武汉市轨道交通3号线一期设备系统工程通信工程监理细则

合集下载

通信工程旁站规定

通信工程旁站规定

通信工程旁站监理规定旁站监理是指监理人员在工程施工阶段监理中,对关键部位、关键工序的施工质量实施全过程现场跟班的监督活动。

1.目的在监理服务过程中,控制和提高关键部位、关键工序的工程质量。

2.范围本规定适用于通信工程光、电缆线路和设备工程建设的关键部位、关键工序和隐蔽工程的旁站监理。

3.职责3.1总监理工程师要确定工程的关键部位、关键工序和隐蔽工程范围(在编制监理规划或监理实施细则中明确);安排监理员旁站监理,并深入工地检查和指导旁站监理工作。

3.2专业监理工程师或监理员根据总监理工程师指令实施旁站监理工作,并制作相应的旁站监理记录。

4.程序4.1旁站监理的总体范围凡涉及通信设备、通信管道、通信线路工程的关键部位、工序和隐蔽工程,新技术、新工艺、新材料、新设备试验过程,均应实行旁站监理。

(或按委托监理合同中有明确的旁站监理范围)4.2 旁站监理的依据4.2.1通信建设工程强制性标准及其它相关法律、法规;4.2.2相关技术标准、规范、规程、施工方法;4.2.3建设工程承包合同文件、委托监理合同文件;4.2.4经批准的设计文件、施工组织文件、监理规划和监理实施细则。

4.3通信工程实施旁站监理的主要范围。

4.3.1通信线路工程实施旁站监理的主要范围4.3.1.1光缆线路路由复测,路由变更,光缆单盘测试、配盘,光缆敷设和接续,ODF架光缆成端,中继段衰耗、PMD测试等。

4.3.1.2电缆线路路由复测,路由变更,电缆单盘测试、配盘,电缆敷设和接续,MDF架电缆成端,交接箱安装,电缆气闭试验,电缆直流电阻、不平衡电阻、绝缘电阻、串音衰耗测试等。

4.3.1.3光、电缆线路特殊地段的施工,如水底光、电缆施工,特大桥樑管道光、电缆施工,超过150米的管道顶管,超过200米的架空光、电缆施工等。

4.3.1.4管道基础浇筑,人手孔基础和上覆浇筑口圈安装、内外粉刷等。

4.3.2通信线路巡、旁结合监理的主要范围4.3.2.1一般要求:巡视检查20%以上设备量的工程质量,并有检查记录。

住房和城乡建设部关于印发城市轨道交通建设工程验收管理暂行办法的通知

住房和城乡建设部关于印发城市轨道交通建设工程验收管理暂行办法的通知

住房和城乡建设部关于印发城市轨道交通建设工程验收管理暂行办法的通知文章属性•【制定机关】住房和城乡建设部•【公布日期】2014.03.27•【文号】建质[2014]42号•【施行日期】2014.03.27•【效力等级】部门规范性文件•【时效性】现行有效•【主题分类】工程质量安全监管正文住房和城乡建设部关于印发城市轨道交通建设工程验收管理暂行办法的通知建质[2014]42号各省、自治区住房城乡建设厅,直辖市建委(建交委),新疆生产建设兵团建设局:为规范城市轨道交通建设工程验收工作,提高城市轨道交通建设工程质量安全水平,我部制定了《城市轨道交通建设工程验收管理暂行办法》。

现印发给你们,请结合本地区实际,认真贯彻执行。

住房和城乡建设部2014年3月27日城市轨道交通建设工程验收管理暂行办法第一章总则第一条为规范城市轨道交通建设工程验收工作,依据《建设工程质量管理条例》、《房屋建筑和市政基础设施工程竣工验收备案管理办法》、《房屋建筑和市政基础设施工程竣工验收规定》和《城市轨道交通工程安全质量管理暂行办法》等有关规定,结合城市轨道交通工程建设的实际,制定本办法。

第二条本办法所称城市轨道交通是指采用专用轨道导向运行的城市公共客运交通系统,包括地铁、轻轨、单轨、磁浮、自动导向轨道等系统。

第三条本办法适用于新建、扩建、改建城市轨道交通建设工程的验收活动及其监督管理。

第四条国务院住房城乡建设主管部门对全国城市轨道交通建设工程验收实施统一监督管理。

县级以上地方人民政府住房城乡建设主管部门负责本行政区域内城市轨道交通建设工程验收的监督管理,具体工作可委托所属工程质量监督机构实施。

县级以上地方人民政府有关部门按照法律法规规定负责相关的专项验收。

第五条城市轨道交通建设工程验收除应执行本管理办法外,还应符合国家、行业等有关规定和标准。

第六条城市轨道交通建设工程验收分为单位工程验收、项目工程验收、竣工验收三个阶段。

单位工程验收是指在单位工程完工后,检查工程设计文件和合同约定内容的执行情况,评价单位工程是否符合有关法律法规和工程技术标准,符合设计文件及合同要求,对各参建单位的质量管理进行评价的验收。

通信工程监理实施细则(全)

通信工程监理实施细则(全)

通信工程监理实施细则通信工程施工监理工作,在总监理工程师的领导下,依据铁道部有关标准、规范、规程以及本项目的设计文件、工程监理合同、审批合格的施工图文件,协助建设单位以控制投资、进度、质量、安全为核心,对工程建设施工进行监督、管理和服务。

为使本工程项目全面实现优质、高效、安全的各项目标。

特制定本工程施工监理细则。

一、工程特点及技术、质量标准1.1工程概况及特点为适应时速200公里客货共线的铁路运输目的对通信提出了更高的要求,要求其通信系统更具有可靠性,确保行车的安全畅通及高效率运营。

