理解计算方法。
3.1 某施工现场的信息:•施工机械设备:起重机1台(功率20kW),挖掘机2台(每台功率15kW),压路机1台(功率10kW);•临时设施:办公区(功率5kW),临时仓库(功率3kW);•照明和通风设备:50个照明灯(每个功率100W),3个通风设备(每个功率200W);•特殊设备:电焊机(功率8kW),空压机(功率6kW)。
3.2 用电功率的计算:施工机械设备的用电功率: - 起重机:20kW; - 挖掘机:2台 × 15kW/台 = 30kW; - 压路机:10kW。
临时设施的用电功率: - 办公区:5kW; - 临时仓库:3kW。
照明和通风设备的用电功率: - 照明灯:50个 × 100W/个 = 5000W; - 通风设备:3个 × 200W/个 = 600W。
施工临时用电计算书
施工临时用电计算书检查施工单位是否按如下公式进行验算,以满足施工现场用电量及安全生产需要。
4.1.用电量计算:依下公式进行P=1.05~1.1(K1ΣP1/cosφ+K2ΣP2+ K3ΣP3+ K4ΣP4)式中:P—供电设备总需安装量(KVA)P1——电动机额定功率(KW)P2——电焊机额定容量(KVA)P3——室内照明容量P4——室外照明容量cosφ—电动机平均功率因数(施工现场最高0.75—0.78,一般为0.65—0.75)4.2.导线截面选择的理论和公式:a、按机械强度选择:导线必须保证不致因一般机械损伤折断。
b、按容许电流选择:导线必须承受负载电流长时间通过引起的升温。
c、导线电压降必须在一定限度内。
所选用导线截面必须同时满足以上三项要求。
在建筑工地配电线路较短,导线截面可由容许电流选定,计算公式如下:a、按最小机械强度选择导线截面:架空BX=10㎜2,BLX=16㎜2(BX为外护套橡皮线、BLX为橡皮铝线)b、按安全载流量选择导线截面:Ijs =KX*Σ(Pis)/3*Uecosφ式中:Ijs —计算电流、KX—同时系数(取0.7—0.8)、Pis—有功功率Ue—线电压、cosφ—功率因数c、按容许电压降选择导线截面:S= KX *Σ(Pe*L)/Ccu*△U式中:S—导线截面、Pe —额定功率、Pis—负载到配电箱的长度Ccu—常数(三相四项制77、单项12.8)△U—允许电压降、临时用电用8%、正式电路取10%4.3.配电箱布置,着重监督施工单位做好以下工作,使施工用电趋于规范化和专业化:4.3.1.金属箱架、门、安装板不带电的金属外壳及靠近带电部分的金属护栏等均需采用绿黄双色多股软绝缘导线与PE保护零线做可靠连接。
施工现场临时用电的配置:以“三级配电、三级漏保”,“一机一闸一漏一箱一锁”为原则。
4.3.2.漏电开关的漏电动作电流分级设置:A级配电箱:I△n <100mA T△n<0.1SB级配电箱:I△n <50mA T△n<0.1SC级配电箱:I△n <30mA T△n<0.1S手持电动工具、夯土电动机械、潮湿场所等活动箱内须采用I△n<15mAT△n<0.1S 的漏电保护开关。
施工用电方案计算书
施工临时用电方案计算书一、编制依据《低压配电设计规范》GB50054-95中国建筑工业出版社《建筑工程施工现场供电安全规范》GB50194-93中国建筑工业出版社《通用用电设备配电设计规范》GB50055-93中国建筑工业出版社《供配电系统设计规范》GB50052-95中国建筑工业出版社《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社《建筑施工安全检查标准》JGJ59-99二、施工条件施工现场用电量统计表:----------------------------------------------------------------------序号机具名称型号安装功率(kW) 数量合计功率(kW)1 平板式振动器 ZB11 1.1 11.12 混凝土输送泵 HB-15 32.2 132.23 卷扬机 JJM-0.5 3 3 94 插入式振动器 ZX50 1.1 55.55 灰浆搅拌机 UJ100 2.2 36.66 蛙式夯土机 HW-32 1.5 34.57 钢筋切断机 QJ32-1 3 1 38 钢筋调直机 GT4/14 4 1 49 木工圆锯 MJ104 3 3 910 木工平刨床 MB503A 3 3 911 钢筋弯曲机 GW40 3 1 312 直流电焊机 AX1-165(AB-165) 6 2 1213 交流电焊机 BX3-120-1 9 2 1814 白炽灯 1 3 315 高压汞灯 3 20 6016 荧光灯 0.2 20 417 塔式起重机 TQ90(自升式) 58 1 5818 塔式起重机 TQ90(自升式) 58 1 58----------------------------------------------------------------------三、设计内容和步骤1、现场勘探及初步设计:(1)本工程所在施工现场范围内施工前无各种埋地管线。
(2)现场采用380V低压供电,设一配电总箱,内有计量设备,采用TN-S系统供电。
临电计算书
mm2
线路6
1、按导线的允许电流选择
Il=1000∑P/(31/2×Ul×cosφ)=
223
A
其中:
∑P:各段线路负荷计算功率
110
kW
