某某小区一区11#楼砌体工程施工方案编制:审核:审批:某某集团有限公司二零二二年四月目录一、编制依据 ---------------------------------------------------------------------------------- 1二、工程概况 ---------------------------------------------------------------------------------- 12.1 工程简介 ---------------------------------------------------------------------------------- 1 2.2、结构概括--------------------------------------------------------------------------------- 12.4砌筑概况----------------------------------------------------------------------------------- 2三、施工计划 ---------------------------------------------------------------------------------- 23.1 组织机构 ---------------------------------------------------------------------------------- 2 3.2进度计划安排----------------------------------------------------------------------------- 23.3施工现场安排----------------------------------------------------------------------------- 3四、施工准备 ---------------------------------------------------------------------------------- 34.1技术准备----------------------------------------------------------------------------------- 3一、编制依据1.1西山千亩保障性住房项目玉门小区一区施工图纸。

二次结构砌筑专项施工方案

二次结构砌筑专项施工方案

633.编制单位:编制日期:目录第一章工程概况 (4)1.1、概况: (4)1.2、墙体构造及技术要求: (5)1.2.1、非承重的外围护结构: (5)1.2.2、内隔墙 (5)1.2.3、南区、北区地下室墙体材料及性能列表 (5)1.2.4、南、北区地上墙体材料及性能列表 (6)1.3、工程项目参与单位: (7)第二章引用标准 (7)第三章施工准备 (8)1.1、技术准备 (8)1.2、机具准备 (8)1.3、人员准备 (8)1.4、材料准备 (8)第四章施工工艺 (10)4.1、施工工序 (10)4.2、基层处理 (10)4.3、放线 (10)4.4、植筋及连接钢筋 (11)4.5、墙脚处理 (11)4.6、排砖 (11)4.7墙体砌筑 (12)4.8、门窗抱柱、构造柱、门窗过梁、水平系梁施工 (12)4.9、水电安装跟进 (25)4.10、砌体填充墙施工注意事项: (26)第五章安全施工 (28)第六章质量控制 (29)6.1、主控项目: (29)6.2、一般项目 (29)6.3、墙体砌筑标准 (29)6.4、墙体的允许偏差和检验方法 (30)第七章成品保护 (31)第一章工程概况1.1、概况:本工程**㎡;1、地下建筑:**㎡;2、地上建筑:**3、总建筑面积约为**㎡;4、建筑结构安全等级为二级;5、建筑抗震等级表1.2、墙体构造及技术要求:1.2.1、非承重的外围护结构:不作为保温层时采用轻集料砼小型空心砌块1.2.2、内隔墙主要使用两种材料: 采用300、200、100厚的轻集料砼小型空心砌块及加气混凝土砌块。

1.2.3、南区、北区地下室墙体材料及性能列表应用部位隔墙材料及厚度密度隔声要求耐火极限(Kg/m3)(Rw+Ctr/C)(h)自行车200厚轻集料砼小型空心砌块≤900 ≥45dB ≥1.00车库200厚轻集料砼小型空心砌块≤900 ≥45dB ≥1.00楼梯间 200厚轻集料砼小型空心砌块≤900 同相应部位要求≥2.00 设备机房200厚轻集料砼小型空心砌块≤900 ≥55dB ≥2.00 (墙面吸声处理)防火墙 200厚加气混凝土砌块≤900 同相应部位要求≥3.00 工具间 200厚轻集料砼小型空心砌块≤900 ≥45dB ≥2.00管井 100/200轻集料砼小型空心砌块≤900 同相应部位要求≥1.001.2.4、南、北区地上墙体材料及性能列表应用部位隔墙材料及厚度密度隔声要求耐火极限(Kg/m3)(Rw+Ctr/C)(h)楼梯间 200厚轻集料砼小型空心砌块≤900 同相应部位要求≥2.00 设备机房200厚轻集料砼小型空心砌块≤900 ≥55dB ≥2.00 (墙面吸声处理)结构洞轻集料砼小型空心砌块≤900 同相应部位要求≥2.00防火墙 200厚加气混凝土砌块≤900 同相应部位要求≥3.00 其他各部位轻集料砼小型空心砌块≤900 同相应部位要求≥2.00注:1、特殊部位需要改变墙厚,详见图纸2、构造做法参《砌体填充墙结构构造》“12G614-1”1.3、工程项目参与单位:工程名称:**第二章引用标准《砌体填充墙结构构造》“12G614-1”《砌体结构设计规范》“GB50003-2001”《建筑抗震设计规范》“GB50011-2001”《砌体工程施工质量验收规范》“GB50203-2011”《建筑砂浆配合比设计规程》“JGJ98-2002”《混凝土小型空心砌块建筑技术规程》“JGJ/T14-2004”《混凝土小型空心砌块砌块灌孔混凝土》“JC861-2000”《干拌砂浆应用技术规程》“DBJ/T01-73-2003”《建筑安装分项工程施工工艺规程》“DBJ/T01—26—2003”《民用建筑节能设计标准》“DBJ01-602-2004”《公共建筑节能设计标准》“DBJ01-621-2005”《民用建筑热工设计规范》“GB50176-93”《轻集料混凝土技术规程》“JGJ51-2002”《建筑工程质量验收统一标准》“GB50300-2001”第三章施工准备1.1、技术准备1)熟悉施工图纸,了解砌体材料。

二次(砌体)结构施工方案

二次(砌体)结构施工方案

目录第一章编制依据 (2)一、施工合同及主要规范、规程和标准 (2)二、施工图纸 (2)三、主要规范、图集及标准 (2)四、主要法规(国家、行业) (2)第二章工程概况 (3)工程概况 (3)第三章施工准备 (3)一、专业设计概况 (3)二、技术准备 (9)三、施工员准备 (9)四、砌墙工程 (10)五、钢筋绑扎 (13)六、植筋 (14)七、模板 (17)八、应注意的质量问题 (17)第四章施工安排 (18)一、蒸气加气砌块砌筑施工准备 (18)二、砌体结构施工工艺 (19)三、交叉作业与配合施工 (25)第五章安全生产、文明施工 (26)第六章工期及进度控制 (27)第七章工程实例 (27)第一章编制依据一、施工合同及主要规范、规程和标准:《重庆市公安局档案馆施工合同》《建筑工程施工质量验收统一标准》GB50300-2001《砌体工程施工质量验收规范》GB50203-2002《砌体结构设计规范》GB50003-2001《砌筑砂浆配合比设计规程》JGJ98-2000《建筑装饰装修工程施工质量验收规范》GB50210—2001二、施工图纸:表1—三、主要规范、图集及标准:参见《重庆市公安局档案馆工程施工组织设计》四、主要法规(国家、行业):第二章工程概况工程概况:本工程为重庆市公安局档案馆,位于江北区石子山街24号,西临内环高速,距观音桥商业圈6公里,距解放碑11公里.本建筑结构为框架剪力墙结构,建筑结构安全等级为二级,抗震设防6度.地下1层,地上6层,本项目总建筑面积8569。