1.1.1本工程通信网由承载网、业务网和支撑网组成。

通信网的设计主要包括传输及接入系统、电话交换系统、调度通信系统、移动通信系统、站间行车电话机及其它通信系统。

车站场通信系统、会议电视电话系统、应急通信系统及其它通信系统。

1.1.2本工程对既有光接入网的传输部分进行更新改造,利用新设20芯光缆的2芯光纤开通基于SDH-622Mb∕s的光传输系统,网管设于银川通信站。

1.13利用地区光缆开通基于SDH-155Mb∕s的光接入网系统,就近在车站接入SDH622Mb∕s光接入网系统,为新建车站站房、IokV配电所、分区所以及红外轴温监测机房等提供传输通道。

1.144本段交换网维持既有、新增自动电话通过光接入网接入既有程控交换机。

惠农通信工区、银川通信工区新设应急通信现场设备,预留接入兰州局应急通信系统中心条件。

沿线新建通信、信息机房设通信电源及环境监控系统,对通信电源及新建机房环境进行统一的集中监控,纳入银川既有通信电源及环境监控系统中心。

既有干局线传输系统设备继续使用,本工程对既有光接入网的传输部分进行改造,各站数字调度通信系统设备利旧;沿线高频开关电源设备利IBo1.2编制依据《包兰线惠农至银川段增建第二线工程HYXS-I标段施工总价承包招标文件》、有关设计图纸、资料及补遗、答疑书。

国家和铁道部、兰州铁路局颁布的现行铁路工程施工技术规范、规程、验收标准及工程建设相关文件。

通信工程监理细则

通信工程监理细则

通信工程监理细则一、绪论通信工程的监理是确保通信工程质量和进度的重要环节,本细则旨在规范通信工程监理工作,保障工程的完整性和稳定性。

二、监理单位的职责1. 监理单位应当具备相关工程监理资质和技术能力,承担监理工作。

2. 监理单位应当依据国家相关法律法规、工程监理规范和合同要求,确保工程的质量、安全和进度。

3. 监理单位应当参与工程的初步设计、施工图设计、施工方案的审查,并提出合理化建议和改进措施。

4. 监理单位应当对工程施工现场进行巡视和检查,及时发现和解决工程质量问题。

5. 监理单位应当对施工单位进行技术指导,确保施工符合相关标准和规范。

6. 监理单位应当对工程施工过程进行记录和验收,及时发现和整改施工缺陷。

7. 监理单位应当组织工程竣工验收,确保工程达到设计要求和验收标准。

三、监理工作的程序与要求1. 开工前(1)监理单位应当参与施工图设计的审查,确保工程图纸的合理性和可施工性。

(2)监理单位应当与施工单位共同编制工程施工方案,明确工程施工的具体要求和标准。

(3)监理单位应当对施工材料进行验收和检测,确保施工材料符合相关标准和规范。

2. 施工中(1)监理单位应当定期巡视施工现场,检查施工进度和施工质量。

(2)监理单位应当及时处理施工变更和工程质量问题,并书面通知施工单位和建设单位。

(3)监理单位应当参与施工单位的安全管理工作,确保施工过程中的人身安全和财产安全。

3. 竣工验收(1)监理单位应当组织工程竣工验收,与建设单位一同对工程进行全面检查和评估。

(2)监理单位应当对工程竣工资料的齐全性和准确性进行核查。

(3)监理单位应当在竣工验收报告中明确工程的质量状况和达到的技术指标。

四、监理费用与支付1. 监理费用应当由建设单位支付给监理单位,支付方式和周期按照合同规定执行。

2. 监理单位应当提供真实、完整的监理费用清单和报告,确保费用支付的合法性和合理性。

3. 建设单位与监理单位应当协商解决相关费用支付争议,如无法达成一致,可寻求法律途径解决。

铁路通信监察详细说明

铁路通信监察详细说明

通信工程监理实施细则一. 工程概况二.工程范围三.编制依据四、专业工程特点温福铁路通信糸统是为本铁路数据、语音、视频图像等应用系统提供基础网络平台,为铁路正常、安全运营提供基础保障。

铁路运营、管理和维护人员通过通信系统传输的数据、语音、视频图像信号进行通信,从而实现对铁路的运营管理和控制。

通信系统是由可独立运行操作的各子系统组成的,但各子系统之间又是相互联系、相互协调的,因此,通信系统又是一个集成系统。

温福线通信系统具备高可靠性、高可用性、可维护性及可扩展性等要求,设备采用模块化设计,便于系统升级和扩展。

通信系统为温福线运营调度、旅客服务、经营管理、防灾安全监控等业务应用系统提供网络服务,并为运输提供高质量的语音、数据及图像通信业务。

通信系统满足与既有通信系统互联的需要。

五.监理工作流程施工阶段建设监理工作的主要内容为工程质量控制、工程进度控制、工程投资控制、施工安全控制、合同管理、信息管理及组织协调主要工作内容如下:1. 熟悉施工图纸,并参与图纸会审和设计交底。

2.审查施工单位提报的施工组织设计、施工方案,提出审核意见,并监督其实施。

3.审核并确认总承包单位选择的分包单位。

4.监督承包单位严格按照施工图纸及有关文件,并遵照国家及铁道部发布的政策、法令、法规、规范、规程、标准及管理程序施工,控制工程质量及进度。

5.审查主要建筑材料、构配件、主要设备的订货,审核其质量、性能是否满足设计要求及有关规范、现行政策、法令的规定。

6. 审核及会签工程变更文件,参与对工程质量问题的处理。

7. 协调建设单位与承包单位的争议,检查工程进度情况,协调各方之间的关系,处理需要解决的问题。

8. 监督施工现场安全防护、消防、文明施工及环保卫生情况,并提出改进意见。

9. 组织工程阶段性验收及竣工预验收,提出工程质量评估报告。

10. 参加工程竣工验收。

11. 保修阶段进行定期回访;对建设单位反映的工程质量缺陷进行检查和记录,并对质量缺陷原因及责任进行调查和确定责任归属,对承包单位在保修书规定的内容和范围内质量缺陷修复的质量进行检查监督验收。