Il:线路工作电流值
Ul:线路工作电压值
三相五线制Ul=
380
V
cosφ:用电设备功率因数,一般建筑工地取
0.75
查表得导线截面S为:
50
mm2
2、按导线的允许电压降校核
0.8
K3:室外照明设备同时使用系数
1.0
1.1:用电不均匀系数
或:
P=1.24×K1∑Pc=
93
kW
其中:
P:计算用电量,即供电设备总需要容量
K1:全部施工用电设备同时使用系数
0.75
施工用电占总用电量的90%,室内外照明占总用电量的10%。
三、配电导线截面计算
线路1
1、按导线的允许电流选择
Il=1000∑P/(31/2×Ul×cosφ)=
ε=∑M/(C×S)=∑P×L/(C×S)=
0.857
%
ε
≤
[ε]=
7
%
其中:
ε:导线电压降
L:各段线路长度
30
m
∑M:各段线路负荷矩(kW·m)
∑M=∑P·L
S:导线截面
C:材料内部系数,根据线路电压和电流种类查表取用
77
[ε]:工地临时网路允许电压降
则导线截面为:
S=∑P×L/(C×[ε])=
6.12
50
mm2
线路2
1、按导线的允许电流选择
Il=1000∑P/(31/2×Ul×cosφ)=
施工临时用电方案计算书(自备电源)
施工临时用电方案深圳(罗湖)金马广场工程;工程建设地点: 深圳市罗湖区桃园路与梨园路交汇处西南角;属于框剪结构;地上5层;地下3层;建筑高度:31.8m;标准层层高:6m ;总建筑面积:5 5 1 3 1 . 97平方米;总工期:540天。
本工程由深圳市正泰园置业发展有限公室投资建设,城脉建筑设计(深圳)有限公司设计,深圳地质建设工程公司地质勘察,深圳市众望工程管理有限公司监理,深圳地质建设工程公司组织施工;由钟柏强担任项目经理,张国良担任技术负责人。
工程说明:拟建金马广场项目规模,总建筑面积55131.97m2,总用地面积10925m2 框架剪力墙结构,地下三层、地上五层,建筑高度31.8m,柱基础为人工成孔灌注桩,基坑局部最深处约16.85m,平均深度15.35m,建筑基底面积约为6499.63m2= 土方开挖约15万m3本工程前期基坑支护采用日本东芝DB-2531h自备电源发电机组发电,总功率195千伏安。
发电机组位于基坑中部,配总电箱一个,其余采用移动式电箱。
一、编制依据《低压配电设计规范》GB50054-95中国建筑工业出版社《建筑工程施工现场供电安全规范》GB50194-9沖国建筑工业出版社《通用用电设备配电设计规范》GB50055-9沖国建筑工业出版社《供配电系统设计规范》GB50052-95中国建筑工业出版社《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社《建筑施工安全检查标准》JGJ59-99二、施工条件施工现场用电量统计表:序号机具名称型号安装功率(kW) 数量合计功率(kW)1交流电焊机BX3-200-223.4 2 46.82交流电焊机BX3-200-223.4 2 46.83交流电焊机BX3-120-19 4 364交流电焊机BX3-200-223.4246.85泥浆泵红星-30302606砼喷射机HPG4202407高压镝灯34128冲钻孔机ZKL400402809泥浆泵红星-3030260三、设计内容和步骤1、现场勘探及初步设计:(1) 本工程所在施工现场范围内施工前无各种埋地管线。
临时用电计算书
第十八章. 临时施工水电计算书19.1施工用水计算现场施工面积为<5公顷,且施工用水q1+现场生活用水q3+施工机械用水q2<消防用水q4所以,总用水量Q取消防用水量q4=10 v/s供水管 d =92mm选用Φ100镀锌钢管作为总供水管,其余支管选用Φ50镀锌钢管。
19.2施工用电计算(1)、施工用电根据施工用电设备总功率选择主干线。
固定物料提升机1台1*18=18KW蛙式打夯机1台1*5.5=5.5KW350搅拌机1台1*7.5=7.5KW震动棒4台(2台备用)2*1.1=2.2KW平板震动器2台2*1.5=3.0KW圆盘锯1台2*5.5=11KW交流电焊机1台1*30=30KW钢筋切断机 1 台1*5.5=5.5 KW钢筋弯曲机1台1*5.5=5.5 KW临时用电10KW合计92.7KW(82.7KW)临网电路电压:380V/220V 平均功率因数取0.75则主干线电流: P=1.05*(0.6*82.7/0.75+1.0*10)=76.16KV A查表,导线选择:铜芯电缆线S=50㎜2(2)施工临时用电布置本工程临时用电高峰期负荷总容量为128.59KV A。
临时用电线路为TN-S系统三相五线制,供电主十线为BLV(3×50+2×25),由工地现场供电电源引接,采用二级配电。
现场设总配电箱和发电机,详见施-电图。
施工机械用电线路首端接漏电保护器,保证安全用电。
为保证外电中断时有些工种能连续施工,工地设备用发电机1台。
(3)施工用电安全措施施工用电应用设计布置图,有审核批准手续,确定供电设备及电线规格,各种电箱、开关箱、漏电保护器等。
电工必须经过地市级专门培训考核合格发证上岗,并按照《施工现场临时用电安全技术规范》进行安装操作,严禁违章操作。
现场临时用电的线路必须采用"三相五线制",所有用电设备必须做统一接地保护或接零保护,不准一部份接地一部份接零。
施工现场临时用电计算书
