国家电网电定〔2008〕26号-关于发布国家电网公司电力工程装置性材料预算价格调整系数的通知
电力工程造价员-试题库
基建造价管理一、单项选择题1.根据《电网工程建设预算编制与计算标准》的规定,以下费用项目不属于强制性费用的项目是()。
(A)税金(B)规费(C)安全文明施工措施补助费(D)工程监理费答案: D2.在项目建议书和可行性研究阶段对拟建项目预先测算出的投资额称为()。
(A)投资匡算(B)投资估算(C)初步设计概算(D)施工图预算答案: B3.《电力建设工程概(预)定额》的基价人工费中未包括的容是()。
(A)劳动保护费(B)工资性补贴(C)职工福利费(D)工伤保险。
答案: D4.现场施工人员产、婚、丧假期间的工资,女工哺乳期间的工资在()中已经包括。
(A)定额人工费(B)社会保障费(C)企业管理费(D)基本预备费答案: A5.施工机械操作人员的工资包括在()中。
(A)定额人工费(B)施工机械使用费(C)企业管理费(D)项目法人管理费答案: B6. 在电网建设工程中,()不计列夜间施工增加费。
(A)变电站建筑工程(B)变电站安装工程(C)一般架空线路工程(D)大跨越工程答案: C7. 现场施工工区间的临时隔墙的砌筑费用由()开支。
(A)临时设施费(B)安全文明施工措施费(C)企业管理费(D)临时工程费答案: A8. 施工企业职工由基地到所承建工程现场调遣期间的工资包括在()中。
(A)定额人工费(B)施工机构转移费(C)企业管理费(D)前期工作费答案: B9. 施工现场土方覆盖、施工过程中的淋水降尘等措施费用应在()项下开支。
(A)临时设施费(B)企业管理费(C)安全文明施工措施费(D)临时工程费答案: C10.按照《电网工程建设预算编制与计算标准》规定,规费是指按照()部门规定必须缴纳的费用。
(A)行政主管(B)省级行政主管(C)电力行业主管(D)县级以上主管答案: A11.我国社会保障体系“五险一金” ,在新预规规定的规费中未包括的是()。
(A)养老保险(B)失业保险(C)工伤保险(D)生育保险答案: D12.施工企业现场临时宿舍的取暖费用由()开支。
电力装置性材料预算价格-2006年版
单位
只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只 只
单价(元)
1720.00 3289.00 348.00 453.00 2467.00 907.00 2541.00 2773.00 2899.00 2920.00 424.00 461.00 582.00 606.00 1188.00 1334.00 1697.00 2788.00 2667.00 2957.00 3120.00 3901.00 5071.00 559.00 727.00 759.00 801.00 822.00 896.00 1001.00 2277.00 2741.00 2952.00 3057.00 3479.00 1792.00 1771.00 206.00 232.00 223.00 309.00 353.00 318.00 325.00 320.00 334.00 327.00 657.00
材料名称
HDG-220/120 HDG-500/120 HHD-10 HHD-35 HJG-220/100 XSH-220/100 XSH-500/100 XSH-500/160 XSH-500/210 XSH-500/240 HXS2-35/70 HXS2-66/70 HXS2-110/70 HXS2-110/100 HXS2-220/100 HXS2-220/120 HXS2-220/160 HXS2-330/160 HXS2-500/100 HXS2-500/180 HXS2-500/210 HXS2-500/240 HXS2-500/300 YDG10 FXB-35/100 FXB-66/100 FXB-110/100 FXB-220/100 FXB-220/160 FXB-220/210 FXB-500/100 FXB-500/160 FXB-500/180 FXB-500/210 FXB-500/300 FXB1-220/100 FXB1-110/100 FXBW-35/70 FXBW-35/100 FXBW4-35/70 FXBW-110/70 FXBW-110/100 FXBW3-110/70 FXBW3-110/100 FXBW4-110/70 FXBW4-110/75-5 FXBW4-110/100 FXBW-220/100
版电力定额装置性材料预算价
kg
G01060101 G01060102 G01070101 G01070102 G01080101 G01080102 G01080103 G01080104 G01080105 G01080106 G01080107 G01080108 G01080109 G02 G02010101 G03 G03010101 G03010102 G04 G04010101 G04010201 G04010401 G05 G05010101 G05010201 G05010301 G05010401 G05010501 G05010601
kg
钢20 P=22.56Mpa t=240℃ DN100及以上
kg