通信工程割接监理细则

通信工程割接监理细则

通信工程割接实施监理细则一、割接概述1、为加强监理在通信工程割接中的安全生产管理,保障人身、通信设备和网络安全,提高工程施工质量、加快工程进度和预防割接风险,提升监理对割接工程项目的管理能力,根据有关法规和规范,结合武汉电信工程割接实际情况,特编制本监理细则。

2、本细则所称通信工程割接,是指各类通信传输、交换、数据、管线等专业对已承载业务的网络系统中的线路、电路/链路、端口、板卡、设备等网络资源进行有计划的割接(或维护)操作,如退铜、交换机退网、搬迁、调整和升级等操作。

二、基本原则1、坚持以用户正常通信为先的原则,在保障通信网络设备正常运行的前提下进行割接工作。

2、割接方案不确切不割接,割接所需资料不准确不割接。

3、国家重大活动和重要通信期间不割接。

4、未接到建设方书面通知不割接,5、建设方未通知用户前不割接,准备工作不充分不割接,线路、设备验收不通过不割接。

6、施工单位提交的割接组织方案会签不齐全或审批未通过不割接。

三、割接实施前的监理工作1、组织建设相关单位人员进行割接工程设计会审,相关人员签字确认。

2、督促施工单位割接方案制定好后,必须在割接前三天呈报建设方,由其组织施工、监理、维护及技术支撑等部门共同审核,监理人员应严格审核施工单位提交的割接组织方案和割接报告,监理人员要认真审核批准并提出审批意见,督促施工单位及时送达建设单位项目经理和区分公司建设主管。

3、监理人员重点审核:(1)施工单位成立的业务割接组织机构、人员配置和任务分工;(2)车辆、仪表、工具等用具配置和材料准备情况;(3)割接的目的、主要内容和工作量;(4)割接时间(割接开始时间-预计割接完成时间);(5)割接的地点和路由;(6)交接箱和测试机房;(7)与相关单位主要负责人联系和沟通;(8)熟悉割接流程、风险源等级识别和应急预案。

4、组织和参加割接工作会议。

5、督促施工单位核对割接资料与实际是否相符,提前安排线路小组在割接点复核被割接光/电缆的型号、芯数、管孔位置和路由复测。

地铁监测监理细则

地铁监测监理细则

. . .. . .目录一、编制依据2二、工程概况3三、本工程监理组织与管理流程4四、本工程的监测容、测点布置及监测方法51、主要监测容52、现场监测工程包括但不限于以下容53、监测实施容54、监测巡视工程75、监测巡视容方法76、风险咨询管理效劳77、监测成果反应78、第三方监测单位与各参建方联动机制9五、监理工作方法与措施101、监测监理事前控制102、监测监理事中控制113、监测监理事后控制11第六章工程及周边环境描述和监测技术相关参数111、各车站和区间基坑监测等级112、监测工程频率及精度一般性要求13一、监理细则编制依据1.建立单位与施工单位签定的施工合同2.“建筑变形测量规“〔JGJ8—2007〕3.“建筑基坑工程监测技术规“GB50497-2009.. .专4.“地下铁道工程施工及验收规“GB50299-19995.“建筑地基根底工程施工质量验收规“〔GB50202-2002〕6.“建立工程监理规“〔GB50319-2000〕7.“城市轨道交通工程工程建立标准“建标104-2008。

8.“铁路隧道设计规“〔TB10003-2005、J449-2005〕。

9.“建筑工程抗震设防分类标准“〔GB50223-2008〕。

10.“建筑抗震设计规“GB50011-2010〕。

11.“铁路工程抗震设计规“GB50111-2006〔2009年版〕。

12.“建筑地基根底设计规“〔GB 50007-2011〕。

13.“建筑构造荷载规“GB50009-2012。

14.“混凝土构造工程施工质量验收规“GB50204-2002〔2011年版〕。

15.“盾构法隧道施工与验收规“〔GB50446-2008〕。

16.“建筑桩基技术规“〔JGJ 94-2008〕。

17.“工程初勘阶段岩土工程勘察报告“〔2014年4月〕。

18.总体组开放的线路、行车和车站建筑等资料〔2014年4月〕。

19.沿线控制性建构筑物及地下管线资料,2014年4月。

关于发布《信息通信工程监理服务计费规则(试行)》的通知(通企〔2021〕65号)