49平方米,建筑高度27。

6米(室外地坪算至女儿墙顶)。

第三章施工准备一、专业设计概况1、本工程采用框架剪力墙结构体系,外墙采用加气混凝土空心砌块,其余参见结构图细部要求,其构造和技术要求见国标02J102—2及本施工方案。

2、墙体厚度及定位:墙体厚度除注明者外均为200,轴线中分;或者100,轴线靠边.3、预留洞的封堵:砌筑墙留洞待管道设备安装完毕后,用C20细石混凝土填实;变形缝处双墙留洞的封堵,应在双墙增设套管。

二次结构砌筑工程施工方案

二次结构砌筑工程施工方案

二次结构砌筑工程施工方案一、施工前准备工作1.编制施工组织设计方案,明确施工任务、施工方法和施工流程。

2.进行现场踏勘,了解工地环境和地质情况,确定施工范围。

3.准备好施工所需的设备、材料和人力资源。

4.制定施工安全措施,进行安全培训和防护设施设置。

二、施工方法选择1.砌筑基础工程首先采用挖土机或人工进行基坑开挖,然后按照设计要求进行基础处理,包括夯实、浇筑等步骤。

2.采用专业施工设备(如起重机、混凝土搅拌车等)进行砌筑工程。

3.根据设计要求和施工实际情况,选择合适的砌筑材料和砌筑方法,如砖砌、石砌或混凝土砌筑等。

4.在砌筑过程中,注意使用水平仪、墙板仪等测量工具,保证砌筑的垂直度、水平度和尺寸精度。

5.结构砌体施工需要注意墙面的光滑度,采用刮平机等工具进行处理。

三、施工流程1.砌体基础工程:包括基坑开挖、基础处理和基础浇筑。

2.砌筑墙体工程:依照设计要求,进行墙体的砌筑。

墙体的砌筑顺序应从下到上,从内到外进行。

3.砌筑梁柱工程:根据设计要求和施工计划,进行梁柱的砌筑。

梁柱的砌筑应注意固定梁柱钢筋骨架,保证其稳定性和强度。

4.房屋二次结构砌筑:包括地板、楼梯、吊顶等二次结构砌筑工程。

地板的砌筑顺序应从下到上,楼梯的砌筑顺序应从下到上,吊顶的砌筑顺序应从上到下。

四、质量控制1.在施工过程中,严格按照设计要求和施工规范进行施工,保证施工质量。

2.定期进行质量检查和验收,发现问题及时整改。

3.采用现代化的施工监控和自动化设备,对施工质量进行实时监控和记录。

4.砌筑工程完工后,进行质量验收和交付,确保符合设计要求和相关法规。

五、安全管理1.制定施工现场安全管理制度,明确责任。

2.设置安全警示标志,保持施工现场的安全秩序。

3.对施工人员进行安全培训,提高安全意识和技能。

4.进行定期安全检查和隐患排查,发现问题及时处理。

5.建立应急预案,做好应急处理措施。

六、环境保护1.严格遵守环境保护法律法规,合理利用资源和能源。

二次结构砌体施工方案

二次结构砌体施工方案

二次结构砌体施工方案1. 背景介绍在建筑施工中,砌体结构是一种常见且重要的施工方式。

而在砌体结构中,二次结构砌体承担着支撑主要负荷、传递力的任务。

因此,设计和施工方案的准确性和可靠性对于确保建筑物结构的安全和稳定性非常重要。

2. 方案目标本施工方案的目标是确保二次结构砌体施工过程中的质量、效率和安全性。

具体目标包括:- 保证砌体墙体结构的垂直度和水平度- 确保砌体墙体结构的强度和稳定性- 提高施工效率和减少成本- 保障工人的安全和劳动环境3. 材料准备为了保证施工的质量和稳定性,我们将使用以下材料:- 砖块:选用符合国家标准的砖块,尺寸一致、无裂缝和明显的缺陷。

- 砂浆:采用水泥、砂和其他添加剂的配比,以确保砌体结构的粘合力和强度。

- 钢筋:按照结构设计要求,使用优质的钢筋,确保砌体的抗震性和承载能力。

4. 施工步骤此施工方案的步骤如下:步骤一:基底处理- 清理基底的灰尘和杂物,确保基底表面干净平整。

- 涂抹底层砂浆,以填补基底表面的凹凸不平。

步骤二:墙体砌筑- 按照图纸要求和标高控制,采用砌筑工艺进行砌体墙体的施工。

- 在墙体中加入钢筋以提高墙体的强度和稳定性。

- 在墙体砌筑过程中,加强对垂直度和水平度的控制,以确保砌体墙体的准确性和稳定性。

步骤三:砌体连接- 在砌体墙体之间,使用砂浆进行连接,以增加墙体的整体强度和稳定性。

- 可根据需要采用金属连接件来加固砌体墙体之间的连接。

步骤四:墙体防水处理- 在二次结构砌体施工完成后,进行墙体防水处理,以保护墙体免受水分和潮气的侵蚀。

5. 施工质量控制为了确保施工质量,我们将采取以下质量控制措施:- 严格按照设计图纸和施工工艺要求进行施工,确保施工的准确性和一致性;- 定期检查施工现场,确保施工过程中质量问题的及时发现和处理;- 对施工材料进行严格的质量检验,确保材料的合格性和适用性;- 对施工现场进行安全检查,确保工人的安全和劳动环境的良好。

6. 施工安全措施在砌体施工过程中,我们将采取以下安全措施:- 提供安全防护设施,如安全帽、安全绳等,确保工人的人身安全;- 定期进行安全教育培训,提高工人的安全意识和技能;- 严禁施工现场吸烟,禁止携带易燃、易爆物品。