G10010301 G10020101 G10020201 G10020301 G10030101 G10030201 G10030301 G10040101 G10040201 G10040301 G11010101 G11010201 G11010301 G11020101 G11020201 G11020301 G11030101 G11030201 G11030301 G11040101 G11040201 G11040301 G12 G12010101 G12010102 G12010201 G12010202 G12010301 G12010302
材料编码 G01 G01010101 G01010102 G01020101 G01020201 G01020301 G01020401 G01020501 G01020601 G01020701 G01030101 G01030201 G01030301 G01030401 G01030501 G01030601 G01030701 G01040101 G01040201 G01040301 G01040401 G01040501 G01040601 G01050101 G01050201 G01050301 G01050401 G01050501
桂电计〔2008〕91号附件电网工程建设预算编制与计算标准实施细则
广西电网公司电网工程建设预算编制与计算标准实施细则第一章总则第一条为加强广西电网公司(以下简称公司)电网工程建设预算管理,统一建设预算的编制和计算规则,合理确定工程造价,根据《电网工程建设预算编制与计算标准》(2006年版)(中电联技经[2007]139号)(以下简称《预规》)的规定,结合公司具体情况,制定本细则。
第二条本细则适用于公司各种投资渠道建设的35kV~500kV基本建设、技术改造、配电网、业扩、农村电网以及其他类似工程的交流输变电和系统通信新建、扩建和改建工程。
第三条本细则与《预规》配套使用,本细则未提及部分费用计算标准按《预规》有关规定执行。
第四条《预规》及本细则作为电网工程可行性研究投资估算、初步设计概算、施工图预算和电网建设工程量清单报价(以下简称预算)的编制和费用计算依据,应与电网工程投资估算指标、概算定额、预算定额和电网建设工程量清单计价规范配套使用[详见《配套定额及费用标准表》(附表一)]。
第二章 建筑安装工程费第五条 人工费1、人工费按照电力行业定额中规定的原则计算,电力工程人工工日单价按照定额中规定的电力行业基准工日单价执行,各册定额基准工日单价标准为:电气设备安装工程31元/工日;送电线路工程33.1元/工日;建筑工程26元/工日。
2、人工费调整,各地区只能调整工资性补贴,其中定额基准工日单价中已经包括了工资性补贴2.4元/工日。
广西地区工资性补贴金额根据电力工程造价与定额管理总站文件《关于公布各地区工资性补贴的通知》(电定总造[2007]12号文)规定为3.14元/工日。
编制预算时,人工费调整金额应汇总计入直接工程费中的人工费,作为各项取费的取费基数。
广西地区人工费调整系数的计算公式如下:()%1003.144.2-+-=定额基准工日单价定额基准工日单价人工费调整系数第六条 材料费电网工程建设预算中的材料费包括装置性材料费和消耗性材料费两部分。
1、电网建设工程概预算定额消耗性材料价格水平的调整根据电力工程造价与定额管理总站文件《关于颁布〈电力建设工程概预算定额价格水平调整办法〉的通知》(电定总造[2007]14号)有关规定执行。
国家电力监管委员会关于印发《电力供需及电煤供应监测预警管理办法》的通知-办市场[2008]41号
国家电力监管委员会关于印发《电力供需及电煤供应监测预警管理办法》的通知正文:---------------------------------------------------------------------------------------------------------------------------------------------------- 国家电力监管委员会关于印发《电力供需及电煤供应监测预警管理办法》的通知(办市场[2008]41号)各派出机构,国家电网公司,南方电网公司,华能、大唐、华电、国电、中电投集团公司,各有关电网企业、发电企业:为提高电力运行监测预警水平,我会制定了《电力供需及电煤供应监测预警管理办法》,现印发试行。
执行中有何问题和建议,请及时向国家电力监管委员会市场监管部报告。
二○○八年七月四日电力供需及电煤供应监测预警管理办法第一条为加快建立全国电力生产运行监测预警信息机制,提高我国电力运行预测预警能力和水平,依据《电力监管条例》和《国务院办公厅关于加强能源预测预警工作的意见》(国办发[2008]2号),制订本办法。
第二条电力供需情况,是指省级及以上电网的电力生产、供需平衡及重要联络线运行等情况;电煤供应情况,是指全国10万千瓦及以上燃煤电厂、重点监测的发电企业、直供电厂等电煤供应情况。
第三条电力供需及电煤供应监测预警信息系统由电监会统一组织建设,各区域电监局、各城市电监办予以配套支持,并根据需要逐步完善。
第四条电力供需情况监测信息主要包括:省级及以上电网的日统调发电负荷、日统调发用电量、月累计发电量,年累计发电量;省级及以上电网拉限负荷情况;跨省跨区送电的日最大输送电力、日输送电量,重要联络线运行情况;重要枢纽水电站的水情及相关运行情况;电力监管机构要求监测的其他信息。