关于发布《信息通信工程监理服务计费规则(试行)》的通知(通企〔2021〕65号)
本计费规则由中国通信企业协会通信工程建设分会负责解释,工业和信息化部通信工程定 额质监中心负责日常管理维护。在执行过程中,请各单位注意发现问题,随时将有关意见和建 议反馈给工业和信息化部通信工程定额质监中心(地址:北京市西城区宣武门西大街 28 号院 大成广场 A 座 13 层,邮编 100053 ),以供今后修改时参考。 主编单位:中国通信企业协会(通信工程建设分会)
I
1 总则
1.0.1 为贯彻执行国家有关法律法规,规范信息通信工程监理工作计价行为,统一监理工作 内容及计费方法,制定本计费规则。 1.0.2 本计费规则适用于信息通信建设工程监理费的计费活动。 1.0.3 信息通信建设工程监理费用的计取活动遵循科学、公正、公平的原则。 1.0.4 在执行本规则时,还应执行国家和信息通信行业主管部门现行的有关规范、强制性标 准的规定。
3.对设备制造过程进行监督和检查,对主要及关键零部件的制造工序进行抽检。 当发生质量失控或重大质量事故时,由总监理工程师签发暂停令,提出处理意见。
4.对设备制造检验结果进行审核确认,不符合测量要求时,要求设备制造单位进行整 改、返修或返工。
5.审查设计变更,并协调处理因变更引起的费用和工期调整,同时报建设单位批准。 6.参加设备整机性能检测、调试和出厂验收,符合要求后应予以签认。 7.检查设备制造单位对待运设备采取的防护和包装措施,并检查是否符合运输、装卸、 存储、安装的要求,以及随机文件、装箱单和附件是否齐全。 8.参加设备制造单位按合同约定与接收单位的交接工作。 9.按设备制造合同的约定审查设备制造单位提交的付款申请,提出审查意见,由总监 理工程师审核后签发支付证书。 10.审查设备制造单位提出的索赔文件,提出意见后报总监理工程师,并由总监理工程
质量问题处理,组织工程预验收、现场验收,参与竣工验收等工作。 2.开展工程进度管理:施工进度计划审核及监督执行,现场进度检查、评估及协调,

通信工程专业监理实施细则

通信工程专业监理实施细则

通信工程专业监理实施细则1. 监理目的本实施细则旨在规范通信工程的监理工作,确保施工过程的合规性、质量和安全。

2. 监理职责2.1 监理人员- 监理人员应具备相关专业背景和资质,并遵守职业道德和行为准则。

- 监理人员应全程参与工程施工过程中的各个阶段,对施工质量进行监督和检验。

- 监理人员应及时向建设单位提供工程进度、质量和安全的监督报告。

- 监理人员应与施工单位建立良好的沟通和合作关系,及时协调解决可能出现的问题。

2.2 监理范围- 施工前,监理人员应审核施工单位的施工方案和技术文件,确保其符合相关技术规范和设计要求。

- 施工中,监理人员应对施工过程进行实地检查和监督,并对施工质量和安全进行评估和审核。

- 施工后,监理人员应验收竣工图纸和成果,确保其符合设计要求和标准。

- 监理人员应参与工程质量评定和验收活动,对施工单位的质量控制进行评估和监督。

3. 监理流程3.1 施工前1. 监理人员审核施工单位提交的施工方案和技术文件。

2. 监理人员与施工单位进行技术交底,明确施工要求和技术标准。

3. 监理人员组织施工单位进行施工前的准备工作,包括场地清理、设备检查等。

3.2 施工中1. 监理人员对施工过程进行监督和检查,确保施工质量符合设计要求。

2. 监理人员与施工单位进行沟通和协调,解决施工中的技术和质量问题。

3. 监理人员定期向建设单位提交施工进度、质量和安全的监督报告。

4. 监理人员组织竣工验收和交接工作,确保工程达到设计要求和标准。

3.3 施工后1. 监理人员验收竣工图纸和成果,确保其符合设计要求和标准。

2. 监理人员参与工程质量评定和验收活动,对施工单位的质量控制进行评估和监督。

3. 监理人员向建设单位提交最终的监督报告,总结工程质量和监理工作。

4. 监理记录监理人员应及时记录施工过程中的关键节点、质量问题和安全隐患,并妥善保存相关文件和资料。

5. 监理评估建设单位可以对监理人员进行定期评估,以确保监理人员的专业能力和工作质量。

通信信号监理实施细则

通信信号监理实施细则

京九铁路电气化改造工程施工监理4合同段通信信号监理实施细则中铁二院(成都)咨询监理有限责任公司京九铁路电气化改造工程监理四标项目部二○○八年八月目录第一章专业工程特点 (1)1 专业工程特点范围及重点 (1)2 信号专业工程建设的特点 (1)3 通信信号监理工作的范围及重点 (2)第二章监理工作的方法及措施 (3)一、质量控制的方法和措施 (3)二、工期控制监理工作方法及措施 (4)三、造价控制监理工作方法及措施 (6)四、合同管理监理控制方法及措施 (7)五、信息管理监理工作方法及措施 (8)六、组织协调监理工作方法及措施 (8)七、相关工程(文明施工、水保、环保)的监理工作方法及措施 (9)八、安全控制监理工作方法及措施 (10)第三章监理工作的控制要点 (13)一、通信工程监理的控制要点 (13)(一)通信设备安装工程监理的控制要点。

