SH3503-2017交工技术文件通用表
SHT3503-2017 交工文件表格全册
SH/T 3503—2017目次附录A(规范性附录)交工技术文件通用表 (7)附录B(规范性附录)交工技术文件土建工程用表 (54)附录C(规范性附录)交工技术文件设备安装工程用表 (68)附录D(规范性附录)交工技术文件管道安装工程用表 (140)附录E(规范性附录)交工技术文件电气安装工程用表 (164)附录F(规范性附录)交工技术文件仪表安装工程用表 (176)附录G(规范性附录)交工技术文件压力容器现场组焊安装工程用表 (188)附录H(规范性附录)交工技术文件起重机械安装工程用表 (202)Appendix A(Normative Appendix)Handover Technical Documentation—General (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (388)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel SiteAssembly Welding and Installation (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation · 414IContentsAppendix A(Normative Appendix)Handover Technical Documentation-General (Chinese) (7)Appendix B(Normative Appendix)Handover Technical Documentation—Civil(Chinese) (54)Appendix C(Normative Appendix)Handover Technical Documentation-Equipment Installation(Chinese) (68)Appendix D(Normative Appendix)Handover Technical Documentation-Piping Installation(Chinese) (140)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (Chinese) (164)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (Chinese) (176)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation(Chinese) (188)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (Chinese) (202)Appendix A(Normative Appendix)Handover Technical Documentation—General (English) (217)Appendix B(Normative Appendix)Handover Technical Documentation-Civil(English) (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (English) (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation(English) (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (English) (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (English) (388)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation(English) (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting MachineryInstallation(English) (414)IISH/T 3503—2017 附录A(规范性附录)交工技术文件通用表交工技术文件通用表(续)78SH/T 3503—2017910SH/T 3503—20171112SH/T 3503—20171314SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017SH/T 3503—2017附录B(规范性附录)交工技术文件土建工程用表。
SH T 3503-2017 附录A 交工技术文件通用表
□不符合 □符合
每组垫铁高度
符合设计文件和规范要求 □不符合 □符合
斜垫铁搭接长度
符合规范要求
□不符合 □符合
垫铁间点焊固定
符合规范要求
□不符合 □符合
结论: 经检查,□不符合 □符合设计文件和规范要求,□不可以 □可以隐蔽。
建设/监理单位 专业工程师:
总承包单位 专业工程师:
施工单位
施工班组长: 质量检查员: 专业工程师:
15
SH/T3503-J106A 施工合同编号
工程中间交接证书
工程名称:
交接日期
年月日
工 程 内 容
附:施工尾项清单:份
接 收 意 见
使用单位负责(代表)人:
年 月日
质 量 监 督 意 见
工程质量监督站长/组长:(监督站/组章)
年月日
建设单位
设计单位
监理单位
施 工单位
(项目部章)
(项目部章)
(项目部章)
工程交工验收证书
工程名称:
年 月 日 交工日期
年月日
工程接收意见:
工程质量监督意见:
使用单位负责(代表)人:
年 月日
工程质量监督站长/组长:(监督站/组章)
建设单位
设计单位
(项目部章)
(项目部章)
项目经理:
项目经理:
年月日
监理单位 (项目部章)
施工单位 (项目部章)
项目总监:
项目经理:
日期: 年 月 日 日期: 年 月 日 日期: 年 月 日 日期: 年 月 日
(项目部章)
项目经理:
项目经理:
项目总监:
年月日
总承包单位 施工单位
(项目部章)
(完整版)SH∕T3503-2017交工文件表格(1)
目次附录A(规范性附录)交工技术文件通用表 (7)附录B(规范性附录)交工技术文件土建工程用表 (54)附录C(规范性附录)交工技术文件设备安装工程用表 (68)附录D(规范性附录)交工技术文件管道安装工程用表 (140)附录E(规范性附录)交工技术文件电气安装工程用表 (164)附录F(规范性附录)交工技术文件仪表安装工程用表 (176)附录G(规范性附录)交工技术文件压力容器现场组焊安装工程用表 (188)附录H(规范性附录)交工技术文件起重机械安装工程用表 (202)Appendix A(Normative Appendix)Handover Technical Documentation—General (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation 388 Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (414)IContentsAppendix A(Normative Appendix)Handover Technical Documentation—General (Chinese) (7)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (Chinese) (54)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (Chinese) (68)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (Chinese) .. 