第五条电煤供应情况监测信息主要包括:当日电煤库存及可用天数;缺煤停机台数及对应发电容量;可用天数低于警戒线水平的电厂数;平均可用天数低于警戒线水平(7天)的省(自治区、直辖市);电力监管机构要求监测的其他信息。
关于发布版电力建设工程概预算定额价格水平调整的通知
附件2013年版电力建设工程概预算定额价格水平调整办法第一章总则第一条为规范电力建设工程概预算定额价格水平的测算、发布和实施工作,科学反映不同时间和不同地区价格水平差异,合理确定工程投资,特制订本办法。
第二条本办法适用于以《火力发电工程建设预算编制与计算规定(2013年版)》、《电网工程建设预算编制与计算规定(2013年版)》(以下简称“预规”)和《电力建设工程概算定额(2013年版)》、《电力建设工程预算定额(2013年版)》(以下简称“定额”)为计价依据,编制电力建设工程概预算时,对定额内人工费、材料费和施工机械费价格水平的调整。
第三条本办法调整的主要内容包括:工程所在地编制基准期价格与概预算定额价格之间的时间差及地区差水平调整。
第四条电力建设工程概预算编制基准期价格水平与定额编制价格水平之间的价差计算:发电和电网工程的人工费均以系数的形式进行调整;发电安装工程和电网安装工程的材料及机械费以系数的形式进行调整;发电建筑工程和电网建筑工程按照本办法中给定的典型材料及机械种类、品种及规格等直接进行价差调整。
第二章人工费调整第五条定额人工费每年调整一次,分别按照建筑工程和安装工程,采用综合系数法进行调整(见附件1)。
不分工种(普通工、技术工)、安装工程不分专业(热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程),计算时按照对应定额基价中人工费总额乘相应的调整系数。
第六条各地区定额人工费调整系数是参照住房与城乡建设部发布的各地区人工信息价格,或当地定额与造价管理部门公布的本地区定额人工价格,但其组成内容要与电力建设工程预规和定额所规定的组成内容相一致,进行转化后综合取定。
第七条定额人工费综合调整系数计算公式:建筑工程定额人工费调整系数=[(转化后当地建筑工程定额人工工日单价/定额普通人工工日单价)*0.79] *100%-1 安装工程定额人工费调整系数=[(转化后当地安装工程定额人工工日单价/定额普通人工工日单价)*0.72] *100%-1 第八条定额人工费调整金额计算公式:定额人工费调整金额合计=建筑工程定额人工费调整合计 + 安装工程定额人工费调整合计建筑工程定额人工费调整合计=建筑工程定额基价人工费总额*建筑工程定额人工费调整系数安装工程定额人工费调整合计=安装工程定额基价人工费总额*安装工程定额人工费调整系数此处安装工程包括热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程。
浙江电网10(20)kV 输配电项目可研标准化设计
浙江电网输变电工程标准化设计10(20)kV配电项目可行性研究标准化集中设计工作组2009-7目录范围 (1)主要设计规定 (2)1、概述 (3)1.1设计依据 (3)1.2工程概况 (3)1.3主要设计原则 (3)1.4设计范围 (3)1.5投资估算 (3)2、电力系统 (3)2.1电网概况 (3)2.2建设必要性 (4)2.3系统接入方案 (4)2.4建设规模 (4)2.4.1开关站 (4)2.4.2 配电站 (5)2.4.3 箱式变电站 (5)2.4.4柱上变压器台 (6)2.5对主要电气设备参数的要求 (6)2.5.1母线容量 (6)2.5.2短路电流水平 (6)2.5.3无功补偿 (7)2.5.4主变选型 (7)2.5.5接线组别 (7)2.5.6调压抽头 (7)2.5.7额定电压、电流 (7)2.5.8电能量计量系统配置方案 (7)3、站址选择和工程设想 (7)3.1站址选择 (7)3.1.1选所经过 (7)3.1.2站址方案 (7)3.1.3站址方案比较及推荐意见 (8)3.2工程设想 (8)3.2.1站址分析 (8)3.2.2站址地质条件 (8)3.2.3站址水文气象条件 (8)3.2.4电气主接线 (9)3.2.5主变压器绕组接线方式 (9)3.2.6总平面布置 (9)3.2.7主要电气设备、导体选型 (10)3.2.8 防雷、接地 (11)3.2.9动力、照明 (11)3.2.10消防及通风 (12)3.2.11电气二次部分(配置继电保护装置的10(20)kV开关站) (12)3.2.12 建筑规模及结构设想 (13)3.2.12.1 总平面布置 (13)3.2.12.2 建、构筑物 (13)3.2.12.3 站区给排水 (14)3.2.12.4 消防 (14)3.2.12.5 采暖通风 (14)3.2.12.6 环境保护与场地处理 (14)4、输电线路路径选择和工程设想 (15)4.1路径选择 (15)4.1.1系统概况 (15)4.1.2进出线走廊 (15)4.1.3 路径方案 (15)4.1.4路径地质条件 (16)4.1.5路径水文气象条件 (16)4.2工程设想 (16)4.2.1气象条件 (16)4.2.2导线选型 (17)4.2.3主要杆塔和基础型式 (19)4.2.4电瓷金具及防雷 (20)4.2.5电缆敷设主要模块技术组合 (20)5、技经部分 (21)5.1编制依据和原则 (21)5.2投资估算 (23)6、图纸 (24)6.1一般提供下表所示设计图纸: (24)6.2图纸深度要求: (24)7、有关协议 (25)范围本标准适用于浙江电网10(20)kV配网工程的可行性研究设计,对于改造和扩建工程可参考本标准进行相应设计。