二次砌体结构施工方案

二次砌体结构施工方案

二次砌体结构施工方案一、施工准备工作1.进行工地平整和清理,确保施工区域平坦,无垃圾和障碍物。

2.搭建安全围挡,并设置明显的安全警告标志,确保施工区域安全。

3.进行土方开挖,按照设计要求开挖基坑,并清理基坑内的泥浆、石块等物料。

二、砌体材料准备1.预先准备好所需的砌体材料,包括砖块、水泥、石灰等。

2.检查砌体材料的质量和数量,确保满足施工需要。

3.按照设计要求进行砌体材料的配比,确保施工质量。

三、基础处理1.对主体结构上的基础进行清理和处理,确保基础表面平整、无杂物。

2.刷涂防水材料,对主体结构上的基础进行防水处理,以防止水分渗透。

四、二次砌体施工工艺1.按照设计要求,在基础上进行砂浆找平,使其表面平整。

2.在找平层上进行第一层砌筑,选用适当规格的砖块进行砌筑,砖缝应留有适当的伸缩缝。

3.定期检查砌筑质量,确保墙体垂直、水平。

4.进行砌筑墙体的抹灰工艺,包括底层抹灰和面层抹灰,抹灰厚度一般为2-3毫米。

5.对已砌筑的墙体进行养护,保持墙体湿润,防止开裂和脱落。

五、二次砌体结构施工注意事项1.施工过程中要注意安全,穿戴好安全防护装备,保障施工人员的人身安全。

2.施工过程中要严格按照设计要求进行施工,确保施工质量。

3.施工现场应保持整洁,材料堆放有序,避免堆放过多杂物,防止施工过程中出现意外事故。

4.施工过程中要注意与其他施工工序的协调配合,确保工期的顺利进行。

5.砌体施工完毕后,对施工现场进行清理,清除垃圾和残留物,恢复场地环境。

六、施工质量控制1.建立质量检查制度,对施工过程进行定期检查,及时发现和处理存在的质量问题。

2.严格按照设计要求进行施工,确保墙体的垂直度和水平度符合要求。

3.对施工现场进行质量验收,必要时可以进行抽样检测,确保施工质量达到设计要求。

通过以上的施工方案,可以保证二次砌体结构的施工质量,提高建筑物的稳定性和承重能力。

同时,要加强施工现场的管理和协调配合,确保施工进度和质量的控制。

二次结构砌体施工方案

二次结构砌体施工方案

二次结构砌体施工方案1. 引言本文档旨在提供一个二次结构砌体施工的详细方案,以确保施工过程高效、安全,并满足设计要求。

本方案包括施工前的准备工作、砌体材料的选择、施工步骤和安全注意事项等内容。

2. 准备工作在施工前,需要进行一系列准备工作,以确保施工能够顺利进行。

以下是准备工作的步骤:•确定施工区域的准确位置,并将其与设计图纸进行核对,确保无误。

•开展土方工作,清除施工区域内的障碍物。

•准备必要的工具和设备,如砌筑批灰工具、搅拌机、脚手架等。

•制定详细的施工计划,包括施工顺序、施工进度等。

3. 砌体材料的选择在二次结构砌体施工中,选择适当的砌体材料对确保工程质量至关重要。

以下是一些常用的砌体材料:•红砖:常用的砌体材料之一,具有较好的抗压强度和耐久性。

•空心砖:常用于墙体内部,减轻自重并提供一定的隔热效果。

•石材:用于特殊要求的建筑物或装饰部分,具有天然美观的特点。

•粘土砖:一种环保的砌体材料,具有良好的吸水性和保温性能。

根据实际情况和设计要求,选择合适的砌体材料。

4. 施工步骤施工步骤是确保施工质量的关键,以下是二次结构砌体施工的主要步骤:4.1 搭设脚手架首先,需要搭建脚手架以便施工人员可以方便地进行砌体工作。

脚手架应该稳固可靠,并按照相关安全规范进行设置。

4.2 粘贴基准线在开始砌体工作前,需要根据设计要求,在墙体表面上粘贴基准线。

基准线的位置应准确无误,并标明墙体的高度和宽度。

4.3 砌墙体根据基准线和设计要求,在墙体的一侧开始砌体工作。

使用砌筑批灰工具将砂浆均匀地涂抹在砖块上,然后将砖块粘贴到墙体上,确保垂直和水平的准确性。

同时,在砌墙的过程中,要随时检查墙体的垂直性和水平性。

4.4 安装墙梁和柱子在墙体的上方,根据设计要求,安装墙梁和柱子。

使用适当的工具和设备将墙梁和柱子与墙体连接在一起,确保其牢固度和准确性。

4.5 完善细节部分在砌墙体和安装墙梁和柱子后,需要对细节部分进行完善。

包括墙体的防水处理、墙体的外部装饰等。

二次结构施工方案

二次结构施工方案

二次结构施工方案(一)概况1、外墙:外墙除现浇钢筋混凝土剪力墙外,采用200、300厚B05蒸压砂加气混凝土砌块砌筑,采用专用胶粘剂;内墙采用200厚陶粒混凝土空心砌块墙,地上内墙采用M5混合砂浆砌筑。

2、砌块强度及砂浆强度:蒸压砂加气混凝土砌块干密度≯600kg/m³,强度外墙不低于A3.5;(二)砌筑要求1、与框架柱连接的填充墙,填充墙沿框架柱全高每隔500mm~600mm设2根φ6拉筋,沿墙全长贯通,锚入墙、柱内180mm。