140 Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (Chinese) (164)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (Chinese) (176)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (Chinese) (188)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (Chinese) (202)Appendix A(Normative Appendix)Handover Technical Documentation—General (English) (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (English) (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (English) (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (English) (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (English) (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (English) (388)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (English) (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (English) (414)II附录A(规范性附录)交工技术文件通用表7交工技术文件通用表(续)891011121314附录B(规范性附录)交工技术文件土建工程用表。
(完整版)SHT3503-2017交工文件表格(2)
151152153154155156157158159160161162163附录E(规范性附录)交工技术文件电气安装工程用表164165166167168169170171172173174175附录F(规范性附录)交工技术文件仪表安装工程用表176177178179180181182183184185186187附录G(规范性附录)交工技术文件压力容器现场组焊安装工程用表188189190SH/T 3503—J703 球形储罐预制件检查记录赤道带/温带板工程名称:单位工程名称:设备名称设备位号产品编号公称容积m3内直径mm 厚度mm 执行标准检查数量张检查比例%项目单位允许偏差值设计值球壳板编号及实侧值球壳板与样板间隙E mm ≤3坡口钝边A mm ±1.5坡口深度t mm ±1.5坡口角度α(°)±2.5长度方向弦长L1mm ±2.5 L2mm ±2.5宽度方向弦长B3mm ±2 B2mm ±2对角线弦长C1mm ±3 C2mm ±3两条对角线间距h mm 5带支柱赤道板支柱直线度mm支柱轴线位移mm支柱断口周长mm检测部位示意图外观检查:结论:建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日191SH/T 3503—J704球形储罐预制件检查记录极板/极中板工程名称:单位工程名称:设备名称设备位号产品编号公称容积m3内直径mm 厚度mm 执行标准检查数量张检查比例%项目单位允许偏差值设计值球壳板编号及实侧值球壳板与样板间隙E mm ≤3开孔处球壳曲率mm ≤3坡口钝边A mm ±1.5坡口深度t mm ±1.5坡口角度α(°)±2.5直径D mm ±2检测部位示意图管口编号管口位置偏差mm管口高度偏差Lmm法兰水平度mm/m 允许值实测值允许值实测值允许值实测值径向周向径向周向外观检查:结论:建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日192SH/T 3503—J705球形储罐预制件检查记录支柱工程名称:单位工程名称:设备名称设备位号产品编号公称容积m3内直径mm 厚度mm 执行标准检查数量张检查比例%支柱编号支柱全长直线度emm支柱长度Hmm支柱与底板垂直度mm分段支柱断口周长mm备注允许偏差实测值允许偏差实测值允许偏差实测值上段下段径向周向检测部位示意图外观检查:结论:建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日193SH/T 3503—J706 球形储罐组装尺寸检查记录工程名称:单位工程名称:设备名称设备位号产品编号公称容积m3内直径mm 厚度mm 检查样板内半径R样mm 检查样板弦长L mm检查项目允许值mm焊缝编号及实测值mm组对间隙M a b c组对错边n a b c组对棱角E abc检测部位示意图结论:建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日194SH/T 3503—J707球形储罐组装尺寸检查记录(续)工程名称:单位工程名称:设备名称设备位号产品编号公称容积m3内直径mm 厚度mm检测部位示意图检查项目允许值mm实测值mm 赤道截面最大内直径与设计内直径之差赤道截面最小内直径与设计内直径之差两极间内直径与设计内直径之差赤道截面最大内直径与最小内直径之差赤道截面最大内直径与两极间内直径之差赤道截面最小内直径与两极间内直径之差赤道线水平度支柱焊缝与对接焊缝最小距离相邻对接焊缝最小距离项目管口编号管口水平度ΔH,mm 允许值实测值管口位置mm 允许值实测值结论:建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日195SH/T 3503—J708 球形储罐支柱检查记录工程名称:单位工程名称:设备名称设备位号产品编号公称容积m3内直径mm 厚度mm 检查时机支柱编号支柱全长直线度mm支柱垂直度mm允许偏差值实测值允许偏差值径向实测值周向实侧值径向周向a1a2a1-a2a1a2a1-a212345678910结论:检测部位示意图建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日196197SH/T 3503—J710 封头/过渡段组装尺寸检查记录工程名称:单位工程名称:设备名称设备位号产品编号封头/过渡段规格材质执行标准检查项目允许值mm焊缝编号及实测值mm组对间隙M a b c组对错边n a b c组对棱角E检查样板长度L=mm abc封头/过渡段规格整体检查样板检查形状偏差大值椭圆度上端小值下端检测部位示意图结论:建设/监理单位总承包单位施工单位专业工程师:日期:年月日专业工程师:日期:年月日施工班组长:质量检查员:专业工程师:日期:年月日198199200。
SHT 3503-2017 交工文件表格
SH/T 3503—J101A
封 面
卷号:
石油化工建设工程项目交工技术文件
工程名称:
卷 名:
建设单位 监理单位 施工单位
(项目部章) (项目部章) (项目部章)
项目经理: 项目总监: 项目经理:
年 月 日 年 月 日 年 月 日
SH/T 3503—J101B
封 面
卷号:
石油化工建设工程项目交工技术文件
设计单位
计划开工日期
年月日
计划交工日期
年月日
工
程
内
容
开
工
条
件
审
查
意
见
质
量
监
督
意
见
工程质量监督站长/组长:(监督站/组章)年月日
建设单位
监理单位
施工单位
(项目部章)
项目经理:
日期:年月日
(项目部章)
项目总监:
日期:年月日
(项目部章)
项目经理:
日期:年月日
SH/T 3503—J105B
工程施工开工报告
工程名称:四川盛马化工股份有限公司装置防腐项目
SH/T 3503—J107B
19
A.12
交工技术文件移交证书
SH/T 3503—J108A
20
A.13
交工技术文件移交证书
SH/T 3503—J108B
21
A.14
重大质量事故处理报告
SH/T 3503—J109
22
A.15
工程设计变更一览表
SH/T 3503—J110
23
A.16
工程联络单一览表
垫 铁 隐 蔽 记 录
SH T 3503-2017 附录A 交工技术文件通用表
录