电力建设工程装置性材料综合预算价格(2013年版)(除税版)
电力建设工程装置性材料综合预算价格(2013年版)FZ01冷风道范围:从送风机、一次风机风口到预热器入口管道、磨煤机调温用的压力冷风道、磨煤机的密封风管道、安全监控系统冷却风道。
不包括消音器及暖风器。
内容:方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓。
编码项目单位预算价(元)FZ011125MW冷风道t5589FZ012200MW冷风道t5613FZ013300MW冷风道t6951FZ014600MW冷风道t7005FZ0151000MW冷风道t7380FZ02热风道范围:从空气预热器出口分别到磨煤机入口、燃烧器(二次风)及煤粉混合器入口。
内容:方圆形管道、风门、孔门、补偿器、异形管件、传动装置、支吊架、螺栓。
编码项目单位预算价(元)FZ021125MW热风道t6576FZ022200MW热风道t6399FZ023300MW热风道t7440FZ024600MW热风道t7247FZ0251000MW热风道t7492FZ03烟道范围:从空气预热器出口到烟囱入口的所有钢管道,并包括高温炉烟道及烟气再循环管道。
内容:方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓,不包括高温烟道的内衬材料。
编码项目单位预算价(元)FZ031125MW烟道t5337FZ032200MW烟道t5450FZ033300MW烟道t6820FZ034600MW烟道t6694FZ0351000MW烟道t6797FZ04原煤管道范围:从原煤斗出口到磨煤机入口,包括金属小煤斗。
内容:方圆形管道及管件、煤闸门、传动装置、接口法兰及支吊架。
编码项目单位预算价(元)FZ041125MW原煤管道t5369FZ042200MW原煤管道t5913FZ043300MW原煤管道t5597FZ044600MW原煤管道t5558FZ0451000MW原煤管道t5511FZ05制粉管道范围:从钢球磨煤机出口到煤粉仓和排粉机入口的全部煤粉空气管道,包括粗粉分离器至磨煤机入口的回粉管、细粉分离器至煤粉仓和螺旋输粉机粉仓的下粉管、煤粉仓的吸潮管和防爆门引出管、煤粉仓的粉位测量装置。
08版通信线路工程预算定额(第四册)
08版通信线路工程预算定额(第四册)通信建设工程预算定额第四册通信线路工程中华人民共和国信息产业部二00八年五月工业和信息化部文件工信部规[2008]75号________________________________________________________________ ________ ___________________________ 关于发布《通信建设工程概算预算编制办法》及相关定额的通知各省、自治区、直辖市通信管理局,中国电信集团公司、中国网络通信集团公司、中国移动通信集团公司、中国联合通信有限公司、中国卫星通信集团公司、中国铁通集团有限公司:为适应通信建设发展需要,合理和有效控制工程建设投资,规范通信建设概算、预算的编制与管理,根据国家法律、法规及有关规定,我部修订了《通信建设工程概算、预算编制办法及费用定额》(邮部[1995]626号)以及通信建设工程预算定额等标准。
新修订的通信建设工程概算、预算定额配套文件包括:《通信建设工程概算、预算编制办法》,《通信建设工程费用定额》,《通信建设工程施工机械、仪器仪表台班定额》,《通信建设工程预算定额》(共五册:第一册通信电源设备安装工程、第二册有线通信设备安装工程、第三册无线通信设备安装工程、第四册通信线路工程、第五册通信3管道工程.)现予发布,自2008年7月1日起实施。
自实施之日起原邮电部《关于发布<通信建设工程概算、预算编制办法及费用定额>等标准的通知》(邮部【1995】626)以及《关于发布<通信建设工程施工机械台班费用定额>等2项定额标准的通知》(邮部【1996】582)同时废止。
附件:1.通信建设工程概算、预算编制办法2.通信建设工程费用定额3.通信建设工程施工机械、仪器仪表台班定额4.通信建设工程预算定额中华人民共和国工业和信息化部(章)二00八年五月二十四日(附件另发)4主题词:邮电通信建设预算通知抄送:国家发展和改革委员会,财政部,住房和城乡建设部。
电力建设工程装置性材料综合预算价格(2013年版)除税价格