(13)(二)通信光(电)缆线路安装工程监理控制要点 (16)(三)通信光缆线路安装工程监理工作的控制要点 (30)(四)、铁路专用通信设备安装工程监理控制要点: (35)(五)、列车:无线调度通信工程施工监理控制要点: (35)(六)数字微波通信工程施工监理控制要点 (39)二、铁路信号工程施工监理工作的控制要点 (41)(一)铁路信号的一般规定 (41)(二〉信号工程施工前监理协助施工单位控制好以下要点: (42)(三)信号设备建筑接近限界监理控制要点 (43)(四)地面固定信号机施工监理控制要点 (48)(五)安装转辙机装置监理控制要点 (49)(六〉轨道电路施工监理控制要点 (51)(七)电缆线路施工监理控制要点 (53)(八)室内信号(含驼峰半自动、自动)设备安装监理控制要点 (57)(九)信号闭塞设备安装监理控制要点 (57)(十)机车信号设备安装监理控制要点 (57)(十一)驼峰信号设备安装监理控制要点 (58)(十二)信号电源设备安装监理控制要点 (70)(十三)其他信号设备安装监理控制要点 (71)(十四)防雷、接地装置施工监理控制要点 (71)(十五)交流电力牵引区段信号设备安装监理控制要点 (73)(十六)信号联锁试验监理控制要点 (74)铁路营业线通信、信号工程监理实施细则前言本监理实施细则,编制依据是根据《铁路建设工程监理规范》(TB10402-2007,J269-2007),《铁路通信设计规范》(TB10006-99),《铁路通信工程施工规范》(TB10205-99),《铁路通信工程质量验收标准》(TB10418-2003,J288-2004),《铁路光缆通信同步数字系列(SDH)工程施工规范》(TB10219-99),《铁路通信用户接入网设计规范》、(TB10073-2000、J80、2001),《铁路通信光纤用户接入网工程施工规范》,(TB10222-2002、J167-2002),《铁路通信电源设计规范》,(TB10072-2000、J78-2001)《铁路信号设计规范》(TB1007-99),《铁路信号施工规范》(TB10206-99),《铁路信号工程施工质量验收标准》(TB10419-2004),《铁路驼峰信号设计规范》,(TB10069-2000、J74-2001),《铁路驼峰信号施工规范》(TB10221-2000、J75-2001)和其他有关通讯、信号的技术资料及通讯信号工程建设的设计文件和监理规范,监理规则,在实施监理工作中根据实际情况进行补充修改和完善。

【铁路监理大纲】轨道交通工程监理大纲(轨道 通信 安装等)

【铁路监理大纲】轨道交通工程监理大纲(轨道 通信 安装等)

目录第一章综合说明······························································································- 1 -1.1 编制依据····································································································- 1 -1.2 工程概况····································································································- 1 -第二章监理服务范围、内容及依据 ·······································································- 7 -2.1监理服务范围·······························································································- 7 -2.2监理服务内容·······························································································- 7 -2.3监理服务的时间和期限················································································· - 11 -2.4监理工作依据····························································································· - 11 -第三章监理工作目标要求 ················································································· - 12 -3.1工程目标··································································································· - 12 -3.2进度控制目标要求······················································································· - 12 -3.3质量控制目标要求······················································································· - 12 -3.4造价控制目标要求······················································································· - 13 -3.5安全控制目标要求······················································································· - 13 -3.6管理协调要求····························································································· - 13 -3.7工程监测管理要求······················································································· - 14 -3.8工程质量检测管理要求················································································· - 14 -第四章监理机构设置、岗位职责及监理工作制度 ··················································· - 15 -4.1监理机构设置····························································································· - 15 -4.2岗位职责··································································································· - 16 -4.3项目监理人员关于专业、技术职称及年龄结构等的配备说明································· - 19 -4.4监理工作制度····························································································· - 20 -第五章监理工作程序 ······················································································· - 27 -5.1监理工作程序划分······················································································· - 27 -5.2施工准备阶段监理工作程序··········································································· - 27 -5.3施工阶段监理工作程序················································································· - 31 -5.4安全管理程序····························································································· - 54 -5.5环保控制体系程序框图················································································· - 55 -5.6依据监理规划和监理实施细则,保证监理工作··················································· - 55 -第六章监理工作重点、难点及措施 ····································································· - 57 -6.1轨道工程··································································································· - 57 -6.2气体灭火系统····························································································· - 66 -6.3火灾自动报警系统······················································································· - 71 -6.4环境与设备监控系统···················································································· - 99 -6.5安全防范系统监理要点················································································- 120 -6.6强电系统工程监理重点及措施·······································································- 124 -6.7系统测试联调····························································································- 137 -6.8系统试运行·······························································································- 138 -6.9系统验收··································································································- 138 -6.10本工程系统接口的管理 ··············································································- 139 -6.11工程进度控制重点 ····················································································- 142 -6.12造价控制重点 ··························································································- 143 -6.13项目管理协调工作重点 ··············································································- 144 -6.14安全控制的重点 ·······················································································- 146 -6.15工程环境管理的重点 ·················································································- 147 -第七章质量控制 ····························································································- 149 -7.1本工程质量控制难点分析·············································································- 149 -7.2质量控制的依据·························································································- 149 -7.3工程质量控制的原则···················································································- 149 -7.4质量目标的确定与分解················································································- 150 -7.5质量控制的主要方法···················································································- 151 -7.6质量控制点的设置与监控·············································································- 151 -7.7工程质量的事前控制···················································································- 157 -7.8施工过程中的质量控制················································································- 161 -7.9工程质量的事后控制···················································································- 166 -7.10针对本工程质量控制方面我们的工作设想 ······················································- 167 -7.11季节性施工监理工作要点及措施 ··································································- 168 -7.12针对本工程施工监理措施 ···········································································- 169 -第八章旁站监理 ····························································································- 177 -第九章进度控制 ····························································································- 181 -9.1本工程进度特点和难点分析··········································································- 181 -9.2进度控制依据····························································································- 181 -9.3工程进度控制的原则···················································································- 181 -。