序号 A.1 A.2 A.3 A.4 A.5 A.6 A.7 A.8 A.9 A.10 A.11 A.12 A.13 A.14 A.15 A.16 A.17 A18 A19 A.20 A.21 A.22 A.23 A.24 A25 A26 A.27 A.28 A.29 序号 A.30 A.31 A.32
施工合同编 号
交接日期
年月日
工
程 附:施工尾项清单:份
内
容
接
收 使用单位负责(代表)人:年月日
意
见
质
量
监 工程质量监督站长/组长:(监督站/组章)年月日
督
意
见
建设单位 (项目部章) 项目经理:
年月日
设计单位 (项目部章) 项目经理: 年月日
监理单位
总承包单位 施工单位
(项目部章) (项目部章) (项目部章)
SH/T3503-J107B
设计单位 (项目部章) 项目经理: 日期:年月日
监理单位 (项目部章) 项目总监: 日期:年月日
施工单位 (项目部章) 项目经理: 日期:年月日
工程交工验收证书
工程名称:
施工合同编号 实际开工日期
年月日 交工日期
年月日
工程内容:
工程验收意见:
使用单位负责(代表)人:年月日
量
监 工程质量监督站长/组长:(监督站/组章)年月日
督
意
见
建设单位 (项目部章) 项目经理:
日期:年月日
设计单位 (项目部章) 项目经理: 日期:年月日
监理单位 (项目部章) 项目总监: 日期:年月日
施工单位 (项目部章) 项目经理: 日期:年月日
SH/T3503-J106B
《石油化工建设工程项目交工技术文件规定》SHT3503-2017交工资料表格目录清单.doc
《石油化工建设工程项目交工技术文件规定》SH T3503-2017 交工资料表格目录清单.doc2007 版 SH/T3503石油化工建设工程项目交工建设文件汇总表格目录《第一册》一、交工技术文件通用表 ( 共 45 张 )(3503-J101A~J131-2)1、 J101A ——封面2、 J101B ——封面3、 J101C——封面4、 J101D——封面5、 J102 ——交工技术文件总目录6、 J103 ——交工技术文件目录7、 J104 ——交工技术文件说明8、 J105B ——开工报告9、 J106A ——工程中间交接证书10、 J106B ——工程中间交接证书11、 J107A ——工程交工证书12、 J107B ——工程交工证书13、 J108A ——交工技术文件移交证书14、 J108B ——交工技术文件移交证书15、 J109 ——重大质量事故处理报告16、 J110 ——工程变更一览表17、 J111 ——隐蔽工程记录18、 J112 ——工程联络单19、 J113 ——合格焊工登记表20、 J114 ——无损检测人员登记表121、 J115A ——开箱检验记录 ( 一) 22 、 J115B ——开箱检验记录 ( 二 ) 23 、J116——防腐工程质量验收记录 24 、 J117 ——隔热工程质量验收记录25 、J118——接地电阻测量记录26、 J119 ——安全阀调整试验记录27 、 J120 ——安全附件安装检验记录28、 J121 ——射线检测结果确认表29 、 J122-1 ——射线检测报告 ( 一) 30 、J122-2 ——射线检测报告 ( 二 ) 31 、 J123-1 ——焊缝超声检测报告 ( 一) 32 、J123-2 ——焊缝超声检测报告 ( 二) 33 、 J124-1 ——材料超声检测报告 ( 一) 34 、J124-2 ——材料超声检测报告 ( 一) 35 、 J125-1 ——超声测厚报告 ( 一) 36 、J125-2 ——超声测厚报告 ( 一 ) 37 、 J126-1 ——磁粉检测报告 ( 一 ) 38 、 J126-2 ——磁粉检测报告 ( 二) 39 、 J127-1 ——渗透检测报告 ( 一) 40 、 J127-2 ——渗透检测报告 ( 二) 41 、 J128 ——金属材料化学成分分析检验报告 42 、 J129 ——硬度检验报告43、 J130 ——垫铁隐蔽记录44、 J131-1 ——设备 / 材料质量证明文件一览表( 一)45、 J132-2 ——设备 / 材料质量证明文件一览表( 一)2《第二册》二、交工技术文件土建工程用表( 共 11 张)(3503-J201~J210)1、 J201 ——地基验槽 ( 土方 ) 记录2、 J202 ——地基处理记录3、 J203 ——工程定位测量记录4、 J204 ——设备基础复测记录5、 J205 ——快体式设备基础允许偏差项目复测记录6、 J206 ——整体框架式设备基础允许偏差项目复测记录7、 J207-1 ——储罐基础允许偏差项目复测记录( 一)8、 J207-2 ——储罐基础允许偏差项目复测记录( 二)9、 J208 ——球形储罐基础允许偏差项目复测记录10、 J209 ——基础沉降观测记录11、 J210 ——水池盖水试验记录3《第三册》二、交工技术文件设备安装工程用表( 共 40 张)(3503-J301~J336)1、 J301 ——机器安装检验记录2、 J302 ——轴对中记录3、 J303 ——机组轴对中记录4、 J304 ——空冷式换热器风机安装检验记录 5 、 J305 ——机器组装质量确认记录 6 、 J306 ——机器单机试车记录7、 J307 ——机组试车条件确认记录 8 、 J308-1 ——往复式压缩机试车记录 ( 一) 9 、 J308-2 ——往复式压缩机试车记录 ( 二) 10 、 J309-1 ——离心式压缩机试车记录( 一 ) 11 、 J309-2 ——离心式压缩机试车记录 ( 二 ) 12 、 J309-3 ——离心式压缩机试车记录 ( 三 ) 13 、 J310-1 ——气轮机 / 燃气轮机试车记录 ( 一) 14 、J310-2 ——气轮机 / 燃气轮机试车记录 ( 二) 15 、 J311 ——电动机试车记录16、 J312 ——变速器试车记录17、 J313 ——釜类设备安装检验记录18 、 J314 ——立式设备安装检验记录19、 J315 ——卧式设备安装检验记录420、 J316 ——塔式安装检验记录21、 J317 ——设备填充检验记录22、 J318 ——催化反应 / 沉降器附件安装检验记录23 、 J319 ——催化再生器附件安装检验记录24 、 J320 ——立式圆通形储罐组装质量检验记录25 、 J321 ——立式圆筒形储罐试验记录26 、J322 ——湿式气柜组装质量检验记录27 、J323——湿式气柜检验记录28、J324 ——干式气柜组装质量检验记录29 、J325 ——干式气柜试验记录30、J326 ——火炬塔架和管筒安装检验记录31 、J327 ——隔热耐磨衬里质量检验记录 32 、 J328 ——换热设备耐压和严密性试验记录33 、 J329 ——设备耐压 / 严密性试验记录34 、 J330 ——常压设备热处理报告35、 J331 ——管式炉炉体钢结构安装检验记录36 、 J332 ——炉管通球试验记录37、 J333 ——管式炉附件安装质量检验记录 38 、 J334 ——耐火砖砌筑炉衬质量检验记录 39 、 J335 ——耐火浇筑料炉衬质量检验记录 40 、 J336 ——耐火纤维模块炉衬质量检验记录5《第四册》三、交工技术文件管道安装工程用表( 共 16 张)(3503-J401~J413) 1、J401——管道组成件验证性和系统性检验记录 2 、 J402 ——阀门试验确认表3、 J403 ——弹簧支 / 吊架安装检验记录4、 J404 ——滑动 / 固定管托安装检验记录5、J405 ——管道补偿器安装检验记录6、J406-1——管道系统耐压试验条件确认与试验记录(一)7、J406-2——管道系统耐压试验条件确认与试验记录( 二 ) 8 、 J407 ——管道系统泄漏性 / 真空试验条件确认与试验记录9 、 J408 ——管道吹扫 / 清洗检验记录10、 J409 ——给排水压力管道耐压试验条件确认与试验记录11 、 J410 ——给排水无压力管道闭水试验条件确认与试验记录12、J411-1——管道焊接接头热处理报告(一) 13、J411-2——管道焊接接头热处理报告(二)14、J412-1——管道焊接接头射线检测比例确认表(一)15、J412-2 ——管道焊接接头射线检测比例确认表(二) 16、 J413 ——管道静电接地测试记录6《第五册》五、交工技术文件电气安装工程用表( 共 8 张)(3503-J501~J508)1、J501——电气设备试验项目确认表2、J502——交流电动机安装检验与空载运行记录3、J503——变压器安装检验记录4、J504——高 / 压开关柜安装检验记录5、J505——保护 / 控制盘 ( 屏 ) 安装检验记录6、J506——直流系统 / 不间断电源 (UPS)安装检验记录7、J507——电缆铺设与绝缘检测记录8、J508——火灾自动报警系统安装检验记录7《第六册》六、交工技术文件仪表安装工程用表( 共 9 张)(3503-J601~J609)1、J601—— DCS机柜 / 仪表盘 / 操作台安装检验记录2、J602——综合控制系统基本功能检测记录3、J603——报警 / 联锁系统与可编程序控制系统调试记录4、J604—— DCS/SIS送电条件确认表5、J605——仪表设备校验项目确认表6、J606——联校试验条件确认表7、J607——联校调试记录8、J608——仪表管道耐压 / 严密性试验记录9、J608——仪表管道泄漏性 / 真空度试验条件确认与试验记录8。
SH3503-2017交工技术文件通用表
工程施工开工报告
日期: 年 月 日 工程名称:
施工合同编号 计划开工日期
设计单位 年 月 日 计划交工日期
年月日
工
程
内
容 开 工 条 件
审 查 意 见
质 量 监 督 意 见
工程质量监督站站长/组长:
建设单位
监理单位
(监督站/组章) 日期: 总承包单位
年月日 施工单位
(项目部章) 项目经理:
(项目部章) 项目总监:
内 容:
经办人: 审核人:
提出单位(项目章) 年月日
接收单位处理意见:
经办人: 审核人: 会签意见:
会签意见:
(项目章) 会签意见:
年月日
代表:
代表:
代表:
会签单位(项目章)
会签单位(项目章)
会签单位(项目章)
日期:
年 月 日 日期:
年 月 日 日期:
年月日
SH/T 3503—J115
合格焊工登记表
总承包单位 专业工程师:
施工单位 施工班组长: 质量检查员: 专业工程师:
日期:
年月日 日期:
日期: 年月日
年月日
工程名称:
SH/T 3503—J113
垫铁隐蔽记录
单位名称:
设备/结构名称
位号
垫铁布置位置示意图:
检查项目
安装要求
检查结果
垫 设铁 备情 找况 正说明: 垫铁规格 平 垫垫 铁铁 布尺 置寸 位置(长 x 宽 x 高):
设计厚度 实测厚度
mm
mm
中间层 面层 验收结论:
建设/监理单位
总承包单位
施工单位
专业工程师:
专业工程师:
SH3503-2017交工技术文件全资料通用表格
年月
监理单位
施工单位
(项目部章)
(项目部章)
项目总监:
项目经理:
日期: 年 月 日 日期: 年 月 日 日期: 年 月 日 日期: 年 月 日
SH/T 3503-J107B
施工合同编号 实际开工日期 工程容:
工程交工证书
工程名称:
年 月 日 交工日期
年月日
工程接收意见:
工程质量监督意见:
使用单位负责(代表)人:
SH/T 3503-J101A
封面
案卷号:
石油化工建设工程项目交工技术文件
工程名称: 卷 名:
建设单位
(项目部章)
项目经理:
监理单位
(项目部章)
承包单位
(项目部章)
项目总监:
项目经理:
SH/T 3503-J101B
封面
案卷号:
石油化工建设工程项目交工技术文件
工程名称: 卷 名:
建设单位
(项目部章)
程
设计单位 年 月 日 计划交工日期
年月日
容 开 工 条 件
审 查 意 见
质 量 监 督 意 见
工程质量监督站站长/组长:
(监督站/组章) 日期: 年 月 日
建设单位
监理单位
施工单位
(项目部章) 项目经理:
(项目部章) 项目总监:
(项目部章) 项目经理:
日期: 年 月 日
日期: 年 月 日
SH/T 3503-J105B
交工技术文件目录
工程名称: 单元工程名称:
资料名称
页次
编制人: 日 期:
SH/T 3503-J104
审核人: 年 月 日 日 期:
交工技术文件说明
SH3503-2017交工技术文件资料通用表
工程名称:
施工合同编号
交接日期
年月日
工 程 容
附:施工尾项清单 份
验 收 意 见
使用单位负责(代表)人:
年月日
标准
实用文档
质 量 监 督 意 见
工程质量监督站站长/组长:
(监督站/组章) 日期: 年 月 日
建设单位 (项目部章)
项目经理:
设计单位 (项目部章) 项目总监:
监理单位 (项目部章)
项目经理:
施工单位 (项目部章)
项目经理:
年月日 SH/T 3503-J106B
年月日
年月日
年月日
工程中间交接证书
工程名称:
施工合同编号
交接收 意 见
使用单位负责(代表)人:
年月日
标准
实用文档
质 量 监 督 意 见
工程质量监督站站长/组长:
(监督站/组章) 日期: 年 月 日
实用文档
SH/T 3503-J101A
封面
案卷号:
标准
实用文档
石油化工建设工程项目交工技术文件
工程名称: 卷 名:
建设单位
(项目部章)
项目经理: 年月日
监理单位
(项目部章)
承包单位
(项目部章)
项目总监: 年月日
项目经理: 年月日
标准
实用文档
SH/T 3503-J101B
封面
案卷号:
标准
实用文档
标准
实用文档
SH/T 3503-J109
重大质量事故处理
报
告
工程名称:
事 故 经 过 说 明
责任单位代表:
责任单位(公章) 年 月 日
事
《石油化工建设工程项目交工技术文件规定》SHT3503-2017交工资料表格目录清单.doc
《石油化工建设工程项目交工技术文件规定》SHT3503-2017交工资料表格目录清单.doc《石油化工建设工程项目交工技术文件规定》SH T3503-2017 交工资料表格目录清单.doc2007 版 SH/T3503石油化工建设工程项目交工建设文件汇总表格目录《第一册》一、交工技术文件通用表 ( 共 45 张 )(3503-J101A~J131-2)1、 J101A ——封面2、 J101B ——封面3、 J101C——封面4、 J101D——封面5、 J102 ——交工技术文件总目录6、 J103 ——交工技术文件目录7、 J104 ——交工技术文件说明8、 J105B ——开工报告9、 J106A ——工程中间交接证书10、 J106B ——工程中间交接证书11、 J107A ——工程交工证书12、 J107B ——工程交工证书13、 J108A ——交工技术文件移交证书14、 J108B ——交工技术文件移交证书15、 J109 ——重大质量事故处理报告16、 J110 ——工程变更一览表17、 J111 ——隐蔽工程记录18、 J112 ——工程联络单19、 J113 ——合格焊工登记表20、 J114 ——无损检测人员登记表121、 J115A ——开箱检验记录 ( 一) 22 、 J115B ——开箱检验记录 ( 二 ) 23 、J116——防腐工程质量验收记录 24 、 J117 ——隔热工程质量验收记录25 、J118——接地电阻测量记录26、 J119 ——安全阀调整试验记录27 、 J120 ——安全附件安装检验记录28、 J121 ——射线检测结果确认表29 、 J122-1 ——射线检测报告 ( 一) 30 、J122-2 ——射线检测报告 ( 二 ) 31 、 J123-1 ——焊缝超声检测报告 ( 一) 32 、J123-2 ——焊缝超声检测报告 ( 二) 33 、 J124-1 ——材料超声检测报告 ( 一) 34 、J124-2 ——材料超声检测报告 ( 一) 35 、 J125-1 ——超声测厚报告 ( 一) 36 、J125-2 ——超声测厚报告 ( 一 ) 37 、 J126-1 ——磁粉检测报告( 一 ) 38 、 J126-2 ——磁粉检测报告 ( 二) 39 、 J127-1 ——渗透检测报告 ( 一) 40 、 J127-2 ——渗透检测报告 ( 二) 41 、 J128 ——金属材料化学成分分析检验报告 42 、 J129 ——硬度检验报告43、 