FZ33 厂区除灰管道·························································································································· 33 FZ34 厂外除灰管道·························································································································· 34 FZ35 脱水仓系统管道······················································································································· 35 FZ36 气力除灰系统管道···················································································································· 36 FZ37 煤矸石排渣系统管道················································································································· 37 FZ38 灰水回收泵房管道···················································································································· 38 FZ39 反渗透处理系统管道················································································································· 39 FZ40 凝聚澄清过滤系统管道·············································································································· 40 FZ41 除盐系统管道·························································································································· 41 FZ42 酸碱贮存及计量管道················································································································· 42 FZ43 酸碱废水处理管道···················································································································· 43 FZ44 树脂清洗及装卸管道················································································································· 44 FZ45 凝结水精处理管道···················································································································· 45 FZ46 循环水加药系统管道(加酸、加氯)··························································································· 46 FZ47 凝汽器铜管镀膜管道················································································································· 47 FZ48 化学加药系统管道(给水联胺、给水加氨、加氧、加磷、炉内水处理)············································· 48 FZ49 汽水取样管道·························································································································· 49
背压机参考(1)
第十三章投资估算及经济效益评价13.1 工程概况乌拉特前旗(简称前旗)位于内蒙古自治区西部,隶属巴彦淖尔市,地处河套平原东端。
本项目由内蒙古国电能源投资有限公司投资,2007年12月我院完成内蒙古自治区巴彦淖尔市乌拉特前旗境内新建2×300MW空冷供热机组,规划容量为4×300MW空冷供热机组的可行性研究报告。
中国国际工程咨询公司于2008年1月3日—4日在呼和浩特市主持召开了内蒙古乌拉特前旗热电厂2×300MW供热机组工程可行性研究报告的审查会。
我院根据审查意见编制了可研收口报告。
根据国家节能减排技术政策,建设方委托我院进行2×B25+1×CC300MW装机方案(即2×B25作工业热负荷供气,一台双抽300MW作采暖抽汽用)可研,2008年4月完成可研补充报告。
