架梁方案汇报材料
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
目录
一、T梁架设计划: ·········································································- 1 -
1、月份T梁架设计划:································································- 1 -
2、T梁架设节点工期安排 ·····························································- 2 - 2.1、单导梁架桥机·········································································- 2 -
2.2、双导架桥机············································································- 4 -
3、T梁架设通路:·······································································- 4 -
二、T梁预制计划:·······································································- 5 -
1、月份预制T梁需求计划: ························································- 6 -
三、T梁运输计划:·······································································- 6 -
1、T梁运输方式 ············································································- 6 - 1.1、铁路运输:·············································································- 7 -
1.2、公路运输:·············································································- 7 -
2、月份T梁运输计划:································································- 7 -
架梁方案汇报材料
哈尔滨西客运站工程总计架设T梁592片。
其中24mT梁137片(包括Ⅰ标12片、Ⅲ标9片)、32mT梁455片(包括Ⅲ标93片)。
T梁架设由一台180T单导梁架桥机及一台160T双导梁架桥机架设。
其中单导梁架桥机架设T梁463片(包括Ⅲ标102片)、双导架桥机架设T梁129片(包括Ⅰ标12片)。
一、T梁架设计划:
以下计划按照高速场9月1日联调链试考虑到T梁架设给桥面系、铺轨等站后工程提供空间后,确定以2011年7月31日为节点工期的架设计划。
1、月份T梁架设计划:
2010年12月架设T梁68片(西场正线哈侧44片(双导)、沈侧24片(单导))
2011年1月架设T梁67片(西场正线哈侧37片(双导)、沈侧12片及西场联络左线18片(单导))
2011年3月架设T梁54片(架设开始日期2011年3月16日)(动左18片、东场右线18片、东场左线18片)(单导)
2011年4月架设T梁84片(西场正线58片及既有右线26片)(单导)
2011年5月架设T梁131片(动右22片(单导)、西场正线
36片(双导)跨线联络右线49片(单导)既有左线24片(单导)2011年6月架设T梁67片(东场岔线33片(单导)东场右线14片(单导)东场左线7片(单导)Ⅰ标站房12片(双导)2011年7月架设T梁102(Ⅲ标哈前特大桥(单导))
2011年9月架设T梁20片(由于跨线联络线连续梁节点工期控制剩余20片(单导))
2、T梁架设节点工期安排
2.1、单导梁架桥机
2010年12月20日~2011年1月18日架设西场正线及联络左线54片T梁。
架桥机在2011年3月10日前在动车左线王岗砖厂大桥0#台后组装试吊,面向哈尔滨方向进行架设
○1、(2011-3-16~2011-3-20)架设动车左线王岗砖厂大桥T梁18片
○2、(2011-3-21~2011-3-25)东场何家沟右线大桥(0-9)T 梁18片
○3、(2011-3-26~2011-3-30)东场何家沟左线大桥(0-9)T 梁18片
○4、(2011-4-1~2011-4-15)西场何家沟正线大桥(9-14)T 梁58片
○5、(2011-4-16~2011-4-22)既有右线王岗砖厂大桥T梁26
片
(2011-4-23~2011-5-4)架桥机移动至动车右线王岗砖厂大桥拆装掉头,面向沈阳测架设
○6、(2011-5-5~2011-5-10)动车右线王岗砖厂大桥T梁22片○7、(2011-5-12~2011-5-24)跨线联络右线王岗砖厂大桥(33-13)T梁49片
○8、(2011-5-25~2011-5-30)既有左线王岗砖厂大桥T梁24片
(2011-5-31~2011-6-12)架桥机转移至跨线联络右线21号墩上部拆装,面向哈尔滨方向架侧