J130 ——垫铁隐蔽记录44、 J131-1 ——设备 / 材料质量证明文件一览表( 一)45、 J132-2 ——设备 / 材料质量证明文件一览表( 一)2《第二册》二、交工技术文件土建工程用表( 共 11 张)(3503-J201~J210)1、 J201 ——地基验槽 ( 土方 ) 记录2、 J202 ——地基处理记录3、 J203 ——工程定位测量记录4、 J204 ——设备基础复测记录5、 J205 ——快体式设备基础允许偏差项目复测记录6、 J206 ——整体框架式设备基础允许偏差项目复测记录7、 J207-1 ——储罐基础允许偏差项目复测记录( 一)8、 J207-2 ——储罐基础允许偏差项目复测记录( 二)9、 J208 ——球形储罐基础允许偏差项目复测记录10、 J209 ——基础沉降观测记录11、 J210 ——水池盖水试验记录3《第三册》二、交工技术文件设备安装工程用表( 共 40 张)(3503-J301~J336)1、 J301 ——机器安装检验记录2、 J302 ——轴对中记录3、 J303 ——机组轴对中记录4、 J304 ——空冷式换热器风机安装检验记录 5 、 J305 ——机器组装质量确认记录 6 、 J306 ——机器单机试车记录7、 J307 ——机组试车条件确认记录 8 、 J308-1 ——往复式压缩机试车记录 ( 一) 9 、 J308-2 ——往复式压缩机试车记录 ( 二) 10 、J309-1 ——离心式压缩机试车记录( 一 ) 11 、 J309-2 ——离心式压缩机试车记录 ( 二 ) 12 、 J309-3 ——离心式压缩机试车记录 ( 三 ) 13 、 J310-1 ——气轮机 / 燃气轮机试车记录 ( 一) 14 、J310-2 ——气轮机 / 燃气轮机试车记录 ( 二) 15 、 J311 ——电动机试车记录16、 J312 ——变速器试车记录17、 J313 ——釜类设备安装检验记录18 、 J314 ——立式设备安装检验记录19、 J315 ——卧式设备安装检验记录420、 J316 ——塔式安装检验记录21、 J317 ——设备填充检验记录22、 J318 ——催化反应 / 沉降器附件安装检验记录23 、 J319 ——催化再生器附件安装检验记录24 、 J320 ——立式圆通形储罐组装质量检验记录25 、 J321 ——立式圆筒形储罐试验记录26 、J322 ——湿式气柜组装质量检验记录27 、J323——湿式气柜检验记录28、J324 ——干式气柜组装质量检验记录29 、J325 ——干式气柜试验记录30、J326 ——火炬塔架和管筒安装检验记录31 、J327 ——隔热耐磨衬里质量检验记录 32 、 J328 ——换热设备耐压和严密性试验记录33 、J329 ——设备耐压 / 严密性试验记录34 、 J330 ——常压设备热处理报告35、 J331 ——管式炉炉体钢结构安装检验记录36 、 J332 ——炉管通球试验记录37、 J333 ——管式炉附件安装质量检验记录 38 、 J334 ——耐火砖砌筑炉衬质量检验记录 39 、 J335 ——耐火浇筑料炉衬质量检验记录 40 、 J336 ——耐火纤维模块炉衬质量检验记录5《第四册》三、交工技术文件管道安装工程用表( 共 16 张)(3503-J401~J413) 1、J401——管道组成件验证性和系统性检验记录 2 、 J402 ——阀门试验确认表3、 J403 ——弹簧支 / 吊架安装检验记录4、 J404 ——滑动 / 固定管托安装检验记录5、J405 ——管道补偿器安装检验记录6、J406-1——管道系统耐压试验条件确认与试验记录(一)7、J406-2——管道系统耐压试验条件确认与试验记录( 二 ) 8 、J407 ——管道系统泄漏性 / 真空试验条件确认与试验记录9 、 J408 ——管道吹扫 / 清洗检验记录10、 J409 ——给排水压力管道耐压试验条件确认与试验记录11 、J410 ——给排水无压力管道闭水试验条件确认与试验记录12、J411-1——管道焊接接头热处理报告(一) 13、J411-2——管道焊接接头热处理报告(二)14、J412-1——管道焊接接头射线检测比例确认表(一)15、J412-2 ——管道焊接接头射线检测比例确认表(二) 16、J413 ——管道静电接地测试记录6《第五册》五、交工技术文件电气安装工程用表( 共 8 张)(3503-J501~J508)1、J501——电气设备试验项目确认表2、J502——交流电动机安装检验与空载运行记录3、J503——变压器安装检验记录4、J504——高 / 压开关柜安装检验记录5、J505——保护 / 控制盘 ( 屏 ) 安装检验记录6、J506——直流系统 / 不间断电源 (UPS)安装检验记录7、J507——电缆铺设与绝缘检测记录8、J508——火灾自动报警系统安装检验记录7《第六册》六、交工技术文件仪表安装工程用表( 共 9 张)(3503-J601~J609)1、J601—— DCS机柜 / 仪表盘 / 操作台安装检验记录2、J602——综合控制系统基本功能检测记录3、J603——报警 / 联锁系统与可编程序控制系统调试记录4、J604—— DCS/SIS送电条件确认表5、J605——仪表设备校验项目确认表6、J606——联校试验条件确认表7、J607——联校调试记录8、J608——仪表管道耐压 / 严密性试验记录9、J608——仪表管道泄漏性 / 真空度试验条件确认与试验记录8。
(完整版)SH∕T3503-2017交工文件表格(1)
目次附录A(规范性附录)交工技术文件通用表 (7)附录B(规范性附录)交工技术文件土建工程用表 (54)附录C(规范性附录)交工技术文件设备安装工程用表 (68)附录D(规范性附录)交工技术文件管道安装工程用表 (140)附录E(规范性附录)交工技术文件电气安装工程用表 (164)附录F(规范性附录)交工技术文件仪表安装工程用表 (176)附录G(规范性附录)交工技术文件压力容器现场组焊安装工程用表 (188)附录H(规范性附录)交工技术文件起重机械安装工程用表 (202)Appendix A(Normative Appendix)Handover Technical Documentation—General (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation 388 Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (414)IContentsAppendix A(Normative Appendix)Handover Technical Documentation—General (Chinese) (7)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (Chinese) (54)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (Chinese) (68)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (Chinese) .. 140 Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (Chinese) (164)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (Chinese) (176)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (Chinese) (188)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (Chinese) (202)Appendix A(Normative Appendix)Handover Technical Documentation—General (English) (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (English) (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (English) (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (English) (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (English) (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (English) (388)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (English) (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (English) (414)II附录A(规范性附录)交工技术文件通用表7交工技术文件通用表(续)891011121314附录B(规范性附录)交工技术文件土建工程用表。