通信工程监理实施细则

通信工程监理实施细则

广西沿海铁路南宁至钦州北段扩能改造工程通信工程监理实施细则编制:审核:北京铁研建设监理有限责任公司南钦铁路监理站2012年3月目录一、编制依据 (1)二、工程特点及技术、质量标准 (1)三、监理工作范围及重点 (1)四、监理工作流程 (2)1.通信工程监理工作流程图 (2)2.施工组织设计(施工方案)审批程序 (3)3.质量监理工作流程 (4)4.工序质量控制流程 (5)5.工程质量缺陷处理流程 (5)6.光电缆及配套器材、设备质量检验流程 (6)7.工序交接检验流程 (7)8.工程隐蔽检、预检及检验批、分项、分部验收流程 (7)9.单位工程质量控制流程 (8)10.通信线路监理工作流程 (9)11.室内设备和箱式机房监理工作流程 (10)12.传输系统监理工作流程 (11)13.接入网监理工作流程 (11)14.数据通信系统监理工作流程 (12)15.电话交换系统监理工作流程 (12)16.数字调度通信系统监理工作流程 (13)17.GSM-R数字移动通信系统监理工作流程 (13)18.会议电视系统监理工作流程 (15)19.综合视频监控系统监理工作流程 (15)20.应急通信系统监理工作流程 (16)21.综合布线监理工作流程 (16)22.数字同步及时间分配系统监理工作流程 (17)23.综合网络管理系统监理工作流程 (18)24.通信设备房屋环境监控及电源监控系统 (18)25.电源设备监理工作流程 (19)五、监理工作控制要点、目标及手段 (19)(一)监理工作控制要点 (19)1.通信线路控制要点 (19)2.室内设备和箱式机房控制要点 (20)3.传输系统控制要点 (21)4.接入网控制要点 (22)5.数据通信系统控制要点 (23)6.电话交换系统控制要点 (25)7.数字调度通信系统控制要点 (25)8.GSM-R数字移动通信系统控制要点 (27)9.会议电视系统控制要点 (32)10.综合视频监控系统控制要点 (33)11.应急通信系统控制要点 (34)12.综合布线控制要点 (35)13.数字同步及时间分配系统控制要点 (36)14.综合网络管理系统控制要点 (37)15.通信设备房屋环境监控及电源监控系统控制要点 (38)16.电源设备监控要点 (39)(二)质量目标 (41)(三)控制手段 (41)六、监理工作方法与措施 (61)七、旁站具体部位及工序 (61)广西沿海铁路南宁至钦州北段扩能改造工程通信工程监理实施细则一、编制依据1、国家和建设部、铁道部颁布的有关工程建设的政策、法规及法律等标准;2、《铁路建设工程监理规范》(TB10402-2007J269-2007)3、已批准的监理规划4、已审核的施工图及变更设计文件5、《高速铁路通信工程施工质量验收标准》(TB10755-2010J1151-2011)6、《高速铁路通信工程施工技术指南》(铁建设[2010]241号)7、《铁路建设监理工作标准化指导书》通信工程分册8、已批准的施工组织设计、专项施工方案二、工程特点及技术、质量标准本工程战线长,参建单位多、协调配合工作量大、管理跨度大。

【通信工程 监理实施细则】信息系统工程监理细则

【通信工程 监理实施细则】信息系统工程监理细则

(建设单位名称)
XXXX信息系统工程
工程编号:XXXXXXXXX
监理细则
2
编制人:XXX
审核人:XXX
河北邮电通信工程建设监理有限公司
编制日期:xxxx年xx月
2
旗开得胜
目录
第一部分信息系统工程监理概述 (3)
第一章信息系统工程监理的范围、一般过程及监理特点 (3)
一、信息系统工程监理的范围 (3)
二、信息系统工程实施的一般过程 (3)
三信息系统工程监理的特点 (4)
第二章监理规划及监理实施细则 (5)
一、监理规划 (5)
二、监理实施细则 (6)
第二部分信息系统工程监理实施 (7)
第一章遴选施工单位的流程 (7)
一、公开招标/邀请招标子流程和内容 (7)
二、非招标子流程和内容 (8)
第二章设备采购项目监理的流程和内容 (9)
第三章建筑智能化工程监理工作程序 (11)
一、监理工作总程序 (11)
二、工程质量控制程序 (12)
三、工程进度控制程序 (13)
四、工程投资控制程序 (14)
第四章软件工程项目监理流程 (15)
一、软件工程项目监理总流程 (15)
二、软件工程设计阶段监理流程和内容 (17)
三、软件工程编码与测试阶段监理流程和内容 (18)
四、软件工程验收阶段监理流程和内容 (19)
第五章施工阶段的监理工作 (21)。

住建部《城市轨道交通建设工程验收管理暂行办法》建质[2014]42号

住建部《城市轨道交通建设工程验收管理暂行办法》建质[2014]42号

《城市轨道交通建设工程验收管理暂行办法》建质[2014]42号:2014年3月27日第一章总则第一条为规范城市轨道交通建设工程验收工作,依据《建设工程质量管理条例》、《房屋建筑和市政基础设施工程竣工验收备案管理办法》、《房屋建筑和市政基础设施工程竣工验收规定》和《城市轨道交通工程安全质量管理暂行办法》等有关规定,结合城市轨道交通工程建设的实际,制定本办法。

第二条本办法所称城市轨道交通是指采用专用轨道导向运行的城市公共客运交通系统,包括地铁、轻轨、单轨、磁浮、自动导向轨道等系统。

第三条本办法适用于新建、扩建、改建城市轨道交通建设工程的验收活动及其监督管理。

第四条国务院住房城乡建设主管部门对全国城市轨道交通建设工程验收实施统一监督管理。

县级以上地方人民政府住房城乡建设主管部门负责本行政区域内城市轨道交通建设工程验收的监督管理,具体工作可委托所属工程质量监督机构实施。

县级以上地方人民政府有关部门按照法律法规规定负责相关的专项验收。

第五条城市轨道交通建设工程验收除应执行本管理办法外,还应符合国家、行业等有关规定和标准。

第六条城市轨道交通建设工程验收分为单位工程验收、项目工程验收、竣工验收三个阶段。

单位工程验收是指在单位工程完工后,检查工程设计文件和合同约定内容的执行情况,评价单位工程是否符合有关法律法规和工程技术标准,符合设计文件及合同要求,对各参建单位的质量管理进行评价的验收。

