中铁十七局集团沪昆客专作业指导书之接口篇
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
沪昆客专长昆湖南段CKTJ-Ⅶ标段施工作业指导书—接口工程
新建铁路
长沙至昆明铁路客运专线
施工作业指导书
——接口工程
编制人:
审核人:
批准人:
中铁十七局集团沪昆客专长昆湖南段项目经理部
二O一0年十一月
中铁十七局集团沪昆客专长昆湖南段项目经理部
沪昆客专长昆湖南段CKTJ-Ⅶ标段施工作业指导书—接口工程
中铁十七局集团沪昆客专长昆湖南段项目经理部
I 目录
路基接口工程施工作业指导书··························································································· - 1 -
1、目的································································································································· - 1 -
2、编制依据························································································································· - 1 -
3、适用范围························································································································· - 1 -
4、施工工艺及技术要求..................................................................................................... - 1 -4.1声屏障、接触网基础立柱施工.................................................................................... - 1 -4.2电缆槽施工 (3)
4.3.过轨管道....................................................................................................................... - 5 -4.4.路基综合接地. (7)
4.5路基地段贯通地线埋设 (8)
5、质量控制及检验............................................................................................................. - 8 -5.1声屏障、接触网基础工程 (8)
5.2电缆槽工程···················································································································· - 8 -桥梁接口工程施工作业指导书··························································································· - 9 -
1、目的································································································································· - 9 -
2、编制依据························································································································· - 9 -
3、适用范围························································································································· - 9 -
4、施工工艺及技术要求····································································································· - 9 -隧道接口工程施工作业指导书························································································· - 12 -
1、目的······························································································································· - 12 -
2、编制依据······················································································································· - 12 -
3、适用范围······················································································································· - 12 -
4、施工工艺及技术要求··································································································· - 12 -4.1隧道槽道施工.............................................................................................................. - 12 -