《石油化工建设工程项目交工技术文件规定》SH T3503-2017交工资料表格目录清单.doc
《石油化工建设工程项目交工技术文件规定》SH T3503-2017交工资料表格目录清单.doc2007版SH/T3503石油化工建设工程项目交工建设文件汇总表格目录《第一册》一、交工技术文件通用表(共45张)(3503-J101A~J131-2)1、 J101A——封面2、 J101B——封面3、 J101C——封面4、 J101D——封面5、 J102——交工技术文件总目录6、 J103——交工技术文件目录7、 J104——交工技术文件说明8、 J105B——开工报告9、 J106A——工程中间交接证书10、 J106B——工程中间交接证书11、 J107A——工程交工证书12、 J107B——工程交工证书13、 J108A——交工技术文件移交证书14、 J108B——交工技术文件移交证书15、 J109——重大质量事故处理报告16、 J110——工程变更一览表17、 J111——隐蔽工程记录18、 J112——工程联络单19、 J113——合格焊工登记表20、 J114——无损检测人员登记表121、 J115A——开箱检验记录(一) 22、 J115B——开箱检验记录(二) 23、J116——防腐工程质量验收记录 24、 J117——隔热工程质量验收记录 25、J118——接地电阻测量记录26、 J119——安全阀调整试验记录 27、 J120——安全附件安装检验记录28、 J121——射线检测结果确认表 29、 J122-1——射线检测报告(一) 30、J122-2——射线检测报告(二) 31、 J123-1——焊缝超声检测报告(一) 32、J123-2——焊缝超声检测报告(二) 33、 J124-1——材料超声检测报告(一) 34、J124-2——材料超声检测报告(一) 35、 J125-1——超声测厚报告(一) 36、J125-2——超声测厚报告(一) 37、 J126-1——磁粉检测报告(一) 38、 J126-2——磁粉检测报告(二) 39、 J127-1——渗透检测报告(一) 40、 J127-2——渗透检测报告(二) 41、 J128——金属材料化学成分分析检验报告 42、 J129——硬度检验报告43、 J130——垫铁隐蔽记录44、 J131-1——设备/材料质量证明文件一览表(一)45、 J132-2——设备/材料质量证明文件一览表(一)2《第二册》二、交工技术文件土建工程用表(共11张)(3503-J201~J210)1、 J201——地基验槽(土方)记录2、 J202——地基处理记录3、 J203——工程定位测量记录4、 J204——设备基础复测记录5、 J205——快体式设备基础允许偏差项目复测记录6、 J206——整体框架式设备基础允许偏差项目复测记录7、 J207-1——储罐基础允许偏差项目复测记录(一)8、 J207-2——储罐基础允许偏差项目复测记录(二)9、 J208——球形储罐基础允许偏差项目复测记录10、 J209——基础沉降观测记录11、 J210——水池盖水试验记录3《第三册》二、交工技术文件设备安装工程用表(共40张)(3503-J301~J336)1、 J301——机器安装检验记录2、 J302——轴对中记录3、 J303——机组轴对中记录4、 J304——空冷式换热器风机安装检验记录5、 J305——机器组装质量确认记录6、 J306——机器单机试车记录7、 J307——机组试车条件确认记录 8、 J308-1——往复式压缩机试车记录(一) 9、 J308-2——往复式压缩机试车记录(二) 10、 J309-1——离心式压缩机试车记录(一) 11、 J309-2——离心式压缩机试车记录(二) 12、 J309-3——离心式压缩机试车记录(三) 13、 J310-1——气轮机/燃气轮机试车记录(一) 14、J310-2——气轮机/燃气轮机试车记录(二) 15、 J311——电动机试车记录16、 J312——变速器试车记录17、 J313——釜类设备安装检验记录 18、 J314——立式设备安装检验记录19、 J315——卧式设备安装检验记录420、 J316——塔式安装检验记录21、 J317——设备填充检验记录22、 J318——催化反应/沉降器附件安装检验记录 23、 J319——催化再生器附件安装检验记录 24、 J320——立式圆通形储罐组装质量检验记录 25、 J321——立式圆筒形储罐试验记录 26、 J322——湿式气柜组装质量检验记录 27、J323——湿式气柜检验记录28、 J324——干式气柜组装质量检验记录 29、 J325——干式气柜试验记录30、 J326——火炬塔架和管筒安装检验记录 31、 J327——隔热耐磨衬里质量检验记录 32、 J328——换热设备耐压和严密性试验记录 33、 J329——设备耐压/严密性试验记录 34、 J330——常压设备热处理报告35、 J331——管式炉炉体钢结构安装检验记录 36、 J332——炉管通球试验记录37、 J333——管式炉附件安装质量检验记录 38、 J334——耐火砖砌筑炉衬质量检验记录 39、 J335——耐火浇筑料炉衬质量检验记录 40、 J336——耐火纤维模块炉衬质量检验记录5《第四册》三、交工技术文件管道安装工程用表(共16张)(3503-J401~J413) 1、J401——管道组成件验证性和系统性检验记录 2、 J402——阀门试验确认表3、 J403——弹簧支/吊架安装检验记录4、 J404——滑动/固定管托安装检验记录5、 J405——管道补偿器安装检验记录6、 J406-1——管道系统耐压试验条件确认与试验记录(一)7、 J406-2——管道系统耐压试验条件确认与试验记录(二)8、 J407——管道系统泄漏性/真空试验条件确认与试验记录9、 J408——管道吹扫/清洗检验记录10、 J409——给排水压力管道耐压试验条件确认与试验记录 11、 J410——给排水无压力管道闭水试验条件确认与试验记录12、 J411-1——管道焊接接头热处理报告(一) 13、 J411-2——管道焊接接头热处理报告(二) 14、 J412-1——管道焊接接头射线检测比例确认表(一) 15、J412-2——管道焊接接头射线检测比例确认表(二) 16、 J413——管道静电接地测试记录6《第五册》五、交工技术文件电气安装工程用表(共8张)(3503-J501~J508)1、J501——电气设备试验项目确认表2、J502——交流电动机安装检验与空载运行记录3、J503——变压器安装检验记录4、J504——高/压开关柜安装检验记录5、J505——保护/控制盘(屏)安装检验记录6、J506——直流系统/不间断电源(UPS)安装检验记录7、J507——电缆铺设与绝缘检测记录8、J508——火灾自动报警系统安装检验记录7《第六册》六、交工技术文件仪表安装工程用表(共9张)(3503-J601~J609)1、J601——DCS机柜/仪表盘/操作台安装检验记录2、J602——综合控制系统基本功能检测记录3、J603——报警/联锁系统与可编程序控制系统调试记录4、J604——DCS/SIS送电条件确认表5、J605——仪表设备校验项目确认表6、J606——联校试验条件确认表7、J607——联校调试记录8、J608——仪表管道耐压/严密性试验记录9、J608——仪表管道泄漏性/真空度试验条件确认与试验记录8。
