1.工程概况General

本工程有现浇柱1区为34根,2区为13根,6区为4根,柱高为7至11

米等,截面尺寸为450㎜×450㎜及550㎜×550㎜,梁1区43根,2区12根,6

区4根。梁截面尺寸为250㎜×350㎜,300㎜×450㎜,300㎜×700㎜等。

柱四角在±0.000以上需做25mm倒角;柱上的牛腿处于不同的标高且相

距较近,牛腿处钢筋密集交错,不易浇捣。砼表面按清水砼施工。

The number of columns to be poured in situ is 34 pieces for area 1, 13 pieces for area 2 and 4 pieces for area 6. the height of the columns varies from 7 to 11m. the section sizes include 450㎜×450㎜and 550㎜×550㎜. The number of beams to be poured in situ is 43 pieces for area 1, 12 pieces for area 2 and 4 pieces for area 6. the section sizes for the beams include 250㎜×350㎜,300㎜

×450㎜,300㎜×700㎜. Chamfers of 25mm need to be made on four corners of the beams above ±0.000 and the brackets of the columns are set at different elevations with smaller spacing. Rebar at the brackets is dense a nd interlaced, making concrete pouring and vibrating difficult.

2.工艺流程Process Flow

弹柱中心线及边线mark the column center line and sideline 基础柱

钢筋绑扎fix column rebar 钉柱压脚板hammer hold down board 钢筋验收rebar acceptance 基础柱模板支设.验收install column formwork and acceptance 基础柱砼浇concrete pouring 土方