施工现场临时用电计算书一、工程概况本工程位于哈尔滨市香坊区哈平路任家桥地段,建筑面积为168000多米,本项目由6栋32层和7栋小多层组成一个地下停车场。
二、本项目建筑部分由6家承建商负责建设其中1#2#号为一家3#4#5#6#地下车库各为一家建筑公司。
三、施工现场用电机械统计表序号设备名称规格、安装功率数量合设功率1 砼泵100-50型90KW 6 540KW2 灰浆机400型 3.5KW 6 21KW3 振动器P2—50 1.1KW 12 13.2KW4 塔吊QTZ63 47.5KW 6 285KW5 升降梯SE-100 44KW6 264KW6 电焊机BX3-500 24KW 12 288KW7 对焊机UNI-100 24KW 7 168KW8 切断机CJS-40 3KW 6 18KW9 弯曲机GW40 3KW 6 18KW10 调直机JQ 3KW 6 18KW11 室内外照明——10KW ——6 60KW四、确定计算负荷1. 砼泵:查表Kx = 0.7 COSψ= 0.68tgψ= 1.08Pis1= Kx × Pe1 = 0.7×540 = 378KWQjs1= Pjs1 × tgψ= 378×1.08 = 408.24Kvar2. 灰浆机:查表Kx = 0.7,COSψ= 0.68,tgψ= 1.08Pis2= Kx × Pe2 = 0.7× 21= 14.7KWQjs2= Pjs2× tgψ= 14.7×1.08 =15.87Kvar3. 振动器:查表Kx = 0.7,COSψ= 0.7,tgψ= 1.02Pis3= Kx × Pe4 = 0.7×13.2 =9.24KWQjs3= Pjs3× tgψ= 9.24×1.02 =9.42Kvar4. 塔吊组:查表Kx = 0.3,COSψ= 0.7,tgψ= 1.02Pis4=Kx×Pe4 =0.3x285 =85.5KWQjs4= Pis4× tgψ=88.5× 1.02 =90.27Kvar5. 升降梯:查表Kx = 0.3,COSψ= 0.7,tgψ= 1.02Pis5= Kx × Pe5 = 0.3×264= 79.2KWQjs5= Pjs5× tgψ= 79.2×1.02 =80.78Kvar6. 电焊机:查表Kx = 0.45,tgψ= 1.98Pe6=√0.5×288= 203.6KWPis6= Kx×Pe6=0.45×203.6= 91.62KWQjs6= Pjs6× tgψ= 91.62×1.98 =181.4Kvar7.对焊机:查表Kx = 0.45,tgψ= 1.98Pe7=√0.5×168= 118.7KWPis7= Kx ×Pe7=0.45×118.7= 53.4KWQjs7= Pjs7×tgψ= 53.4× 1.98 =105.7Kvar8. 切断机:查表Kx = 0.7,tgψ= 1.02Pis8= Kx × Pe8= 0.7×18=12.6KWQjs8= Pjs9×tgψ= 12.6×1.02 =12.85Kvar9. 弯曲机:查表Kx = 0.7,tgψ= 0.88Pis9= Kx×Pe9=0.7×18=12.6KWQjs9= Pjs9×tgψ= 12.6×0.88 =11.08Kvar10.调直机:查表Kx = 0.7,tgψ= 0.88Pis10= Kx×Pe10=0.7×18=12.6KWQjs10= Pjs10×tgψ= 12.6×0.88 =11.08Kvar11. 总的计算负荷计算,干线同期系数取KX=0.9Pis=KX ×(Pis1+ Pis2…+ Pis10)=0.9×749.46=674.5KW总的无功功率:Qis= KX ×(Qis1+ Qis2…+ Qis9)=0.9×926.69=834.02KW总的视在功率:Sis =√Pis2+Qis2=√204.22+342.362=1072.63KV A总的计算电流计算:Iis = Sis/(√3•Ue)=1072.63/(√3×0.38 )=1629.69A315KV A湿式变压器超载率20%(根据标牌估算)计算:张跃辉办公楼照明电气中,已知本用电系统各功率的总和Pe,另外通过表查得需要系数值Kx,功率因素值cos∮,想计算出Ijs值,请问公式是怎样的?Ijs=Pe*Kx/1.732*0.38*cos∮.配电手册中的负荷计算章节都有这计算公式.三相电流计算:Ijs=Pe*Kx/1.732*0.38*cos∮.单相电流计算:Ijs=Pe*Kx/*0.22*cos∮.再重复一次吧:配电设计手册中的负荷计算章节都有这计算公式.。
道路施工现场临时用电方案计算书
道路施工现场临时用电方案计算书1.1计算依据1.《建设工程施工现场供用电安全规范》GB50194-932.《施工现场临时用电安全技术规范》JGJ46-20053.《低压配电设计规范》GB50054-954.《供配电系统设计规范》GB50052-955.《通用用电设备配电设计规范》GB50055-936.《建筑施工安全检查标准》JGJ59-20111.2现场勘探及初步设计1.本工程所在施工现场范围内部分地区有埋地管线,在搭接线路时严格保护原有管线不被破坏。
2.现场采用380V低压供电,设8配电总箱,内有计量设备,采用TN-S系统供电。
3.根据施工现场用电设备布置情况,采用导线架空敷设,布置位置参见现场平面图,采用三级配电,两极防护。