2009年11月,巴彦淖尔煤电路项目筹建处委托进行乌拉特前旗热电厂装机方案进一步研究,我院于11月底编制完成乌拉特前旗热电厂《供热机组装机方案说明》,并提交筹建处。
内蒙古国电能源投资有限公司发函委托我院进行2XB50MW+3X410t/h装机方案可研工作。
2009年12月,根据相关企业工业蒸汽实际用量和发展前景,建设方和设计院进一步研究调整装机方案,确定本项目按(2×B25MW+1×B50MW +3×410t/h)装机方案继续进行可行性研究工作。
本期建设规模为(2×B25MW(背压机)+1×B50MW(背压机)+3×410t/h(锅炉))供热机组。
采用塔然高勒煤为设计煤种,锅炉100%尾部烟气脱硫,脱硫效率达90%以上,预留脱硝装置位置。
厂内设采暖换热首站。
13.2 编制原则13.2.1 国家发展改革委、建设部发改投资【2006】1325 号文印发的《建设项目经济评价方法与参数》;13.2.2 《火力发电厂可行性研究报告内容深度规定》DL/T5375—2008;13.2.3 2009年11月内蒙古国电能源投资有限公司关于委托开展乌拉特前旗热电厂2XB50MW+3X410t/h装机方案可研工作的函;13.2.4 河北省电力勘测设计研究院编制《内蒙古乌拉特前旗热电厂2×300MW供热机组工程可行性研究报告》及审查意见。
电网工程建设预算编制与计算标准
电网工程建设预算编制与计算标准为了规范电力工程建设市场,科学、合理地确定工程造价,积极推进电力工程建设预算的编制与管理工作,完善电力工程建设预算管理制度,根据国家发展改革委发改办能源〔2006〕427号文和原国家经贸委国经贸电力〔2001〕712号文的要求,电力工程造价与定额管理总站(以下简称“定额总站”)组织编制完成了《电网工程建设预算编制与计算标准》、《火力发电工程建设预算编制与计算标准》(即新“预规”,以下简称“本标准”)。
本标准的颁布按照规定程序完成了编制、校核、测算、征求意见、修改、定稿、专业审核和专家审查等项工作,由国家发展和改革委员会于2007年7月以发改办能源〔2007〕1808号文核准颁布,自2007年12月1日起实施。
一、本标准的编制过程(1)2004年9月定额总站以电定造〔2004〕17号文下达了编制任务,成立了各专业编制组,于当年底经过调研、编写和讨论,拟订了各专业的编制大纲。
2005年1月,在哈尔滨召开了专家审查会,确定了工作方案、编制原则和编制大纲。
(2)2005年3月,各编制组正式开始了调研、收资和编制工作,在调研、收资过程中,编制组先后走访了15个省、市、自治区的共计四十多个工地和企业,取得了第一手的资料后,按计划开始了分组编制工作。
(3)分组编制工作完成之后,编制组于2005年10月在长春集中,经过认真协调和研究,于2005年底完成了本标准的初稿。
(4)2006年开始,由定额总站主持先后将初稿向电力行业有关建设单位、施工单位、设计院分别征求意见,并进行了进一步修改。
(5)自2006年8月开始,由定额总站组织,选择典型工程进行了测算,同时,分别向国家电网公司、南方电网公司和各发电集团公司分别征求意见,经测算、汇总,进一步修改形成了本标准的征求意见稿。
(6)2006年11月,定额总站以电定总造函〔2006〕11号文将本标准向全国征求意见,截止到12月25日,共接到反馈意见55份108条,其中电网53条,发电55条。
送电线路设计执行标准规范及文件清单
中电联
33
电网工程建设预算编制与计算标准
国家发展和改革委员会(2007年版)
34
电力工程装置性材料预算价格(2008年版)-华北地区
国家电网公司电力建设定额站
35
国家电网电定〔2010〕7号
关于印发国家电网公司输变电工程勘察设计费概算编制办法(试行)的通知。
51
国家电网科〔2011〕12号
协调统一基建类和生产类标准差异条款
52
基建设计〔2011〕115号
加强输变电工程通用设备应用管理会议纪要
53
基建设计〔2011〕120号
国家电网公司10kV~220kV复合材料杆塔设计要求(试行)、国家电网公司输电杆塔用纤维增强复合材料技术条件(试行)
54
基建设计〔2011〕311号
砌体结构设计规范
6
GB 50009-2001
建筑结构荷载规范
7
GB 50010-2002混凝土结构设计规范8来自GB 50217-2007
电力工程电缆设计规范
9
GB 50545-2010
110kV~750kV架空输电线路设计规范
10
GB50065-2011
交流电气装置的接地设计规范
11
DL5003-91
关于进一步完善输变电工程初步设计质量过程控制机制的通知
58
基建设计〔2012〕136号
关于印发《国家电网公司依托工程基建新技术推广应用实施目录(2012年版第一批)》的通知
59
基建技术〔2012〕183号
国家电网公司2012年第一次输变电工程设计竞赛创新和亮点
60
基建技术〔2012〕272号
基建工程知识考题1
一、判断题1.《中华人民共和国价格法》规定,国家实行并逐步完善宏观经济调控下主要由市场形成价格的机制。
价格的制定应当符合价值规律,所有商品和服务价格实行市场调节价。
答案:×说明:《中华人民共和国价格法》第一章总则第三条说明:国家实行并逐步完善宏观经济调控下主要由市场形成价格的机制。
价格的制定应当符合价值规律,大多数商品和服务价格实行市场调节价,极少数商品和服务价格实行政府指导价或者政府定价。
