填方工程施工方案
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
目录
一.编制依据································二.工程概况································三.施工布置································
1.任务划分··································
2.材料准备··································
3.机械准备··································
4.人员准备··································
5.施工工期··································四.施工工艺································
1.施工工序··································
2.施工准备··································
3.施工步骤··································五.质量保证措施····························六.安全保证措施····························七.环境保证措施····························八.文明施工管理····························
泥港湖鱼苗繁育车间填方工程施工方案一.编制依据
本方案是根据泥港湖现场规划总平面图及有关施工的技术标准、规范和现场实际情况并结合我们的施工条件而编制。
二.工程概况
鱼池边坡取土填鱼池分别为王中红121#、唐昌彪122#、唐才雄123#、、唐昌彪124#、龙国秀125#鱼池共计27073M2.填塘深度平均约2.5M合计总方量67683M3。如鱼池边坡土方量不够由甲方提供土源。
三.施工布置
1.材料准备
2.机械准备
为保证及时开工以及现场实际情况,开工前所有机械必须到
位。包挎污水泵两台、挖掘机2台、推土机及铲运车3台、
压路机1台、自卸汽车30辆。
3.人员准备
为保证工期及质量,确定了24小时轮班工作制,即保证污水
泵必须有两人分班值守,其他每台机械必须两个司机保证机
械能够24小时正常工作。
4.施工工期
根据本段施工情况,鱼塘填方的施工工期定为2012年5月
25日~2012年7月05日。
四.施工工艺
1.施工工序
排水—测量放线—修坡—运土—回填—平整—压实。
2.施工准备
根据相关技术标准、规范以及现场实际情况,为确保处理工作的顺利进行,采取了以下措施:
2.1核查地行质料,选择合适的施工机械和施工方法。
2.2为满足回填效率,备好充足料源。
2.3测量放线,定出控制边线,并标识。
3.施工步骤
3.1排水
根据现场实地核查,鱼池排水到相邻的鱼池内。
3.2修坡
根据施工图要求鱼池边坡按1:2修坡,鱼池与鱼池间提埂上表宽为6M,鱼池深度为3M。
3.3回填
排水工作结束后,对鱼池进行回填。鱼塘由东向西填料。在填料过程中采取分层压实法,即先在鱼塘地层均匀填50cm后进行压实,然后每填30cm进行一次压实直至设计标高。
五.质量保证措施
1.修坡过程中,必须保证边坡的平整度及水平度。提埂及边坡
严格按照图纸尺寸进行施工。
2.回填前,必须保证鱼池内无积水,方可进行分层回填。
六.安全保证措施
1.建立健全安全生产规章制度好安全生产责任制,贯彻管生产
必须管安全的原则,牢固树立安全第一的观念,把安全生产
责任落实到人。使安全生产有章可循,有法可依,形成制度。
2.经常组织学习有关安全生产法规和安全生产操作规程,抓好
安全教育,增强安全意识。
3.特殊工种人员必须持证上岗,做到管理人员不违章指挥,作
业人员不违章操作,工地所用配电闸箱,均必须安装漏电保
护装置,以确保安全。
4.施工机械、设备等在进行作业时,严格按照机械技术操作规
程进行作业。
七.文明施工管理
1.施工便道平整畅通,雨天不泥泞,晴天不烟尘。
2.进场设备及辅助材料在每天完工后集中存放,并设专人看管。施工现场要设2人小组的专职保洁人员,负责施工现场的保洁工作。
3.