4.按照《JGJ46-2005》规定制定施工组织设计,接地电阻R≤4Ω1.3一号取电点用电计算位置:项目部门口右侧、明渠边上,主要供项目部生活用电及桥梁桩基施工用电。
1.3.1项目部及桥梁桩基主要用电量统计表1.3.2项目部及桥梁桩基用电量计算(1)、钢筋切断机K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×2×1.5=7.15kWQ js=P js×tgφ=7.15×0.75=1.3625kvar (2)、钢筋切断机K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×2×7.5=9.75kWQ js=P js×tgφ=9.75×0.75=7.3125kvar(3)、钢筋箍筋弯曲机K x=0.8,Cosφ=0.85,tgφ=0.62P js=0.8×2×1.5=2.4kWQ js=P js×tgφ=2.4×0.62=1.488kvar(4)、钢筋弯曲机K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×2×3=3.9kWQ js=P js×tgφ=3.9×0.75=2.925kvar(5)、钢筋调直切断机K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×2×4=1.2kWQ js=P js×tgφ=1.2×0.75=3.9kvar(6)、对焊机K x=0.65,Cosφ=0.8,tgφ=0.75将J c=20%统一换算到J c1 =100%的额定容量P n=16kWP e=n×(J c/J c1)1/2×P n=2×(0.2/1)1/2×16=14.31 kW P js=K x×P e=0.65×3×14.31=27.9045kWQ js=P js×tgφ=27.9045×0.75=20.93kvar(7)、碘钨灯K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×1×35=22.75kWQ js=P js×tgφ=22.75×0.75=17.1kvar(8)、钢筋直螺纹套丝机K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×3×4=7.8kWQ js=P js×tgφ=7.8×0.75=1.85kvar(9)、管理人员办公室节能灯K x=0.8,Cosφ=0.7,tgφ=1.02将J c=60%统一换算到J c1 =70%的额定容量 P n=0.1kWP e=n×(J c/J c1)1/2×P n=150×(0.6/0.7)1/2×0.1=13.125kWP js=K x×P e=0.8×13.125=10.5kWQ js=P js×tgφ=10.5×1.02=10.71kvar(10)、插入式振动器K x=0.65,Cosφ=0.9,tgφ=0.48P js=0.65×1.1×2=1.43kWQ js=P js×tgφ=1.43×0.48=0.69kvar (11)、潜水泵K x=0.65,Cosφ=0.9,tgφ=0.48P js=0.65×2.2×20=28.6kWQ js=P js×tgφ=28.6×0.48=13.728kvar(12)、搅拌机K x=0.7,Cosφ=0.9,tgφ=0.48P js=0.7×7.5×2=10.5kWQ js=P js×tgφ=10.5×0.48=1.04kvar(13)卷扬机K x=0.7,Cosφ=0.9,tgφ=0.48P js=0.7×1.5×20=21kWQ js=P js×tgφ=21×0.48=10.08kvar(14)、手提电钻K x=0.7,Cosφ=0.9,tgφ=0.48将J c=40%统一换算到J c1 =100%的额定容量 P n=1.5kWP e=n×(J c/J c1)1/2×P n =15×(0.4/1)1/2×1.5=14.25kW P js=K x×P e=0.7×14.25=9.975kWQ js=P js×tgφ=9.975×0.48=4.788kvar(15)、管理人员宿舍照明节能灯K x=0.7,Cosφ=0.9,tgφ=0.48将J c=60%统一换算到J c1 =70%的额定容量P n=0.04kWP e=n×(J c/J c1)1/2×P n =100×(0.6/0.7)1/2×0.1=3.8 kWP js=K x×P e=0.7×3.8=2.66kWQ js=P js×tgφ=2.66×0.48=1.2768kvar(16)、管理人员办公室空调及电脑K x=0.7,Cosφ=0.9,tgφ=0.48将J c=60%统一换算到J c1 =70%的额定容量P n=2.3kWP e=n×(J c/J c1)1/2×P n =45×(0.6/0.7)1/2×2.3=39.33 kWP js=K x×P e=0.7×39.33=27.531kWQ js=P js×tgφ=27.531×0.48=13.215kvar(17)、管理人员办公室打印机K x=0.7,Cosφ=0.9,tgφ=0.48将J c=60%统一换算到J c1 =70%的额定容量P n=0.02kWP e=n×(J