单位工程划分应符合国家、行业等现行有关规定和标准。

项目工程验收是指各项单位工程验收后、试运行之前,确认建设项目工程是否达到设计文件及标准要求,是否满足城市轨道交通试运行要求的验收。

竣工验收是指项目工程验收合格后、试运营之前,结合试运行效果,确认建设项目是否达到设计目标及标准要求的验收。

专项验收是指为保证城市轨道交通建设工程质量和运行安全,依据相关法律法规由政府有关部门负责的验收。

第七条城市轨道交通建设工程所包含的单位工程验收合格且通过相关专项验收后,方可组织项目工程验收;项目工程验收合格后,建设单位应组织不载客试运行,试运行三个月、并通过全部专项验收后,方可组织竣工验收;竣工验收合格后,城市轨道交通建设工程可履行相关试运营手续。

通讯工程施工监理细则

通讯工程施工监理细则

通讯工程施工监理细则一、总则1.1 本细则依据《中华人民共和国合同法》、《中华人民共和国建筑法》、《建设工程质量管理条例》等有关法律、法规和标准规范,结合通信工程实际情况制定。

1.2 本细则适用于通信工程施工监理工作,包括施工准备阶段、施工阶段、竣工验收阶段和缺陷责任期阶段。

1.3 监理单位应按照合同约定和国家相关法律、法规的要求,认真履行监理职责,确保工程质量、安全、进度和投资控制等目标的实现。

二、监理组织及人员2.1 监理单位应建立健全监理组织机构,明确监理人员的职责和权限。

2.2 监理单位应指派具备相应资格和经验的总监理工程师,负责监理工作的组织和协调。

2.3 监理人员应具备相应的专业知识和技能,了解通信工程的特点和施工工艺,经培训合格后方可上岗。

三、监理内容3.1 施工准备阶段(1)审查施工图纸、设计文件和施工方案,确保其符合国家标准和设计要求。

(2)审查施工单位的人员、设备、材料等资源配置情况,确保满足施工需求。

(3)对施工现场进行勘查,了解地质、水文、交通等情况,为施工提供合理建议。

(4)审查施工单位的安全生产应急预案,确保施工安全。

3.2 施工阶段(1)对施工过程中的质量、安全、进度、投资控制等方面进行现场监督。

(2)检查施工单位的施工工艺、操作规程、工程质量等方面,确保符合设计要求和标准规范。

(3)对施工单位的材料、设备进行检查,确保合格合规。

(4)定期召开监理例会,协调解决施工中出现的问题,确保工程顺利进行。

3.3 竣工验收阶段(1)审查施工单位的竣工资料,确保完整、准确、规范。

(2)对工程质量进行验收,确保符合设计要求和标准规范。

(3)参加竣工验收会议,签署竣工验收意见。

3.4 缺陷责任期阶段(1)对施工单位的缺陷修复工作进行监督,确保及时、质量合格。

(2)对缺陷责任期结束后的工程进行验收,签署验收意见。

四、监理工作方法4.1 采用现场巡查、平行检验、定期会议等方式进行监理。

通信线路工程监理细则

通信线路工程监理细则

新建西宝铁路JL-1标四电集成施工监理通信电线路工程监理实施细则编制审核批准北京中铁诚业监理公司新建西宝铁路JL-1标监理站2011年11月目录一、工程特点及技术质量标准------------------------ 11.1通信电线路工程特点 -------------------------- 11.2技术质量标准 ------------------------------- 2二、监理细则的编制依据和说明 ----------------------- 22.1编制依据 -------------------------------- 22.2编制说明 -------------------------------- 3三、监理工作范围及重点 ------------------------- 33.1监理工作范围 ------------------------------ 33.2监理工作的重点 ---------------------------- 3四、监理工作流程图--------------------------- 4五、监理工作控制目标、要点及监控手段------------------- 55.1控制要点 --------------------------------- 55.2监控目标 --------------------------------- 65.3监控手段 --------------------------------- 7六、监理工作方法和措施 ------------------------- 11七、旁站具体部位及工序 ------------------------- 12一、工程特点及技术质量标准1.1通信光电线路工程特点1.1.1通信光电线路在通信中的作用通信光电线路是构成通信网的极其重要的组成部由其构成厂区各种通信网络及完成各种信息的传递。

轨道交通工程质量验收实施细则

轨道交通工程质量验收实施细则

南宁轨道交通工程质量验收实施细则(试行)第一章总则第一条为规范南宁轨道交通集团有限责任公司管辖范围内的轨道交通工程质量验收工作,提高轨道交通工程质量安全水平,明确其操作程序及内容,保证工程质量,根据《建设工程质量管理条例》(2000年国务院279号令)、《房屋建筑和市政基础设施工程竣工验收备案管理暂行办法》(2000年建设部78号令,2009年住建部2号修改令)、《城市轨道交通工程安全质量管理暂行办法》(建质〔2010〕5号)、《住房城乡建设部关于印发城市轨道交通建设工程验收管理暂行办法的通知》(建质〔2014〕42号)、《建筑工程施工质量验收统一标准》(GB50300—2013)、CJJ/T180-2012《城市轨道交通工程档案整理标准》、《城市轨道交通工程建设项目管理规范》(GB50722—2011)等规范及《南宁市城乡建设委员会关于印发南宁市城市轨道交通建设工程验收管理办法(试行)的通知》(南建质安〔2014〕59 号)等有关规定,结合南宁市城市轨道交通建设工程的实际情况,将《南宁轨道交通有限责任公司轨道交通工程质量验收管理办法(试行)》([2013]85号文)细化修订为《南宁轨道交通工程质量验收实施细则(试行)》(以下简称“本细则”)。