2、框架结构砌体填充墙构造柱间距按不大于6m设置,截面为墙厚×240mm,配筋4φ12,φ6@200,构造柱下端锚入地面以下500mm。

上端锚入板或梁内,锚固长度不小于35d,构造柱上下端楼层处1/6层高范围内,箍筋间距加密到100,构造柱与楼面相交处在施工楼面时应留出相应插筋。

填充墙转角处应加构造柱。

3、墙高度超过4m时,应在门洞上方或墙高中部设置一道与柱连接的通长钢筋混凝土圈梁,墙高大于7m时应设2道圈梁。

截面宽同墙厚,高240mm,配筋4φ14,φ6@200mm,圈梁兼作过梁时,应在洞口上方按过梁要求确定截面和钢筋。

隔墙砌筑非承重隔墙顶部应采用砖斜砌顶紧或加木楔挤紧后用砂浆填实,后砌填充墙或隔墙长大于5m时,墙顶部与梁(板)宜有钢筋拉结。

梁板应预埋插筋,并随砌墙时用不低于M5砂浆,分层填实。

见下图:(三)作业条件1、砌块砌筑施工前,必须作好上道工序的隐检,质量验收合格,并且办完隐验手续,操作面清理干净。

2、根据施工要求,进行水平标高抄测工作,不符合要求的部分要先进行处理。

3、砌筑基层面上弹出纵横墙轴线、边线、门窗洞位置线及其它尺寸线,并复测合格,经监理单位复核无误签证。

4、拌制砂浆所用的搅拌机及计量台磅秤安装就绪,且试转正常,砂浆配合比标示牌须设挂到位。

5、操作面的安全防护设施已安装到位,并经安全人员检查,符合有关安全规定。

(四)预拌砂浆要求1、预拌砂浆进场储存(1)材料进场时,生产厂家要提供产品的质量证明文件及使用说明书等。

二次结构砌体施工方案

二次结构砌体施工方案

二次结构砌体施工方案1. 概述1.1 项目背景二次结构砌体施工是建筑施工中的重要环节,直接影响着建筑物的质量和安全性。

本文旨在探讨二次结构砌体施工方案,确保施工顺利进行。

1.2 施工目标确保二次结构砌体施工质量,保障建筑物结构安全,提高施工效率。

2. 施工准备2.1 材料准备•砌体材料:选用符合标准规定的砖块、砂浆等材料;•工具设备:保证工地上具备必要的砌筑工具和设备,如砌筑刀、水平仪、捆绑材料等。

2.2 施工人员组建砌体施工小组,确保施工人员具备相应的操作技能和安全意识。

3. 施工流程3.1 基础准备在确保地基稳固的前提下,进行墙体竖直线设置,为后续砌体施工提供参考。

3.2 墙体砌筑根据设计要求,进行砌体结构的搭建,注意保持墙体的水平、竖直度,及时做好墙体的抗裂处理。

3.3 结构连接对砌体结构进行连接固定,加强结构的稳定性和承载能力。

4. 施工注意事项4.1 安全保障施工现场要严格执行安全操作规程,做好安全警示标识,保障施工人员和周围环境的安全。

4.2 质量控制加强质量管理,严格按照施工方案进行操作,确保砌体结构质量达标。

5. 施工结束5.1验收完成砌体施工后进行自检,保证砌体结构的稳固性和符合设计要求。

5.2 竣工整理施工现场,做好竣工记录和资料整理,确保施工过程留痕可追。

6. 总结二次结构砌体施工是建筑工程中至关重要的环节,合理的施工方案和严格的执行是保障施工质量和安全的关键。

希望通过本文的分享,能为砌体施工人员提供一定的参考和指导,确保施工质量和效率达到预期目标。

二次结构墙体砌筑施工方案

二次结构墙体砌筑施工方案

目录1.编制依据 (2)2.工程概况 (3)3.施工准备 (5)4.主要施工方法 (10)5.质量要求和质量验收 (20)6.安全文明施工 (24)1.编制依据1.1.《翻建书库项目施工组织设计》1.2.《翻建书库项目结构、建筑施工图》1.3.《工程做法》(08BJ1-1)1.4.《墙身-加气混凝土(砌块、条板隔墙)》(88J2-3A)1.5.《墙身-外墙保温》(88J2-9)1.6.《无障碍设施》(88J12-1)1.7.《常用门窗》(05J4-1)1.8.《地沟及盖板》(02J331)1.9.《内装修-室内(楼)地面及其他装修构造》(03J502-3)1.10.《屋面工程质量验收规范》(GB0207-2002)1.11.《砌体结构工程施工质量验收规范》(GB50203-2011)1.12.《建筑地面工程施工质量验收规范》(GB50209—2010)1.13.《建筑装饰装修工程质量验收规范》(GB50210—2001)1.14.《建筑涂饰工程施工及验收规范》(JGJ29-2003)1.15.《建筑工程施工质量验收统一标准》(GB50300-2001)1.16.《安全防范工程技术规范》(GB50348-2004)1.17.《施工现场临时用电安全技术规范》(JGJ46-2005)1.18.《建筑机械使用安全技术规程》(JGJ33-2001)1.19.《建筑施工高处作业安全技术规范》(JGJ80-91)1.20.《混凝土结构后锚固技术规程》(JGJ-145-2004)1.21.《建筑施工手册》2.工程概况2.1.本工程位于大兴区西红门镇七村,南侧紧邻南五环,地下一层为库房,地上两层为办公室。