2.根据《中华人民共和国价格法》规定,国家根据国民经济发展的需要和社会承受能力,确定市场价格总水平调控目标,列入国民经济和社会发展计划,并综合运用货币、财政、投资、进出口等方面的政策和措施,予以实现。
答案:√3.国家行政机关的收费,适用中华人民共和国价格法。
答案:×说明:《中华人民共和国价格法》第四十七条国家行政机关的收费,应当依法进行,严格控制收费项目,限定收费范围、标准。
收费的具体管理办法由国务院另行制定。
4.《中华人民共和国建筑法》规定,建筑工程总承包单位可以自行将承包工程中的部分工程发包给具有相应资质条件的分包单位。
答案:×说明:《中华人民共和国建筑法》第二十九条:建筑工程总承包单位可以将承包工程中的部分工程发包给具有相应资质条件的分包单位;但是,除总承包合同中约定的分包外,必须经建设单位认可。
施工总承包的,建筑工程主体结构的施工必须由总承包单位自行完成。
5.《中华人民共和国建筑法》规定,中标的工程监理单位可以将工程监理业务转包给具有相应资质的监理单位。
答案:×说明:《中华人民共和国建筑法》第三十四条:工程监理单位不得转让工程监理业务。
6.《中华人民共和国建筑法》规定,大型建筑工程或者结构复杂的建筑工程,可以由两个以上的承包单位联合共同承包。
共同承包的各方对承包合同的履行承担连带责任。
两个以上不同资质等级的单位实行联合共同承包的,应当按照资质等级高的单位的业务许可范围承揽工程。
关于政策、法规的通知清单
009-2010有
主要内容
调整部分单体调试的综合工日数专题报告:环境影响评估、水土保持方案、用地评估、使用林地可行性报告、压覆矿评估、地灾评估、地震评估、文物评估;竣工验收:环境监测及验收费、水土保持验收(含监测费)
为配合2006年版定额与费用标准的颁布,四川为3.12元
1、把“工程质量监督检测费”调整为“电力工程质量检测费”
2、取消“电力工程定额编制管理费”
3、将“电力建设标准编制管理费”调整为“电力工程技术经济标准编制管理费”,计算标准为:电力工程技术经济标准编制管理费=(建筑工程费+安装工程费)×0.2%
输变电工程按照《电力建设工程概预算定额补充本》、《电力建设工程概算定额》(通信工程补充本)、《电力建设工程预算定额》(通信工程补充本)
与国家电网电定[2010]7号配合使用
取消工程定额测定费试行3年。
电定总造〔2009〕34号 关于颁布《20kV及以下配电网工程预算定额价格水平调整办法》的通知
电力工程造价与定额管理总站文件电定总造〔2009〕34号关于颁布《20kV及以下配电网工程预算定额价格水平调整办法》的通知国家电网公司电力建设定额站、中国南方电网有限责任公司电力建设定额站,各有关单位:《20kV及以下配电网工程建设预算编制与计算标准》和《20KV及以下配电网工程预算定额》已经颁布实施,为便于定额价格水平的调整和计算,如实反映不同年度、不同地区市场价格水平,我站制定了《20kV 及以下配电网工程预算定额价格水平调整办法》(见附件),现予颁布实施。
请国家电网公司电力建设定额站和中国南方电网有限责任公司电力建设定额站组织所属各电力建设定额站,按照本办法要求认真做好各地价格收集与测算工作。
本办法自颁布之日起执行。
附件: 20kV及以下配电网工程预算定额价格水平调整办法二〇〇九年十月二十九日附件:20kV及以下配电网工程预算定额价格水平调整办法—1—第一章总则一、为规范20kV及以下配电网工程预算定额价格水平测算和发布工作,科学反映各地区价格水平差异,合理确定工程投资,特制订本办法。
二、本办法适用于以《20kV及以下配电网工程建设预算编制与计算标准》(以下简称“配电网预规”)和《20kV及以下配电网工程预算定额》(以下简称“配电网定额”)为计价依据,编制的20kV及以下配电网工程建设预算中对定额价格水平的调整。
三、定额价格水平的调整包括:人工工日单价的调整、消耗性材料价格的调整和施工机械台班价格水平的调整。
调整的内容包括:工程所在地价格水平与预算定额所规定的电力行业基准价格之间的地域价格水平调整,以及预算编制年与定额编制基准年之间的年度价格水平调整。
四、本办法所给定的定额价格水平调整方式分为定额人工费的调整(以下简称“人工费调整”)和定额内消耗性材料与机械台班费用调整(以下简称“材机调整”)两部分,各地在编制工程建设预算时,应分别计算人工调整和材机调整金额。
五、人工费调整是指对定额基价中所包括的人工费进行各地区编制年与定额基准年之间价格水平差值的调整。
电力工程造价与定额管理
电网工程建设预算编制与计算标准发布: 2008-9-28 17:35 | 作者: 大白兔28 | 来源: 四川造价信息网《电网工程建设预算编制与计算标准》交底讲义电力工程造价与定额管理总站2007年11月第一章概述为了规范电力工程建设市场,科学、合理地确定工程造价,积极推进电力工程建设预算的编制与管理工作,完善电力工程建设预算管理制度,根据国家发展改革委发改办能源[2006]427号文和原国家经贸委国经贸电力[2001]712号文的要求,电力工程造价与定额管理总站(以下简称“定额总站”)组织编制完成了《电网工程建设预算编制与计算标准》、《火力发电工程建设预算编制与计算标准》(即新“预规”,以下简称“本标准”)。