c/J c1)1/2×P n=20×(0.6/0.7)1/2×0.02=0.152 kWP js=K x×P e=0.7×0.152=0.1064kWQ js=P js×tgφ=0.1064×0.48=0.0511kvar(18)、厨房排气扇K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×0.1×1=0.065kWQ js=P js×tgφ=0.065×0.75=0.04875kvar(19)、蒸饭机K x=0.65,Cosφ=0.8,tgφ=0.75P js=0.65×6×1=3.9kWQ js=P js×tgφ=3.9×0.75=2.925kvar(20)、室外照明K x=0.8,Cosφ=0.7,tgφ=1.02将J c=60%统一换算到J c1 =70%的额定容量P n=0.024kWP e=n×(J c/J c1)1/2×P n=30×(0.6/0.7)1/2×0.024=0.63kWP js=K x×P e=0.8×0.63=0.504kWQ js=P js×tgφ=0.504×1.02=0.515kvar一号取电点:总的负荷计算,总箱同期系数取Kx=0.85总的有功功率:P js=K x×ΣP js=0.85×(7.15+9.75+2.4+3.9+1.2+27.9045+ 22.75+7.8+10.5+1.43+28.6+10.5+21+9.975+2.66+27.531+ 0.1064+0.065+3.9+0.504)=203.6259kW总的无功功率:Q js=K x×ΣQ js=0.85×(1.3625+7.3125+1.488+2.925+3.9+20.93+17.1+1.85+10.71+0.69+13.728+1.04+10.08+4.788+1.2768+13.215+0.0511+0 .04875+2.925+0.515)=127.94 kvar总的视在功率S js=(P js2+Q js2)1/2=(203.62592+127.942)1/2=240.48kVA1.3.3、变压器的选择:根据计算的总的视在功率与最大干线功率(以单个开关箱的最大功率逐级计算选择)取大值选择S11-400/10型三相电力变压器,它的容量为400kVA>240.48kVA能够满足使用要求,其高压侧电压为10kV同施工现场外的高压架空线路的电压级别一致。
临时用电计算书
工地临时用电计算书依据《低压配电设计规范》GB50054-95中国建筑工业出版社《建筑工程施工现场供电安全规范》GB50194-93中国建筑工业出版社《通用用电设备配电设计规范》GB50055-93中国建筑工业出版社《供配电系统设计规范》GB50052-95中国建筑工业出版社《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社一、施工条件施工现场用电量统计表二、设计内容和步骤1、现场勘探及初步设计:(1)本工程所在施工现场范围内无各种埋地管线。
(2)现场采用380V低压供电,设一配电总箱,内有计量设备,采用TN-S系统供电。
(3)根据施工现场用电设备布置情况,采用导线穿钢管埋地敷设,布置位置及线路走向参见临时配电系统图及现场平面图,采用三级配电,两极防护。
(4)按照《JGJ46-2005》规定制定施工组织设计,接地电阻R≤4Ω。
2、确定用电负荷:(1)高压汞灯(2台)K x = 0.6,Cosφ= 0.7,tgφ= 1.02P js = K x×P e = 0.6×6 = 3.6kWQ js = P js×tgφ= 3.6×1.02 = 3.672kvar(2)塔式起重机(2台)K x = 0.85,Cosφ= 0.6,tgφ= 1.333P js = K x×P e = 0.85×96 = 81.6kWQ js = P js×tgφ= 81.6×1.333 = 108.773kvar(3)交流电焊机K x = 0.5,Cosφ= 0.4,tgφ= 2.291P js = K x×P e = 0.5×9 = 4.5kWQ js = P js×tgφ= 4.5×2.291 = 10.31kvar(4)钢筋切断机K x = 0.65,Cosφ= 0.7,tgφ= 1.02P js = K x×P e = 0.65×5.5 = 3.575kWQ js = P js×tgφ= 3.575×1.02 = 3.647kvar(5)钢筋调直机K x = 0.65,Cosφ= 0.7,tgφ= 1.02P js = K x×P e = 0.65×11 = 7.15kWQ js = P js×tgφ= 7.15×1.02 = 7.293kvar(6)钢筋弯曲机K x = 0.65,Cosφ= 0.7,tgφ= 1.02P js = K x×P e = 0.65×3 = 1.95kWQ js = P js×tgφ= 1.95×1.02 = 1.989kvar(7)交流电焊机P js = K x×P e = 0.5×9 = 4.5kWQ js = P js×tgφ= 4.5×2.291 = 10.31kvar (8)平板式振动器K x = 0.3,Cosφ= 0.7,tgφ= 1.02P js = K x×P e = 0.3×1.1 = 0.33kWQ js = P js×tgφ= 0.33×1.02 = 0.337kvar (9)插入式振动器(3台)K x = 0.3,Cosφ= 0.7,tgφ= 1.02P js = K x×P e = 0.3×4.5 = 1.35kWQ js = P js×tgφ= 1.35×1.02 = 1.377kvar (10)木工圆锯(6台)K x = 0.65,Cosφ= 0.6,tgφ= 1.333P js = K x×P e = 0.65×18 = 11.7kWQ js = P js×tgφ= 11.7×1.333 = 15.596kvar (11)碘钨灯(10台)K x = 0.6,Cosφ= 0.6,tgφ= 1.333P js = K x×P e = 0.6×5 = 3kWQ js = P js×tgφ= 3×1.333 = 3.999kvar (12)自落式混凝土搅拌机(4台)K x = 0.75,Cosφ= 0.85,tgφ= 0.62P js = K x×P e = 0.75×60 = 45kWQ js = P js×tgφ= 45×0.62 = 27.9kvar (13)真空吸水泵K x = 0.75,Cosφ= 0.8,tgφ= 0.75P js = K x×P e = 0.75×5.5 = 4.125kWQ js = P js×tgφ= 4.125×0.75 = 3.094kvar (14)建筑施工外用电梯(2台)P js = K x×P e = 0.85×22 = 18.7kWQ js = P js×tgφ= 18.7×1.333 = 24.927kvar(15)总负荷计算总的有功功率P js = K x×ΣP js = 0.9×191.08 = 171.972kW总的无功功率Q js = K x×ΣQ js = 0.9×223.224 = 200.902kvar总的视在功率S js = (P js2 + Q js2)1/2 = (171.9722+200.9022)1/2 = 264.454kVA总电流计算I js = S js / (1.732 ×U e) = 264.454 / (1.732 ×0.38) = 401.808A3、干线进线截面及进线开关在选择前应对照平面图和系统图先由用电设备至开关箱计算,再由开关箱至分配箱计算,选择导线及开关设备。
、、、工程临电计算书(定稿)
附件:临时用电计算书一、负荷计算1#总配电箱用电设备及参数表编号用电设备名称与型号铭牌技术数据换算后设备容量Pe1 闪光对焊机90KVA JC=15% 29.632 1#施工电梯33KW 333 2#施工电梯33KW 334 楼层移动箱30KW 305 楼层移动箱30KW 306 塔式起重机 QTZ4708 28.5KW JC=25% 28.57 塔式起重机 QTZ4708 28.5KW JC=25% 5.78 电焊机20KW 209 木工车间7KW 710 木工车间7KW 711 现场照明7KW 712 现场照明7KW 713 钢筋调直机6KW 614 1#钢筋弯曲机3KW 315 2#钢筋弯曲机3KW 316 型材切割机3KW 317 1#钢筋切断机 1.5KW 1.518 2#钢筋切断机 1.5KW 1.5合计255.83设备容量及计算负荷总箱下电气设备组成一个设备组,总需要系数Kx=0.6,综合功率因数Cosφ=0.7,总计算负荷为P j =Kx∑Pe=0.6×255.83=153.50KWQ j = Pjtgφ=153.50×1.02=156.57KvarSj= P j2+ Q j2=153.50 2+156.57 2=219.26KVAI j =Sj=219.26=333.14A 3×Ue 1.732×0.38总箱至1#楼分配电箱的计算负荷功率因数Cosφ=0.8,Pj=5.7+30+7+7=49.7KW,Q j =Pjtgφ=49.7×0.75=37.28KvarSj= P j2+ Q j2=49.7 2+37.28 2=62.13KVAI j =Sj=62.13=94.40A 3×Ue 1.732×0.38总箱至6#楼分配电箱的计算负荷功率因数Cosφ=0.8,Pj=30+7+28.5+7=72.5KW,Q j =Pjtgφ=72.5×0.75=54.38KvarSj= P j2+ Q j2=72.5 2+54.38 2=90.63KVAIj=Sj=90.63=137.70A3×Ue 1.732×0.38总箱至施工电梯的计算负荷功率因数Cosφ=0.8,Pj=33+33=66KW,Q j =Pjtgφ=66×0.75=49.50KvarSj= P j2+ Q j2=66 2+49.50 2=82.50KVAIj=Sj=82.50=125.35A3×Ue 1.732×0.38总箱至钢筋车间的计算负荷功率因数Cosφ=0.8,Pj=29.63+3+3+1.5+1.5+6+20+3=67.63KW,Q j =Pjtgφ=67.63×0.75=50.72KvarSj= P j2+ Q j2=67.63 2+50.72 2=84.54KVAIj=Sj=84.54=128.45A3×Ue 1.732×0.382#总配电箱用电设备及参数表编号用电设备名称与型号铭牌技术数据换算后设备容量Pe1 混凝土输送泵90KW 902 塔式起重机 QTZ4708 