本工程建筑面积为:2600.44㎡。

内外高低差为0.9m。

采用现浇钢筋混凝土框架结构。

2.2.主要做法2.3.工程质量目标争创竣工“优质工程”与“安全文明工地”。

2.4.工期目标本工程装修计划工期为:2012年8月1日至2012年10月31日。

二次结构施工方案砌体

二次结构施工方案砌体

二次结构施工方案砌体在建筑结构中,二次结构是指承担主要荷载的主体结构之外的部分,主要由砖墙和混凝土柱、梁组成。

在建筑二次结构的施工中,砌体是其中一项重要的工作。

下面将详细介绍二次结构砌体的施工方案。

砌筑砖墙是建筑施工的常见工序,其目的是构筑建筑物的承重墙、隔墙、围护墙等。

砌筑砖墙的第一步是确定墙体的厚度和尺寸,然后根据设计图纸确定墙体的起砖线和终砖线,并在墙体两端拉线确认墙体的轴线位置。

接下来,根据墙体的高度和砖的规格,计算砖墙需要的砖块数量,以便提前准备好足够的砖块。

在砌筑砖墙之前,需要进行墙体的找平工作。

首先,在墙体基底上铺设一层水泥砂浆,然后使用水平仪和嵌线器进行调整,确保墙体的垂直度和水平度。

随后,使用水泥砂浆在墙体上进行找平,将不平的地方填平,以便建设牢固的墙体。

砖墙的砌筑一般采用砌筑法进行施工。

首先,将砂浆均匀涂抹在一块砖的底部,然后将砖从一侧放置在墙体的起砖线上,注意保持与墙体的垂直度。

接下来,再涂抹一层砂浆,将另一块砖与第一块砖连接,保持砖与砖之间的间隙均匀,并使用坡尺进行调整。

以此类推,逐渐砌筑整个墙体,保持墙体的垂直度和水平度。

在砌筑过程中需要留出空洞或门窗洞口,这需要进行模板支撑和钢筋悬挂,以保持洞口的规整和稳定。

当墙体达到一定高度时,还需要安排水平带和脚手架,以便工人在高处进行作业,并提高施工效率。

另外,为了增强砖墙的稳定性和承载能力,还需要进行墙体加固。

常见的加固方法有加贴预埋件、承重钢筋混凝土柱、墙面钢筋网等,根据实际需要选择适当的加固措施。

在砌筑砖墙完成后,需要进行墙体的验收和修整工作。

首先,使用长尺或水平仪检查墙体的垂直度和水平度,如有偏差,则进行调整。

再次检查墙体砖与砖之间的缝隙,如有不均匀或高低差,需进行修整。

最后,清理墙体表面的杂物和残留物,使墙体看起来整洁美观。

总结来说,二次结构砌体的施工方案包括确定墙体尺寸、找平墙体、砌筑砖墙、安排洞口和加固墙体等。

在砌筑过程中,需注意墙体的垂直度和水平度,以及砖与砖之间的缝隙和墙体表面的修整。

二次结构砌体工程施工方案

二次结构砌体工程施工方案

目录一、编制依据..................................................................................................................................................... - 1 -二、工程概况..................................................................................................................................................... - 1 -三、施工准备....................................................................................................................................................... - 1 -3.1、施工场地准备...................................................................................................................................... - 1 -3.2、技术准备.............................................................................................................................................. - 1 -3.3、组织准备.............................................................................................................................................. - 1 -3.4、机械配置.............................................................................................................................................. - 1 -四、工期筹划....................................................................................................................................................... - 2 -五、施工总体部署............................................................................................................................................... - 2 -六、主要施工工艺............................................................................................................................................... - 2 -6.1、砌筑工程.............................................................................................................................................. - 2 -6.1.1材料要求...................................................................................................................................... - 2 -6.1.2工艺流程...................................................................................................................................... - 2 -6.1.3砌筑施工...................................................................................................................................... - 2 -6.1.4砌筑工程质量要求...................................................................................................................... - 3 -七、测量控制....................................................................................................................................................... - 4 -八、质量目标、保证体系及保证措施............................................................................................................. - 4 -8.1 工程质量保证措施................................................................................................................................ - 4 -8.2 建立工序质量控制体系........................................................................................................................ - 5 -九、环境保护及文明施工措施......................................................................................................................... - 6 -9.1 环境保护措施........................................................................................................................................ - 6 -9.2 文明施工措施........................................................................................................................................ - 7 -十、安全目标、保证体系及保证措施............................................................................................................. - 8 -一、编制依据1.1 主体建筑设计图纸。

二次结构墙体砌筑施工方案

二次结构墙体砌筑施工方案

二次结构墙体砌筑施工方案
一、施工准备
在进行二次结构墙体砌筑施工前,需进行如下准备工作:
1.施工图纸和设计方案的审查,了解墙体布置、尺寸等要求;
2.确定施工现场,清理杂物,进行标高测量和墙体定位标记;
3.准备所需的材料和工具,如砖瓦、砂浆、水平仪、抹水工具等;
4.安排施工人员,确保具备相关施工经验和技能。

二、砌体标高控制
1.根据设计要求和标高测量结果,确定砌体的起始标高和砌筑高度;
2.在墙体基础上设置标高线,用水平仪和标尺进行标高控制,保证墙体
垂直度和水平度。

三、砌体砌筑方法
1.将预先配好的砂浆均匀涂抹在砖瓦上;
2.将砖瓦按规定的砌法和尺寸逐层砌筑,留出砂浆缝;
3.使用水平仪保证墙体的垂直度和水平度,及时修正偏差。

四、砂浆配制和砌筑质量要求
1.确保砂浆的配制比例准确,搅拌均匀;
2.砌筑过程中保持砂浆层均匀,砖瓦紧密贴合,砂浆缝适中;
3.检查墙体表面平整度和垂直度,修正出现的缺陷。

五、砌体砌筑中的注意事项
1.遇到天气变化大的情况,及时采取措施保护砌筑墙体;
2.施工过程中要及时清理施工现场,确保安全、整洁;
3.定期检查砌体砌筑质量,及时处理发现的问题。

六、施工安全措施
1.搭设好安全防护设施,如安全网、标志牌等;
2.施工人员需佩戴好安全防护用品,注意安全操作;
3.严格按照施工规范和流程进行作业,杜绝事故发生。

以上为二次结构墙体砌筑施工的基本方案,施工过程中需认真执行,确保施工质量和工程安全。

二次结构施工方案(砌体)

二次结构施工方案(砌体)

二次结构施工方案(砌体)一、施工准备在进行二次结构施工之前,首先需要进行施工准备工作。

具体步骤如下:1.材料准备:–硅酸盐砖、水泥、沙子等施工所需的砌体材料;–钢筋、绑扎线等辅助材料;–水平仪、量具等施工工具。

2.人员组织:–组织好砖瓦工、钢筋工等施工人员;–制定施工计划,明确工作职责。

3.施工场地:–清理施工场地,确保施工区域平整、干净;–搭建必要的安全防护设施。

二、施工步骤1. 基础处理在进行砌体二次结构施工之前,需要对基础进行处理,确保基础牢固、平整。

具体步骤如下:•清理基础表面的杂物和灰尘;•用水泥砂浆找平基础,确保基础表面平整。

2. 砌体墙体施工砌体墙体是二次结构的关键部分,施工质量直接影响整体结构的稳定性。

具体施工步骤如下:•按照设计要求,在基础上进行墙体布置标线;•使用硅酸盐砖和水泥砂浆进行砌筑,注意保持墙体的垂直和水平;•钢筋的设置要符合设计要求,与砌体墙体连接牢固。

3. 砌筑梁柱在砌体二次结构中,梁柱的砌筑也是至关重要的一环。

具体步骤如下:•设计好梁柱的位置和尺寸,与墙体砌筑衔接;•采用相应强度的砖块和水泥砂浆进行梁柱的砌筑;•使用钢筋加固梁柱的连接处,确保梁柱的稳固性。

4. 渗漏处理在二次结构施工完成后,需要对墙体进行渗漏处理,以确保整体结构的密封性。

具体步骤如下:•对墙体表面进行清理,去除灰尘和浮浆;•使用防水材料进行涂刷,确保墙体表面的防水性;•检查墙体表面,处理漏洞和裂缝,确保墙体的完整性。

三、施工质量验收二次结构施工完成后,需要进行质量验收工作,确保施工质量符合设计要求。

具体验收内容如下:•墙体垂直度和水平度的检查;•砌体墙体的强度和稳定性测试;•梁柱连接处的牢固性检验;•渗漏处理效果的检查。

四、施工安全注意事项在二次结构的施工过程中,需要注意施工安全,做好安全防护工作。

具体注意事项如下:•着装符合安全要求,佩戴安全帽、手套等防护用具;•施工现场保持整洁,防止材料堆放混乱导致意外发生;•使用施工工具时要注意操作规范,避免造成伤害;•严格执行施工操作规程,确保施工过程安全顺利。

二次结构施工方案

二次结构施工方案

二次结构施工方案第一小节、加气混凝土砌块施工:第一条、施工要点:在基础平面或楼面需砌筑加气混凝土砌体墙部位处对基层清理和找平,并弹出墙体的中线、边线与门、窗洞口位置。

目的是:为了保证砌体的位置正确。

并由上而下计算好皮数(含水平灰缝高度、斜块砌筑空间预留)。

在底皮砌块高度不规则时可采用水泥砖或素混凝土和特制规格的砌块砌筑。

在砌筑第一皮砌块前,按设计排块的要求进行试摆,目的是:为了更好发挥砌体的力学性能,上下皮砌块的搭接长度不宜小于砌块长度的1/3;在“L”、“T”、“十”型接头处砌筑时咬砌,以保证砌体的整体稳定性;通过试摆能确定采用哪几种型号规格,尽量减少非型号规格的用量,达到减少锯砖的目的;通过试摆,可以校正皮数杆上的尺寸是否有误。

试摆后在砌筑第一皮砌块前,先用水润湿基面,再用砂浆铺砌,砌块的垂直灰缝披刮粘结剂(如果采用普通砂浆施工的,在垂直灰缝处披刮普通砂浆),并注意校正砌块的水平和垂直度,待第一皮砌块的水平灰缝的砌筑砂浆初凝后方可进行上皮砌块的砌筑。

常温下,砌块的日砌筑高度宜控制在1.8m内。

对于所需的非规格尺寸砌块采用手提式电锯或相应的机械设备进行切割成规则长方体,严禁刀劈斧砍。

砌筑施工时,在每皮砌块砌筑前,要用毛刷清理砌块表面浮砂,处理干净后再铺水平、垂直灰缝处的粘结剂、混合砂浆。

每皮砌块砌筑时,注意校正水平、垂直位置,并做到上下皮砌块错缝搭接、表面平整、水平灰缝基本平直。

上下搭接长度不宜小于被搭接砌块长度的1/3,竖向通缝不大于两皮。

采用混合砂浆砌筑时,将砂浆铺设于下皮砌块表面及待砌砌块的端面。

砌筑墙面平整干净、灰缝处无溢出的砂浆。

砌上墙的砌块不任意移动或撞击,不得用敲打的方法来校正墙面,如有不平整,用钢齿磨砂板磨平,使偏差控制在允许范围内,对于有很大偏差值的墙体,拆除重新进行铺浆砌筑。

墙体水平配筋时预先在砌块的水平灰缝面开设通长的凹槽,置入钢筋后,用M5水泥砂浆填实至槽的上口平。

砌体与钢筋混凝土柱交接处,在柱内预留拉结钢筋进行拉结或L 型铁件连接。

建筑二次结构砌体施工方案

建筑二次结构砌体施工方案

建筑二次结构砌体施工方案建筑二次结构是指建筑物中除主体结构外的其他结构,包括砌体墙体、梁柱体系、楼板等。

砌体施工方案是指在建筑二次结构中的砌体墙的施工方案。

下面将就砌体施工方案进行详细阐述,主要包括砌体墙体选材、施工方法、注意事项等方面的内容。

首先是砌体墙体选材。

砌体墙体的主要选材有砖块、砌筑砂浆、砌筑胶等。

在选择砖块时,应考虑砖块的材质、规格、强度等方面的要求。

常用的砖块有实心砖、空心砖、多孔砖等。

在选择砌筑砂浆时,应根据墙体的承重要求、粘结力要求等因素进行确定。

同时还要注意砌筑胶的选择,砌筑胶主要是用于墙体的定位和加固,要选择符合要求的品牌和型号。

其次是砌体墙的施工方法。

首先要进行墙的定位和标高,确定好墙体的位置和高度。

然后进行基础的施工,也就是墙的下部分。

墙的下部分应当注意按要求进行基础处理,确保墙体的稳定性。

接下来是墙的砌筑,根据设计要求和图纸进行墙的砌筑。

砌筑过程中要注意墙的垂直度和水平度的控制,确保墙体的垂直性和平整度。

墙的砌筑应采用砌筑砂浆进行,砌筑砂浆应根据墙的要求进行配比。

墙的顶部要进行檐口、龙骨或者梁的施工,确保墙的上部结构完整和稳固。

再次是砌体施工的注意事项。

在进行砌体施工过程中,要注意施工过程中的质量控制,确保墙的质量符合要求。

在墙的砌筑过程中,要采用适当的方法进行砌筑,避免出现墙体的开裂、变形等情况。

同时,还要注意施工过程中的安全措施,确保施工人员的安全。

另外,在砌体墙体施工过程中,还要注意环境保护,合理利用资源,减少对环境的影响。

总结起来,砌体施工方案是确保建筑二次结构中砌体墙的质量和安全的重要方案。

在施工过程中,应根据砌体墙的具体要求,选择适当的材料和施工方法,并注意遵循相应的施工规范和标准,确保砌体墙的质量和施工效果。

同时,还应加强施工过程中的质量控制和安全措施,保证施工的安全和质量。

此外,还要注意环境保护,减少施工对环境的影响。

通过合理的砌体施工方案,可以确保砌体墙的稳定性和持久性,为建筑的整体结构提供良好的支撑。

二次结构砌体施工方案

二次结构砌体施工方案

二次结构砌体施工方案一、工程概况非承重内隔墙、外围护墙全部采用加气混凝土砌块砌筑,填充墙的厚度有250mm、200mm 等规格,其中250mm厚填充墙为外围护墙,200mm厚填充墙为内隔墙。

填充墙依据图集砌筑,砌筑砂浆为M5水泥砂浆,砌块强度等级为MU3.5,密度W600kg/m3,砌体底部及顶部斜砌使用的烧结页岩砖强度等级为MU10,砌体结构中圈梁、构造柱、配筋带、抱框柱混凝土强度等级为C20。

二、施工部署1. 质量目标本工程质量目标为合格。

二次结构工程的质量目标为:各分项工程合格率100%。

2. 施工顺序根据现场实际情况,二次结构整体施工先后顺序为:从上向下,首先是五层砌筑,之后是四至一层砌筑。

二次结构砌筑前先做样板墙及样板间,经建设、监理、施工单位三方验收合格后方可进行全面施工。

3.施工准备工作任务划分4.劳动力配置6.材料进场及存放A.所有材料按计划进场,材料股负责及时供应。

材料进场后由工长、技术员、质检员同时验收,合格后方可使用,有复试要求的经试验合格后方可使用于工程中。

B.水泥、砂、石、轻集料砌块等材料按现场平面布置图堆放。

7.施工现场平面布置二次结构施工时应根据现场重新按照装修施工需要进行布置,但尽量利用现有的水、电、消防等设施及现场硬化路面。

在主楼西侧中间位置设置一部物料提升架。

三、施工准备1.技术准备工作A.专业技术人员熟悉图纸,对于图纸有问题的地方及时与设计联系解决。

B.编制主要材料及机具的需用计划,物资设备部门按计划分批按时组织进场。

C.专业技术人员编制分项工程技术交底,并及时向工长及施工人员进行图纸及分项工程技术交底。

E. 外管部门做好劳动力计划,并组织评审及选择工作。

2.施工准备工作A. 现场临时用电由甲方提供的变压器接入的现场总配电箱位于现场北侧,本工程采用TN~S三项五线制供电系统,各施工楼层设流动箱,以满足装修用电。

为了保证物料提升机的正常使用,物料提升机用电采用独立电源供电。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