 第二条本细则适用于南宁轨道交通集团有限公司(以下简称轨道公司)管辖范围内的轨道交通工程的质量验收活动。

包括:轨道交通建筑工程、轨道工程、机电系统安装工程等。

并作为轨道公司管辖范围内的轨道交通工程质量验收有关的检验规定、说明及验收记录的统一准则。

参与验收活动的建设、勘察、设计、施工、监理、检测、测量、监测等单位应遵守本细则。

 第三条根据有关法律法规的规定,建设行政主管部门对轨道交通建设工程的验收实施监督管理,轨道交通建设工程质量监督机构(以下简称“质量监督机构”)具体负责实施轨道交通工程质量验收监督工作。

 第四条参与验收的建设、勘察、设计、施工、监理等各方不能形成一致意见时,应当协商提出解决的方法,重新组织验收。

通信工程割接监理细则

通信工程割接监理细则

通信工程割接实施监理细则一、割接概述1、为加强监理在通信工程割接中的安全生产管理,保障人身、通信设备和网络安全,提高工程施工质量、加快工程进度和预防割接风险,提升监理对割接工程项目的管理能力,根据有关法规和规范,结合武汉电信工程割接实际情况,特编制本监理细则。

2、本细则所称通信工程割接,是指各类通信传输、交换、数据、管线等专业对已承载业务的网络系统中的线路、电路/链路、端口、板卡、设备等网络资源进行有计划的割接(或维护)操作,如退铜、交换机退网、搬迁、调整和升级等操作。

二、基本原则1、坚持以用户正常通信为先的原则,在保障通信网络设备正常运行的前提下进行割接工作。

2、割接方案不确切不割接,割接所需资料不准确不割接。

3、国家重大活动和重要通信期间不割接。

4、未接到建设方书面通知不割接,5、建设方未通知用户前不割接,准备工作不充分不割接,线路、设备验收不通过不割接。

6、施工单位提交的割接组织方案会签不齐全或审批未通过不割接。

三、割接实施前的监理工作1、组织建设相关单位人员进行割接工程设计会审,相关人员签字确认。

2、督促施工单位割接方案制定好后,必须在割接前三天呈报建设方,由其组织施工、监理、维护及技术支撑等部门共同审核,监理人员应严格审核施工单位提交的割接组织方案和割接报告,监理人员要认真审核批准并提出审批意见,督促施工单位及时送达建设单位项目经理和区分公司建设主管。

3、监理人员重点审核:(1)施工单位成立的业务割接组织机构、人员配置和任务分工;(2)车辆、仪表、工具等用具配置和材料准备情况;(3)割接的目的、主要内容和工作量;(4)割接时间(割接开始时间-预计割接完成时间);(5)割接的地点和路由;(6)交接箱和测试机房;(7)与相关单位主要负责人联系和沟通;(8)熟悉割接流程、风险源等级识别和应急预案。

4、组织和参加割接工作会议。

5、督促施工单位核对割接资料与实际是否相符,提前安排线路小组在割接点复核被割接光/电缆的型号、芯数、管孔位置和路由复测。

某系统工程设备安装监理细则

某系统工程设备安装监理细则

某系统工程设备安装监理细则某系统工程设备安装监理细则为确保系统工程设备安装工作的安全和准确性,需要制定一系列的监理细则,以确保该系统工程设备的安全而顺利地投入使用。

本文将从五个方面介绍某系统工程设备安装监理细则。

一、前期准备工作1.确定项目的目标:为确保整个系统工程设备安装工作过程中,监理员必须首先对项目的目标进行梳理,以确保项目的目标一致性和实现公司的战略目标。

2.制定技术方案:在项目实施开始前,需要制定可靠性的安装技术方案来确保安装质量,例如计划施工地点中的场地土壤性质、铺位、导线和管道的敷设以及通信、监控与控制系统的设计。

3.建立监理体系:在确保安装工作可行性和技术方案的制定后,监理单位应建立相应的监理体系并招募技术人员来保障项目的顺利完成。

二、安装监理及其程序1.严格按照监理计划执行:监理人员应按照监理计划逐级审核,保证在相应的时间节点内完成安装工作。

2.监控工程进度:监理员应对工程的进度进行实时监控并配合施工方完成进度计划。

3.对施工中遇到的问题进行解答和协调:施工进程中遇到问题,监理员应及时与工程负责人及其他相关人员进行沟通,予以解答和协调,以确保安装工作正常开展。

4.发现施工问题时,需及时记录并进行纠正。

例如不符合图纸要求的铺位、走线等等,及时纠正以防止将来的通信故障。

三、现场安全、环保等管理要点1.安全施工:发生安全事故时,监理员应立即与现场施工队员联络,采取应急措施并报告上级单位、彻底查明事故原因,同时结合监理任务情况,提出决议,确保事故及时得到处理。

2.保证环保:监理员应与施工负责人配合,严格执行环保原则,防止对环境造成不良影响。

四、变更时间节点及程序1.监理期间,任何技术变更及措施应保证安全、合理有效,并应在监理报告进行记录;2.遇到必须变更的问题时,监理员应及时审批和签署变更单,并在变更单内记录详细情况。

五、监理工作的总结及报告1.监理结束后,需要准确的监理记录和报告,以便予以进一步的总结和改进;2.对于监理期间遇到的问题和困难,监理员应及时、详细、准确地记录,并提出相应的解决方案;3.监理员应针对本次监理的工作总结和回顾,进一步提高自己的技术能力,同时也对系统工程设备的安装工作进行评估和改进,以提高监理质量和水平。