28.5KW JC=25% 28.53 塔式起重机 QTZ4708 28.5KW JC=25% 28.54 楼层移动箱25KW 255 楼层移动箱25KW 256 办公区动力10KW 107 1#生活区回路8KW 88 施工现场8KW 89 2#生活区回路7KW 710 木工车间7KW 711 木工车间7KW 712 现场照明7KW 713 现场照明7KW 714 照明7KW 715 办公区照明5KW 5合计270.00设备容量及计算负荷总箱下电气设备组成一个设备组,总需要系数Kx=0.6,综合功率因数Cosφ=0.7,总计算负荷为P j =Kx∑Pe=0.6×270=162.00KWQ j = Pjtgφ=162.00×1.02=165.24KvarSj= P j2+ Q j2=162.00 2+165.24 2=231.40KVAI j =Sj=231.40=351.59A 3×Ue 1.732×0.38总箱至2#楼分配电箱的计算负荷功率因数Cosφ=0.8,Pj=25+7+28.5+7=67.5KW,Q j =Pjtgφ=67.5×0.75=50.63KvarSj= P j2+ Q j2=67.5 2+50.63 2=84.38KVAI j =Sj=84.38=128.21A 3×Ue 1.732×0.38总箱至3#楼分配电箱的计算负荷功率因数Cosφ=0.8,Pj=25+7+28.5+7=67.5KW,Q j =Pjtgφ=67.5×0.75=50.63KvarSj= P j2+ Q j2=67.5 2+50.63 2=84.38KVAIj=Sj=84.38=128.21A3×Ue 1.732×0.38总箱至地下停车库的计算负荷功率因数Cosφ=0.8,Pj=7+90+8=105KW,Q j =Pjtgφ=105×0.75=78.75KvarSj= P j2+ Q j2=105 2+78.75 2=131.25KVAIj=Sj=131.25=199.42A3×Ue 1.732×0.38总箱至办公区生活区的计算负荷功率因数Cosφ=0.8,Pj=5+10+8+7=30KW,Q j =Pjtgφ=30×0.75=22.50KvarSj= P j2+ Q j2=30 2+22.50 2=37.50KVAI j =S j=37.50 =56.98A3×Ue1.732×0.38二、 选择导线与配电箱开关电器按允许温升初选电缆芯线截面,然后按电压偏移和机械强度校验。
施工临时用电方案计算书
施工临时用电方案计算书
本计算书根据《建筑施工计算手册》江正荣着、《施工现场临时用电安全技术规范》
JGJ 46-2005。
一、用电量计算:
;
,则有:
---------------------------------------------------------------------------------
序号机具名称型号额定功率(kW) 距离电源(m) 台数
1 塔吊 Q 80.00 20.0 1
---------------------------------------------------------------------------------
路必须采用五芯电缆):
其中 I l──线路工作电流值(A);
U l──线路工作电压值(V),三相四线制低压时取380V。
经过计算得到 I l =2×p0=2×104.16=208.32A。
根据上式计算所得结果,查《建筑施工计算手册》P1084表18-24得出以下铜芯导线类型及其
截面积分可供选择:
TJ型铜裸线──35.00mm2
BX型铜芯橡皮线──50.00mm2
2
46.3;
2
由导线的允许电流及导线的允许电压降校核,分别计算出的导线截面进行比较,取大值;
最后得出如下结果供使用者参考选择:
TJ型铜裸线──35.00mm2
BX型铜芯橡皮线──50.00mm2
BV型铜芯塑料线──50.00mm2
注:三相四线制线路的N线和PE线截面不小于相线截面的50%,单相线路的零线截面与相线截面相同。
临时用电专项方案计算书
一、工程概况项目名称:XX住宅小区临时用电工程工程地点:XX市XX区XX街道建设单位:XX房地产开发有限公司施工单位:XX建筑工程有限公司二、编制依据1. 《施工现场临时用电安全技术规范》(JGJ46-2005)2. 《低压配电设计规范》(GB50054-2011)3. 《建筑工程施工现场供电安全规范》(GB50194-93)4. 《通用用电设备配电设计规范》(GB50055-93)三、计算内容1. 临时用电负荷计算根据现场施工图纸和设备清单,统计各类用电设备的额定功率,计算总负荷。
(1)照明负荷:照明灯具总功率为10kW,负荷系数取0.7,则照明负荷为7kW。
(2)动力负荷:空调、水泵、风机等设备总功率为50kW,负荷系数取0.7,则动力负荷为35kW。
(3)插座负荷:插座总功率为30kW,负荷系数取0.7,则插座负荷为21kW。
(4)总负荷:照明负荷 + 动力负荷 + 插座负荷 = 7kW + 35kW + 21kW = 63kW。
2. 临时用电线路选择根据总负荷和施工现场实际情况,选择合适的导线截面和电缆类型。
(1)照明线路:照明负荷为7kW,采用RVV-21.5mm²导线,满足安全规范要求。