本标准的颁布按照规定程序完成了编制、校核、测算、征求意见、修改、定稿、专业审核和专家审查等项工作,由国家发展和改革委员会于2007年7月以发改办能源[2007]1808号文核准颁布,自2007年10月日起实施。
一、本标准的编制过程1、2004年9月定额总站以电定造[2004]17号文下达了编制任务,成立了各专业编制组,于当年底经过调研、编写和讨论,拟订了各专业的编制大纲。
2005年1月,在哈尔滨召开了专家审查会,确定了工作方案、编制原则和编制大纲。
2、2005年3月,各编制组正式开始了调研、收资和编制工作,在调研、收资过程中,编制组先后走访了15个省、市、自治区的共计四十多个工地和企业,取得了第一手的资料后,按计划开始了分组编制工作。
3、分组编制工作完成之后,编制组于2005年10月在长春集中,经过认真协调和研究,于2005年底完成了本标准的初稿。
4、2006年开始,各编制组先后将初稿向有关建设单位、施工单位、设计院分别征求意见,并分别进行了进一步修改。
5、2006年8月始,由定额总站组织,选择典型工程进行了测算,同时,分别向国家电网公司、南方电网公司和各发电集团公司分别征求意见,经测算、汇总,修改形成了本标准的征求意见稿。
国家电网电定[2010]7号-附件1-国家电网公司输变电工程勘察设计费概算编制办法(试行)
国家电网公司输变电工程勘察设计费概算编制办法(试行)第一章总则第一条为全面落实国家、行业关于工程勘察设计有关规定的精神,充分体现输变电工程勘察设计工作的规律与特点,进一步规范输变电工程勘察设计费计算工作,依据《工程勘察设计收费管理规定》(计价格[2002]10号,以下简称“十号文”)制定本办法。
第二条本办法用于指导输变电工程勘察设计费的概算编制,由设计单位负责计算勘察设计费。
第三条本办法适用于国家电网公司及其所属单位投资的交流35~750千伏变电、线路工程,直流±500千伏工程,通信工程。
(一)交流变电工程包括新建、改扩建变电站、开关站以及串联补偿、静止补偿等专项工程。
(二)交流线路工程包括架空线路和电缆工程。
(三)直流工程包括换流站、接地级和直流线路工程。
第二章勘察费的计算方法第四条勘察费用遵照十号文的方法计取。
第五条线路长度不足5公里,勘察收费按5公里计算。
第三章设计费的计算方法第六条输变电工程设计收费由基本设计收费和其他设计收费组成,按下式计算。
工程设计收费=基本设计收费+其他设计收费(一)基本设计收费是指在工程设计中提供编制初步设计文件、施工图设计文件收取的费用,并相应提供设计技术交底、解决施工中的设计技术问题、参加试车考核和竣工验收等服务。
(二)其他设计收费包括总体设计费、施工图预算编制费、竣工图编制费等。
第七条基本设计收费计算按设计费计费额累进计费。
第八条设计费计费额。
(一)设计费计费额的组成。
1.变电工程设计费计费额由建筑工程费计费额、设备购置费计费额、安装工程计费额构成,按下式计算。
变电工程设计费计费额=建筑工程费计费额+设备购置费计费额+安装工程费计费额2.线路工程设计费计费额,按本体工程费计费额计取。
3.非隧道敷设电缆工程设计费计费额,由安装工程费计费额、设备购置费计费额、建筑工程费计费额构成,按下式计算。
非隧道敷设电缆工程设计费计费额=安装工程费计费额+设备购置费计费额+建筑工程费计费额4.隧道敷设电缆工程土建部分单独计费,电气部分设计费计费额由安装工程费计费额、设备购置费计费额构成,按下式计算。
2023年国网预规调考题库
2023版《电网工程建设预算编制与计算规定》考试题库一、判断题1.《电网工程建设预算编制与计算规定》是编制电网工程招标标底、最高投标限价、投标报价和工程结算旳根据。
答案:√2.在《电网工程建设预算编制与计算规定》中,建设预算指旳是初步设计概算、施工图预算。
答案:×阐明:还包括投资估算3.2023 版《电网工程建设预算编制与计算规定》中,女工旳生育保险已经在定额人工费旳工资性补助中予以考虑。
答案:×阐明:未包括4.2023 版《电网工程建设预算编制与计算规定》中,直接工程费中旳人工费已经包括了按规定原则计提旳工会经费答案:×阐明:未包括5.2023 版《电网工程建设预算编制与计算规定》中,直接工程费中旳人工费已经包括了按规定原则计提旳职工教育经费。
答案:×阐明:未包括6.2023 版《电网工程建设预算编制与计算规定》中,直接工程费中旳人工费已经包括了按规定原则计提旳劳动安全卫生检测费。
答案:×阐明:未包括7.2023 版《电网工程建设预算编制与计算规定》中,直接工程费中旳人工费已经包括了职工因公出差旳差旅费。
答案:×阐明:未包括8.2023 版《电网工程建设预算编制与计算规定》中,生产工人调动工作、探亲、休假期间旳工资已经在直接工程费中旳人工费辅助工资中予以考虑。
答案:√9.根据《电网工程建设预算编制与计算规定》旳规定,材料预算价格可以看作是工程所需材料在施工现场仓库或堆放地点旳出库价格。
答案:√10.根据《电网工程建设预算编制与计算规定》旳规定,材料预算价格范围包括:材料原价(或供应价格)、保险保价费、运送损花费、采购及保管费四项费用。
答案:×阐明:还包括材料运送费11.根据《电网工程建设预算编制与计算规定》旳规定,社会保险费中旳养老保险费是企业按照规定原则为职工缴纳旳基本养老保险费。
答案:√12.根据《电网工程建设预算编制与计算规定》旳规定,社会保险费中旳医疗保险费是是企业按照规定原则为职工缴纳旳基本医疗保险费。