二次结构砌体施工方案-CAL-FENGHAI-(2020YEAR-YICAI)_JINGBIAN二次结构砌体施工方案一、工程概况非承重内隔墙、外围护墙全部采用加气混凝土砌块砌筑,填充墙的厚度有250mm、200mm等规格,其中250mm厚填充墙为外围护墙,200mm厚填充墙为内隔墙。

填充墙依据图集砌筑,砌筑砂浆为M5水泥砂浆,砌块强度等级为,密度≤600kg/m3,砌体底部及顶部斜砌使用的烧结页岩砖强度等级为MU10,砌体结构中圈梁、构造柱、配筋带、抱框柱混凝土强度等级为C20。

二、施工部署1. 质量目标本工程质量目标为合格。

二次结构工程的质量目标为:各分项工程合格率100%。

2. 施工顺序根据现场实际情况,二次结构整体施工先后顺序为:从上向下,首先是五层砌筑,之后是四至一层砌筑。

二次结构砌筑前先做样板墙及样板间,经建设、监理、施工单位三方验收合格后方可进行全面施工。

3.施工准备工作任务划分4.劳动力配置劳动力均衡需求量如下:5.机械配置6.材料进场及存放A. 所有材料按计划进场,材料股负责及时供应。

材料进场后由工长、技术员、质检员同时验收,合格后方可使用,有复试要求的经试验合格后方可使用于工程中。

B. 水泥、砂、石、轻集料砌块等材料按现场平面布置图堆放。

7.施工现场平面布置二次结构施工时应根据现场重新按照装修施工需要进行布置,但尽量利用现有的水、电、消防等设施及现场硬化路面。

在主楼西侧中间位置设置一部物料提升架。

三、施工准备1.技术准备工作A. 专业技术人员熟悉图纸,对于图纸有问题的地方及时与设计联系解决。

B. 编制主要材料及机具的需用计划,物资设备部门按计划分批按时组织进场。

C. 专业技术人员编制分项工程技术交底,并及时向工长及施工人员进行图纸及分项工程技术交底。

E. 外管部门做好劳动力计划,并组织评审及选择工作。

2.施工准备工作A. 现场临时用电由甲方提供的变压器接入的现场总配电箱位于现场北侧,本工程采用TN~S三项五线制供电系统,各施工楼层设流动箱,以满足装修用电。

为了保证物料提升机的正常使用,物料提升机用电采用独立电源供电。

四、加气混凝土砌块施工1. 材料准备A. 本工程所选用的砌块材料必须是优质产品,砌块龄期宜大于35d,并且不得小于28d。

进场时必须提供材料的准用证、出厂合格证及检测报告,先进行严格仔细的外观检查,符合规范规定后才准入场。

进场后,按规范规定进行现场取样,送到检测部门进行检测,检测合格达到设计或规范要求的指标,并报监理批准后方准使用。

B. 所用的水泥必须有出厂合格证和检测报告,经北京市建委备案,并要按规范要求进行进场复试,复试合格报监理批准后方可使用。

施工中所用的砂浆必须按照设计要求进行配合比试配,按照试配的配合比进行搅拌,并留好试块,按规定送试。

2. 填充墙砌筑(一).操作工艺A.工艺流程:基层清理→放线→打孔、植筋→绑扎构造柱筋,甩墙拉筋→钢筋验收→砌体砌筑→支构造柱、配筋带、抱框模板→混凝土浇筑→剩余砌体砌筑及顶部处理→砌体验收2φ6沿墙高每设一道采用结构胶植筋2φ6沿墙高每设一道拉结筋植入深度80mm,配筋带100mm图1 拉结筋及配筋带拉结作法详图⑵.建筑隔墙过梁位置见建筑施工图,过梁宽同墙宽,高度及配筋详见下表1。

过梁采取现浇方法施工。

表1序号梁跨度L(mm)过梁长度梁高上筋下筋箍筋1L≤1000L+5001202Ф122Ф12φ6@10022000≥L>1000L+5001802Ф123Ф12φ6@15032500≥L>2000L+5002402Ф122Ф16φ6@15043000≥L>2500L+7003002Ф143Ф14φ6@15053500≥L>3000L+7003002Ф143Ф16φ8@200注:1、当砌体墙厚≤120mm时在墙中间位置可只设置1φ6@500。

2、当过梁高度不符合砌块模数时,可用普通砖补齐。

⑶.在填充墙的拐角处、T字形接头处、墙体端头处、沿墙长每4米处按设计要求设置构造柱,构造柱尺寸为墙厚240mm,柱主筋为4Ф12,柱箍筋φ6@200,构造柱与上下结构进行连接,连接方式同拉接筋。

构造柱主筋采取绑扎搭接方式,搭接长度为(600mm),沿构造柱高度每600mm预留2Φ6向墙内各伸出1000mm,详见图2、图3。

梁下筋见配筋表配筋带(外墙有)配筋带(内墙有)抱框筋2φ12,φ6@200过梁φ6@200上筋门口l<2100时洞口及抱框作法l<2100图4 门洞口宽度<时洞口及抱框做法 配筋带(外墙有)l≥2100抱框筋2φ12,φ6@200配筋带(内墙有)φ6@200过梁梁上筋梁下筋见配筋表抹灰预留厚度。

⑻.隔墙砌筑时砌块底部朝上,以便坐浆和浇筑混凝土配筋带,窗洞口两侧砌块无槽一端面向洞口,窗框固定点处需使用预制混凝土锚固块砌筑。

砌块应错缝搭接,搭接长度不小于90mm,灰缝高度10mm,构造柱部位采用马牙茬砌筑,马牙茬长度100mm。

⑼.填充墙砌至接近梁、板底时,应留一定的空隙,待填充墙砌筑完并至少间隔7天后,再用页岩砖斜砌挤紧,并用砂浆塞实。

90mm隔墙顶部无法采用斜砌时设压顶混凝土带,压顶混凝土带高度50-100mm,先在梁、板底固定Φ8膨胀螺栓,间距≤1000mm,再用通长φ6与膨胀螺栓焊接,最后用豆石混凝土塞实⑽.在隔墙施工前由技术人员做好排版图及技术交底详细传达给施工班组,并严格实施。