○9、(2011-6-13~2011-6-20)东场何家沟岔Ⅰ线T梁33片
○10、(2011-6-21~2011-6-24)东场何家沟右线(9-10)(17-23)T梁14片
○11、(2011-6-25~2011-6-28)东场何家左线(9-10)(17-19)T梁7片
架桥机拆装走哈双路将架桥机转移至Ⅲ标哈前特大桥哈台面向沈阳测(2011-6-28~2011-7-5)
○12、(2011-7-5~2011-7-31)哈前特大桥T梁102片
2011年8月25前将架桥机转移至跨线联络右线14号墩上部面向沈阳侧
○13、跨线联络右线(13-12)(9-0)T梁20片(2011-9-1~2011-9-6)
2.2、双导架桥机
架桥机在西场何家沟大桥27号台后组装试吊
2010年12月10日~2011年1月19日架设西场正线81片T 梁。
○1、(2011-5-1~2011-5-15)西场何家沟大桥正线(18-14)T梁36片
架桥机转移至Ⅰ标站房(2011-5-15~2011-5-30)
○2、Ⅰ标站房T梁12片(2011-6-1~2011-6-5)
3、T梁架设通路:
为保障T梁架设运梁线路的畅通在夏家存梁场至西场何家沟正线及动车走行左线0#台、既有右线王岗砖厂大桥0#台铺设一条长2.0km的架梁运梁通道。
1、由夏家存梁场经由王岗砖厂至西场何家沟0号台后铺设一条650mT梁运输通道。
2、插入9号单开道岔7组
○1、GK922+050处设置一组右开道岔(1号道岔)
○2、GK922+750处设置一组右开道岔(2号道岔)
○3、GK922+800处设置一组右开道岔(3号道岔)
○4、DK922+750处设置一组右开道岔(4号道岔)
○5、DK922+830处设置一组左开道岔(5号道岔)
○6、跨线联络右线22墩上部设置一组右开单开道岔(6号道
岔)
○7、西场何家沟正线大桥12号墩上部设置一组右开单开道岔
(7号道岔)
3、Ⅲ标段T梁由于无法使用夏家存梁场,为确保哈前特大桥
架梁按规定时间完成,经现场调查,拟采取在对应哈大客专里
程DK920+100处木材专用线上增设一组P50-9#单开道岔(右
开),同时在动车左线DdzK920+780处增设一组P50-9#单开道
岔(左开),使之相连接,形成架梁通道。
二、T梁预制计划:
按T梁架设节点工期推算T梁预制生产计划
结止12月10日已预制完成T梁183片(其中达到架设条件147片,未张拉37片)将未张拉37片T梁计入剩余预制梁生放计划当中,以下计划按T梁总数592片T梁已完成147片剩余445片T 梁计算(其中完成147片T梁包括2010年架设的135片T梁、动车左线王岗砖厂大桥4片、东场何家沟右线8片)
预制T梁从浇筑砼至达到架设条件需28日(14天终张、2天注浆、7天停滞期、5天防水)
以下计划按T梁从生产至架设31天计算,根据T梁架设节点工期推算T梁预制最迟开始日期为2011年2月10日
1、月份预制T梁需求计划:
(以下计划为每月架设T梁需求量)
2011年2月份预制42片T梁(动左14片、东场右线(0-9)10片、东场左线(0-9)18片)
2011年3月份预制96片T梁(西场正线(9-14)58片、既有右线26片、西场正线(18-14)12片)
2011年4月份预制119片T梁(动右22片、西场正线(14-18)24片、跨线联络右线(33-13)49片、既有左线24片)
2011年5月份预制94片T梁(东场岔Ⅰ线33片、东场右线(9-23)14片、东场左线(9-19)7片、跨线联络右线(12-0)20片Ⅰ标站房12片、Ⅲ标哈前大桥8片)
2011年6月份预制94片T梁(Ⅲ标哈前大桥94片)
从以上预制计划看,现梁场的预制生产能力很难保证施工工期的顺利完成,必须采取有效措施增加T梁预制生产能力及进行冬施施工才能保证节点工期的顺利完成。
故我部与梁场协商马上采取冬期措施恢复施工生产并增加6个台座、2套32m梁模板、1套24m梁模板及一台大吨位吊车。
采用此项措施后约需增加570万的投入
三、T梁运输计划:
1、T梁运输方式
T梁运输:分为铁路运输(单导梁架设T梁)与公路运输(双
导梁架设T梁)两种运输方式。
1.1、铁路运输:
从齐齐哈尔梁场发车运至哈尔滨顾乡站后由我部轨道车到顾乡站走既有哈大线经由哈屯上行线在K0+527.226里程处插入临1#道岔进入夏家存梁场。
哈局运输处2010年为我部提供DLⅠ型运输车12组,每日发车6组可运输6片T梁。
每3日一个运输循环每日平均可到场4片T 梁。
2011年运输处考虑到我部运输量较大的情况提供DLⅠ型运输车16组以保证每日平均到场T梁4片。
1.2、公路运输:
授权哈尔滨巨力吊装运输有限公司承运
运输路线为齐齐哈尔→碾北公路→大齐公路→哈大公路→施工现场。
计划由15辆运输车运输每日发5辆车每3天一个循环。
保证每天到场5片T梁,本方案考虑到运输受其它因素的影响按每日到场4片T梁编制架设计划。
2、月份T梁运输计划:
2011年运输最迟开如日期为2011年3月1日
2010年12月份运输135片(铁路54片,公路81片)
2011年3月份运输56片(铁路运输)
2011年4月份运输96片(铁路运输68片,公路运输20片)2011年5月份运输119片(铁路运输91片,公路运输28片)2011年6月份运输94片(铁路运输)
2011年7月份运输92片(铁路运输)
哈尔滨西客运站工程架梁方案汇报
- 10 -
运 梁 便 线 道 岔 示 意 图
11
12
13。