2019.1.15模板方案-印度OPPO制造中心(二期工程)G1
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
目录
一、普通模板体系First, the ordinary template system (2)
1、材料准备Material preparation (2)
2、劳动力准备Labor preparation (3)
3、机具、设备准备Equipment preparation (3)
4、技术准备Technical preparation (4)
5、作业条件Working conditions (6)
二、施工工艺流程及操作要点Construction process and operation points (6)
1、施工工艺流程Construction process (6)
2、模板加工Template processing (7)
3、测量放线Measuring payoff (7)
4、柱模板体系Column template system (8)
6、地下室外墙模板体系Underground outdoor wall formwork
system .................................. 错误!未定义书签。
7、梁板模板Beam plate template (10)
7、楼梯模板Stair template (14)
8、降板模板Down board template (16)
三、高大模板体系Tall template system (17)
四、模板拆除Template removal (20)
五、模板支设的质量要求及允许偏差Quality requirements and 中国建筑潇湘(印度)有限公司
tolerances for template support (22)
一、普通模板体系First, the ordinary template system
1、材料准备Material preparation
模板材料:模板采用2440x1220x12mm的胶合模板。
Template material: The template is a 2440x1220x12mm glued template. 木枋材料:木枋采用截面为45 x 70 x 3000mm的印度标准木方。
Hibiscus material: The raf] is made of Indian standard wood with a section of 45 x 70 x 3000mm
方圆扣:采用规格型号为1m~1.5m的方圆扣。
Square buckle: The round buckle with the specification model is 1m~1.5m.
柱、梁丝杆:采用直径为ϕ14,长度为1.2m的丝杆。
Wall and column screw: A screw with a diameter of φ16 and a length of 1.2m is used.
模板支撑:模板支撑采用碗扣式满堂钢管脚手架搭设,架体钢管采用Φ48钢管。
Formwork support: The formwork support is set up with a wheeled full house steel scaffold, and the frame steel pipe is made of Φ48 steel 中国建筑潇湘(印度)有限公司
pipe.
2、劳动力准备Labor preparation
施工阶段,每施工区由一~二个班组负责施工,各施工段间组织流水施工,高峰期施工总人数约100人,具体人数可根据实际情况调整。
During the construction phase, one to two teams will be responsible for the construction in each construction area, and the construction of the construction will be carried out. The total number of construction during the peak period will be about 100. The specific number can be adjusted according to the actual situation.
3、机具、设备准备Equipment preparation
本工程需配备足额机械设备及机具以满足现场施工需求,模板工程相关施工设备机具计划准备如下:
The project needs to be equipped with sufficient machinery and equipment to meet the on-site construction needs. The construction equipment and equipment related to the formwork plan are prepared as follows:
(1)清理基层的施工工具:水枪、铁锹、扫帚、抹布等。
Construction tools for cleaning the base: water guns, shovel, brooms, rags, etc.
中国建筑潇湘(印度)有限公司
(2)辅助施工器具:铲子、锄头、扫把等。
Auxiliary construction equipment: shovel, hoe, broom, etc. (3)其它相关配套工具小型工具(如锤子、钳子、扳手、吊线锤等视工人需要进行准备),并检查其安全性能等状况。
Other related tools, small tools (such as hammers, pliers, wrenches, wire hammers, etc., need to be prepared), and check the safety performance and other conditions.
4、技术准备Technical preparation
模板工程应编制专项施工方案,支撑体系设计应经过计算。项目技术负责人以会议的形式对管理人员进行主体模板工程施工方案交底,施工员
对劳务班组进行技术、质量、安全交底,安全员对劳务班组进行专项安全中国建筑潇湘(印度)有限公司