(三).施工技术措施⑴.测量人员在结构楼板上和框柱上放出轴线及水平标高线,砌筑施工人员根据图纸和轴线弹好墙体边线及门窗洞口位置线。

⑵.砌筑前应根据砌筑工程量及砌块模数制作皮数杆。

⑶.墙体砌筑时应单面挂线,随着砌体的增高要随时用靠尺校正平整度、垂直度,保证墙体垂直、平整,不允许砸砖修墙。

⑷.每天砌筑高度不得大于。

⑸.在砌筑砂浆终凝前时间内,应将灰缝刮平。

⑹.砌筑砂浆不准使用已经初凝的砂浆,且使用过程中不准随便加水,搅拌后的砂浆要尽快在短时间内用完,避免时间过长,砂浆凝固。

⑺.在浇筑圈梁、过梁、构造柱及配筋带、抱框混凝土时,要注意保证钢筋的保护层及钢筋的位置正确,混凝土要通过振捣棒和敲击方式进行振捣,保证混凝土密实。

⑻.水电专业作管应采用云石机切槽,隐检完毕后通知土建用干硬性豆石混凝土塞实、填满,抹灰前表面钉钢板网作加强处理。

(四). 质量标准1. 保证项目:①. 砌块的品种、规格、强度必须符合设计要求,有出厂合格证、试验报告。

②. 砂浆品种必须符合设计要求,强度必须符合下列规定:A、同品种、同强度等级砂浆各组试块平均强度不小于fm,k。

B、任意一组试块强度不小于,k。

C、砌体水平灰缝砂浆饱满,立缝填塞密实。

D、转角处严禁留直槎,其它部位应留斜槎。

2. 基本项目:①. 上下砌块错缝,块体搭砌长度≥90mm,竖向通缝不大于2皮。

②. 接槎处砂浆密实,砖缝平直,接槎处水平灰缝小于5mm或有透亮缺陷的不超过5个。

③. 拉结筋、构造柱、现浇钢筋混凝土带、抱框等均符合设计要求。

3. 允许偏差项目,见下表:序号项目允许偏差 (mm)检查方法1轴线位移10拉线尺量检查2垂直度≤10m5吊线、尺量检查3表面平整度8用2m靠尺,楔形尺检查4水平灰缝平直度10拉10m线,尺量检查5门窗洞口宽度(后塞口)高度±5尺量检查6水平灰缝厚度±2与皮数杆比较尺量检查7构造柱、配筋带、抱框等截面+10尺量检查8外墙窗口位置上下偏移20用经纬仪或吊线检查,以底层窗口为准4. 应注意的质量问题⑴. 砂浆强度不够:注意不使用过期水泥,计量要准确,保证搅拌时间,砂浆试块的制作、养护、试压应符合规定。

⑵. 墙体顶面不平直:砌到顶部时不好使线,墙体容易里出外进,应在梁底或板底弹出墙边线,认真按线砌筑,以保证墙体顶部平直通顺。

⑶. 砌体墙后剔凿:预留孔洞、预埋件应预留、预埋,防止后剔凿,以免影响质量。

⑷. 拉结筋不合砖行:拉结筋经常不能与砖行灰缝吻合,应预先计算砖行模数、位置、标高,依此进行植筋,不应将拉结筋弯折使用。

⑸. 锚固在墙、柱内的拉结筋任意弯折、切断:应注意保护,不允许任意弯折或切断。

5. 工程试验⑴. PSA 水泥进场使用前,应分批对其强度、安定性等项目进行复验。

检验批应以同一生产厂家、同一批次每≤200吨为一批。

⑵. 当在使用中对水泥质量有怀疑或水泥出厂超过三个月时,应复查试验,并按其结果使用。

⑶. 砂浆用砂不得含有有害杂物。

砂浆用砂的含泥量应满足:水泥砂浆和强度等级不小于M5的水泥砂浆、混合砂浆,不应超过5%。

⑷. 轻集料砌块和砂浆的强度等级必须符合设计要求,抽检数量:每一生产厂家,每1万块小砌块至少应抽检一组。

⑸. 每一楼层且不超过250m3砌体的砌筑砂浆,做一组试块,每台搅拌机应至少抽检一次。

每层留置构造柱、过梁混凝土试块一组。

6. 应注意的质量问题①. 填充墙与主体结构接缝处易产生通缝:不同材质或施工缝处应做防裂处理,如加钢丝网等,处理经验收合格后须方可施工。

五、质量保证措施1.在二次结构工程施工前由技术人员认真审图,明确工程施工中的各项做法和细部节点处理方法,在技术交底中重点突出细部施工工艺,并严格按照其执行,以保证工程质量。

2.对于施工过程中采用的新材料、新工艺等严格控制原材料质量、施工工艺流程,并加强施工过程的中间检查和控制。

3.工程技术人员对于工程中容易出现的质量通病提前进行总结分析,针对本工程提出解决方案,在施工过程中严格控制。

4.在各分项施工前,由工长根据施工方案对操作班组长进行详细的技术交底。

5.制定详细的施工过程质量奖罚细则,认真执行自检、交接检制度,定期检查,奖优罚劣。

6.在各项施工中,工长严格进行过程控制,每道工序必须经过项目技术质量科验收合格后方可进行下步工序。

7.分层、分部位进行施工、交验,保证工程施工工序的有序性,在保证质量的前提下加快进度。

六、安全文明施工措施1.材料的码放:各种材料进场后,经检验合格后,码放在指定的存放区,易燃物区内应设有完善的防火灭火措施。

2.进入施工现场必须戴好安全帽,高空作业必须系好安全带。

3.施工现场不许吸烟,电气焊等明火作业开用火证,并应有灭火措施。

4.施工中,楼梯口、电梯口、预留洞、出入口必须做好有效防护。

5.现场材料必须按照平面布置图进行整齐堆放,严格按照城建集团现场施工管理方法执行。

6.操作工人严格执行“活完料净场地清”,并设专人、定时地进行场地清理、洒水工作,保持现场清洁。

七、成品保护措施1.每道工序必须做好成品保护,严禁本工序施工污染上一道工序。

2.在搬运轻质易碎材料时,轻拿轻放防止材料损坏。

3.施工过程中水电与土建进行有效配合,避免成品破坏。

4.关键部位搭设临时防护,防止操作工人上去破坏成品。

八、环境保护措施1.现场施工道路、办公区每天进行清扫,洒水降尘。