低压加热器投运

LPH put into operation

编号No.: 第 1 页共 4 页(1/4)

操作开始时间:年月日时分,终了时间:年日时分Operating starting time: Y M D H M;Finishing time: Y M D H M 操作任务Operation task:

低压加热器投运

( )

LPH put into operation

顺序No. 操作内容

Operation Items

已执行

Executed

操作时间

Operation

time

一操作危险点、安全措施和注意事项(按工作顺序填写与执行)Operation risk point, safety measures and cautions(fill in and execute base on working sequence)

1 投运前低加水侧及旁路注水完毕。

Complete LPH water side and bypass water ejection before startup.

2 投运低加过程中,应注意水侧和汽侧排空气。

During LPH put into operation, pay attention to water side and steam side air exhaust.

3 低加投运应注意由低到高顺序,投运时应注意控制低加温升。

Pay attention to the sequence from lower to higher when put LPH into operation, and control the LPH temperature rising.

4 关闭低加旁路门前就地确认进出水门均已开启.

Locally confirm inlet and outlet water valve is open before close LP bypass valve.

二操作项目(按操作顺序填写与执行)

Operation Item(fill in and execute base on working sequence)

1 得值长令,号机低压加热器( )投运。Receive shift in charge engineer's order, #__ turbine LPH is put into operation.

2 检查# 低压加热器检修工作已结束,具备投运条件。

Confirm #__ LPH maintenance work is finished, and is ready to put into operation.

3 检查# 低压加热器各表计、热工一次门已开启。Confirm #__ LPH each meter, C&I primary valve open.

4 检查各电动门已送电并切远方位置。

Confirm each motor valve energized and switched to remote.

5 检查各气动调节门气源压力正常。

Confirm each pneumatic regulating valve steam supply pressure normal.

操作人(Operator) ______________ 监护人(Supervisor) _____________ 值班负责人(Responsible):__________________ 值长(Shift-chief):_______________

LPH put into operation

编号No.: 第 2 页共 4 页(2/4)

操作开始时间:年月日时分,终了时间:年日时分Operating starting time: Y M D H M;Finishing time: Y M D H M 操作任务Operation task:低压加热器投运

( )

LPH put into operation

顺序No. 操作内容

Operation Items

已执行

Executed

操作时间

Operation

time

6 确认# 低加有关联锁保护正常。

Confirm #__ LPH related interlock protection normal.

7 检查凝结水系统已投运,# 低加走旁路。

Confirm condensate water system is put into operation, #__ LPH go bypass.

8 关闭# 低加入口电动门( )。Close #__ LPH inlet motor valve.

9 关闭# 低加入口管道放水门。

Close #__LPH inlet pipe discharge water valve.

10 关闭# 低加出口电动门( )。Close #__ LPH outlet motor valve.

11 开启# 低加出口管道放空气门。

Open #__ LPH outlet pipe air vent valve.

12 开启# 低加水侧放空气门。

Open #__ LPH water side air vent valve.

13 开启# 低加水侧出水管处放空气门。

Open #__LPH water side outlet pipe air vent valve.

14 关闭# 低加汽侧放水门。

Close #__LPH steam side water discharge valve.

15 关闭# 低加水侧放水门。

Close #__LPH water side water discharge valve.

16 关闭# 低加汽侧放水门。

Close #___LPH steam side water discharge valve.

17 检查汽侧安全门工作正常。

Confirm steam side safety valve normal.

18 打开# 低加汽侧启动排空气门。

Open #__LPH steam side startup air vent valve.

19 开启# 低加正常疏水手动门( )。Open #__ LPH normal drain water manual valve.

操作人(Operator) ______________ 监护人(Supervisor) _____________ 值班负责人(Responsible):__________________ 值长(Shift-chief):_______________