(2)动力线路:动力负荷为35kW,采用YJV-36mm²电缆,满足安全规范要求。
(3)插座线路:插座负荷为21kW,采用RVV-21.5mm²导线,满足安全规范要求。
3. 临时用电配电箱设计根据现场用电需求,设计临时用电配电箱。
(1)配电箱容量:总负荷为63kW,采用断路器额定电流为100A的配电箱。
(2)配电箱接线:照明、动力、插座分别接入配电箱的不同回路。
(3)配电箱保护:设置漏电保护器、过载保护器等安全保护装置。
四、计算结果1. 临时用电负荷:63kW2. 临时用电线路:照明线路采用RVV-21.5mm²导线,动力线路采用YJV-36mm²电缆,插座线路采用RVV-21.5mm²导线3. 临时用电配电箱:容量为100A,照明、动力、插座分别接入配电箱的不同回路,设置漏电保护器、过载保护器等安全保护装置五、结论根据上述计算,本临时用电工程满足安全规范要求,能够保证施工现场的用电需求。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
一、编制依据
《建筑工程施工现场供电安全规范》GB50194-93
《通用用电设备配电设计规范》GB50055-93
《施工现场临时用电安全技术规范》JGJ46-2005
《建筑施工安全检查标准》JGJ59-99
二、用电总平面布置
本次方案为三期(19#20#21#22#)楼施工用电。
常用电源由临电专用变压器(500KVA)提供,备用电源由440KW发电机提供,在临电总配电室转换后再引至各栋一级配电柜。
从一级配电柜引至二级配电箱、再从二级配电箱引至三级配电箱。
各配电系统及位置及线路走向详见平面布置图。
三、用电线路布局
本工程供电线路采用TN-S三相五线制,由原临电变压器(500KVA)及发电机(440KW)经转换后提供电源引至临电配电房的总配电箱,由总配电房引出线(漏电设定:150mA/0.1s)到三期各栋一级配电柜(漏电设定:100mA/0.1s),施工加工区,施工机械设备处设置二级配电箱(漏电设定:50mA/0.1s)、生活区设置一个二级配电箱,由二级配电箱引出至各设备用电三级箱(漏电设定:30mA/0.1s)。
四、施工用电量
施工现场用电量统计表(钢筋加工及木工加工):
施工现场用电量统计表(水电加工):
施工现场用电量统计表(混凝土):
施工现场用电量统计表(塔吊.施工电梯):
生活区用电量统计表:
五、用电布置
1、现场情况:
(1)本工程主电源由临电总转换柜经二期地下室明敷设至各一级配电箱,二级箱引至三级箱采用架空/埋地敷设。
(2)现场采用TN-S系统供电(交流三相五线制380V供电),接地系统采用重复。
(3)根据施工现场用电布置情况,总出线柜分为2台(二期1台,三期1台位置及线路走向参见平面布置图,采用二级配电,三级保护。
2、用电负荷:
总有功荷载计算,取同期系数KP=0.8
P总1=KP×(73.25+42.28+23.86+253.9+10.06)=403KW
总无功荷载计算,取同期系数KP=0.70
P总2=KP×(24.9+90.7+3.8)=95.52KW
总视在功率
S js =(P总12 +P总22)1/2= (403.2+95.522)1/2 = 414.6kVA
总电流计算
I js = S j s/(1.732×U e) = 414/(1.732×0.38) = 709.5 A
3、导线选择
根据铝芯导线的载流量查得240平方的导线明敷设时载流量为483.8A,所以三相五线架空线路采用3×240+2×120的铝芯导线架空敷设
六、安全用电要求及措施
一、用电要求
1、按照《建设工程施工现场供用电安全规范》的规定采用专用保护零线的TN-S接零保护,采用三相五线制供电。
2、所有机械及各线路的终端,必须就近重复接地。
3、所有电线、电缆均采用保护套管,电线电缆不得用裸金属线绑扎。
4、水平架设线缆的高度必须符合安全技术规范要求,凡汽车通道的跨越线路无法按高度架设时,应采用钢管埋地敷设,深度应不小于50cm。
5、单相用电设备的使用应考虑相间平衡。
二、用电安全措施
1、施工用电设备必须按规定接地接零,并装有二级防漏电保护开关,电工必须持证上岗,并经常进行全部电器设备的安全检查,现场电线线路采用三相五线制,并有保护接零专用线,落地屏/柜做防雨及周围防护,开关箱安放高度不小于1.5m,非现场电工人员一律不得移动及拆装场地内电气/器设备。
每天开工前须先检查防漏电开关有无失灵。
2、每台用电设备应有各自专用的开关箱,必须实行“一机一闸”制,严禁用同一个开关电器直接控制二台用电设备(含插座)。
3、开关箱内的开关电器必须能在任何情况下都可以使用电设备实行电源隔离,及开关箱内必须装置漏电保护器。
4、配电箱、开关箱内的电器必须可靠完好,不准使用破损、不合格的电器。
5、配电箱和开关箱的金属箱体及所有用电设备的金属外壳等必须接地作保护。
箱体门要完好无损,并能加锁,及要有防雨、防尘的保护措施,有危险标志。
配电箱、开关箱统一编号由持证专职电工管理。
6、施工现场每月应进行用电设备及接地电阻测量并做好记录。
7、施工机械操作人员在开动机械前要进行机械设备的安全状况检查,检查机械的油、水、钢丝绳等是否符合安全要求才能开机。
发现问题应及时排除,重大问题及时上报单位领导及公司主管部门,确保安全生产。
附件:临时用电平面布置图。