SH3503-2017交工技术文件通用表
交工技术文件目录
工程名称: 单元工程名称:
资料名称
页次
编制人: 日 期:
审核人: 年 月 日 日 期:
年月日
SH/T 3503-J104
交工技术文件说明
工程名称:
编制人: 日 期:
审核人: 年 月 日 日 期:
年月日
SH/T 3503-J105A
施工合同编号 计划开工日期
工 程 内 容
工程施工开工报告
事由
工程名称: 单位工程名称:
实施情况说明
建设单位 专业工程师:
监理单位 专业工程师:
施工单位 编制人: 审核人:
日期:
年 月 日 日期:
年 月 日 日期:
年月日
SH/T 3503-J112 隐蔽项目
隐蔽工程记录
工程名称: 单位工程名称:
施工图号
隐 蔽 内 容 及 简 图
检 查 结 果
建设/监理单位
工程变更一览表
工程名称: 单位工程名称:
变更原因
实施图号及变更要点
实施情况说明
注:变更原因填写设计原因或非设计原因
建设单位 专业工程师:
监理单位 专业工程师:
施工单位 编制人: 审核人:
日期:
年 月 日 日期:
年 月 日 日期:
年月日
SH/T 3503-J110
工程联络单一览表
专业 序号
联络单编号
监理单位
(项目部章) 审核人:
承包单位
(项目部章) 经办人:
日期:
年 月 日 日期:
年 月 日 日期:
年月日
SH/T 3503-J108B
交工技术文件移交证书
工程名称: 合同编号:
SH3503-2017交工技术文件土建工程用表
单位工程名称:
储罐位号
复测日期
年 月 日
储罐容积
3m
储罐直径
m
基础中心
标
偏差,mm
允许值
土20
基础中心
位置
偏差,mm
允许值
20
直径允许
偏差,mm
允许值
+30 0
实测值
实测值
实测值
储 罐 基 础 同 心 圆 及 测 点 编 号 布 置 图
复 测 结
果 确 认
接收单位
建设/监理单位
总承包单位
施工单位
设备基础复测记录
工程名称:
单位工程名称:
基础名称
设备位号
施工图号
引点标桩号
引点标高
m
标高土0.00
ml
观测仪器
复测日期
年 月 日
仪器检定 日期
年 月 日
复测项
目名称
测点
编亏
设计可
m X
§标
Y
坐标
m AX
:差
m
△Y
测点
编亏
设计标高
m
实测标高
m
标1口」/
mm
+
-
测点编号图示:
复测结果确认:
建设/监理单位
施工日期年 月 日至年 月 日
处理依据:施工图号,设计变更 /洽商(编号)及国家现行标准、规范等。
处理方式:
处理部位及状况(或用简图表示):
处理结果:
附:□施工记录、口桩检测报告。
检验结论:
口通过,可进入下步工序□未通过,整改后复查□附检查情况影像
建设/监理单位
设计/总承包单位
SH3503-2017交工技术文件通用表.docx
工程中间交接证书
工程名称:
交接日期
年月日
工 程 内 容
附:施工尾项清单 份
验 收 意 见
使用单位负责(代表)人:
年 月日
质 量 监 督 意 见
工程质量监督站站长/组长:
(监督站/组章) 日期: 年 月 日
建设单位 (项目部章)
项目经理:
设计 单 位 (项目部章) 项目总监:
监理单位 (项目部章) 项目总监:
总承包单位 (项目部章) 项目经理:
施工单位 (项目部章) 项目经理:
年月日
精选
年月日
年月 日
年 月 日年 月 日
SH/T 3503-J107A
施工合同编号 实际开工日期 工程内容:
工程交工证书
工程名称:
年 月 日 交工日期
年月日
工程接收意见:
工程质量监督意见:
使用单位负责(代表)人:
年 月日
工程质量监督站站长/组长:
工程变更一览表
工程名称: 单位工程名称:
变更原因
实施图号及变更要点
实施情况说明
注:变更原因填写设计原因或非设计原因
建设单位 专业工程师:
监理单位 专业工程师:
日期:
年月日
日期:
年月日
施工单位 编制人: 审核人:
日期:
年月日
精选
SH/T 3503-J110
工程联络单一览表
专业 序号
联络单编号
事由
工程名称: 单位工程名称:
责任单位代表:
责任单位(公章) 年 月 日
事
故
处
理
方
案
与
处
理
结
果
SH∕T3503-2017交工文件全全资料表格(1)
Contents
Appendix A (Normative Appendix) Handover Technical Documentation—General (Chinese) 7
Appendix B (Normative Appendix) Handover Technical Documentation—Civil (Chinese) 54
计划交工日期
年 月曰
工
程
容
开 工 条 件
审 査 意 见
质量监督意见
工程质量监督站长/组长:(监督站/组章) 年 月曰
建设单位
监理单位
施工单位
(项目部章)
项目经理:
日期: 年 月曰
(项目部章)
项目总监:
日期: 年 月曰
(项目部章)
项目经理:
日期: 年 月曰
SH/T 3503—J105B
工程施工开工报告
附录H(规性附录) 交工技术文件起重机械安装工程用表202
Appendix A(Normative Appendix) Handover Technical Documentation—General 217
Appendix B (Normative Appendix) Handover Technical Documentation—Civil 264
43
A.36
超声测厚报告
SH/T 3503—J128-1
44
A.37
超声测厚报告(续)
SH/T 3503—J128-2
45
A.38
金属材料化学成分检验报告
SH/T 3503—J129
46
A.39
硬度检测报告
SHT3503-2017交工文件表格全册
SHT3503-2017交工文件表格全册SH/T 3503—2017目次附录A(规范性附录)交工技术文件通用表 (7)附录B(规范性附录)交工技术文件土建工程用表 (54)附录C(规范性附录)交工技术文件设备安装工程用表 (68)附录D(规范性附录)交工技术文件管道安装工程用表 (140)附录E(规范性附录)交工技术文件电气安装工程用表 (164)附录F(规范性附录)交工技术文件仪表安装工程用表 (176)附录G(规范性附录)交工技术文件压力容器现场组焊安装工程用表 (188)附录H(规范性附录)交工技术文件起重机械安装工程用表 (202) Appendix A(Normative Appendix)Handover Technical Documentation—General (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (278)Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (376)Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation 388 Appendix G (Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (400) Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (414) IContentsAppendix A(Normative Appendix)Handover Technical Documentation—General (Chinese) (7)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (Chinese) (54)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (Chinese) (68) Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (Chinese) ·· 140Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (Chinese) (164) Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (Chinese) (176) Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (Chinese) (188)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (Chinese) (202) Appendix A(Normative Appendix)Handover Technical Documentation—General (English) (217)Appendix B(Normative Appendix)Handover Technical Documentation—Civil (English) (264)Appendix C(Normative Appendix)Handover Technical Documentation—Equipment Installation (English) (278) Appendix D(Normative Appendix)Handover Technical Documentation—Piping Installation (English) (351)Appendix E(Normative Appendix)Handover Technical Documentation—Electrical Installation (English) (376) Appendix F(Normative Appendix)Handover Technical Documentation—Instrumentation Installation (English) (388)Appendix G(Normative Appendix)Handover Technical Documentation—Pressure Vessel Site Assembly Welding and Installation (English) (400)Appendix H(Normative Appendix)Handover Technical Documentation—Lifting Machinery Installation (English) (414) IISH/T 3503—2017附录A(规范性附录)交工技术文件通用表7交工技术文件通用表(续)8SH/T 3503—2017910SH/T 3503—20171112SH/T 3503—20171314SH/T 3503—20171516SH/T 3503—20171718SH/T 3503—20171920SH/T 3503—20172122SH/T 3503—201723。
《石油化工建设工程项目交工技术文件规定》SHT3503-2017交工资料表格目录清单.doc
《石油化工建设工程项目交工技术文件规定》SH T3503-2017 交工资料表格目录清单.doc2007 版 SH/T3503石油化工建设工程项目交工建设文件汇总表格目录《第一册》一、交工技术文件通用表 ( 共 45 张 )(3503-J101A~J131-2)1、 J101A ——封面2、 J101B ——封面3、 J101C——封面4、 J101D——封面5、 J102 ——交工技术文件总目录6、 J103 ——交工技术文件目录7、 J104 ——交工技术文件说明8、 J105B ——开工报告9、 J106A ——工程中间交接证书10、 J106B ——工程中间交接证书11、 J107A ——工程交工证书12、 J107B ——工程交工证书13、 J108A ——交工技术文件移交证书14、 J108B ——交工技术文件移交证书15、 J109 ——重大质量事故处理报告16、 J110 ——工程变更一览表17、 J111 ——隐蔽工程记录18、 J112 ——工程联络单19、 J113 ——合格焊工登记表20、 J114 ——无损检测人员登记表121、 J115A ——开箱检验记录 ( 一) 22 、 J115B ——开箱检验记录 ( 二 ) 23 、J116——防腐工程质量验收记录 24 、 J117 ——隔热工程质量验收记录25 、J118——接地电阻测量记录26、 J119 ——安全阀调整试验记录27 、 J120 ——安全附件安装检验记录28、 J121 ——射线检测结果确认表29 、 J122-1 ——射线检测报告 ( 一) 30 、J122-2 ——射线检测报告 ( 二 ) 31 、 J123-1 ——焊缝超声检测报告 ( 一) 32 、J123-2 ——焊缝超声检测报告 ( 二) 33 、 J124-1 ——材料超声检测报告 ( 一) 34 、J124-2 ——材料超声检测报告 ( 一) 35 、 J125-1 ——超声测厚报告 ( 一) 36 、J125-2 ——超声测厚报告 ( 一 ) 37 、 J126-1 ——磁粉检测报告 ( 一 ) 38 、 J126-2 ——磁粉检测报告 ( 二) 39 、 J127-1 ——渗透检测报告 ( 一) 40 、 J127-2 ——渗透检测报告 ( 二) 41 、 J128 ——金属材料化学成分分析检验报告 42 、 J129 ——硬度检验报告43、 J130 ——垫铁隐蔽记录44、 J131-1 ——设备 / 材料质量证明文件一览表( 一)45、 J132-2 ——设备 / 材料质量证明文件一览表( 一)2《第二册》二、交工技术文件土建工程用表( 共 11 张)(3503-J201~J210)1、 J201 ——地基验槽 ( 土方 ) 记录2、 J202 ——地基处理记录3、 J203 ——工程定位测量记录4、 J204 ——设备基础复测记录5、 J205 ——快体式设备基础允许偏差项目复测记录6、 J206 ——整体框架式设备基础允许偏差项目复测记录7、 J207-1 ——储罐基础允许偏差项目复测记录( 一)8、 J207-2 ——储罐基础允许偏差项目复测记录( 二)9、 J208 ——球形储罐基础允许偏差项目复测记录10、 J209 ——基础沉降观测记录11、 J210 ——水池盖水试验记录3《第三册》二、交工技术文件设备安装工程用表( 共 40 张)(3503-J301~J336)1、 J301 ——机器安装检验记录2、 J302 ——轴对中记录3、 J303 ——机组轴对中记录4、 J304 ——空冷式换热器风机安装检验记录 5 、 J305 ——机器组装质量确认记录 6 、 J306 ——机器单机试车记录7、 J307 ——机组试车条件确认记录 8 、 J308-1 ——往复式压缩机试车记录 ( 一) 9 、 J308-2 ——往复式压缩机试车记录 ( 二) 10 、 J309-1 ——离心式压缩机试车记录( 一 ) 11 、 J309-2 ——离心式压缩机试车记录 ( 二 ) 12 、 J309-3 ——离心式压缩机试车记录 ( 三 ) 13 、 J310-1 ——气轮机 / 燃气轮机试车记录 ( 一) 14 、J310-2 ——气轮机 / 燃气轮机试车记录 ( 二) 15 、 J311 ——电动机试车记录16、 J312 ——变速器试车记录17、 J313 ——釜类设备安装检验记录18 、 J314 ——立式设备安装检验记录19、 J315 ——卧式设备安装检验记录420、 J316 ——塔式安装检验记录21、 J317 ——设备填充检验记录22、 J318 ——催化反应 / 沉降器附件安装检验记录23 、 J319 ——催化再生器附件安装检验记录24 、 J320 ——立式圆通形储罐组装质量检验记录25 、 J321 ——立式圆筒形储罐试验记录26 、J322 ——湿式气柜组装质量检验记录27 、J323——湿式气柜检验记录28、J324 ——干式气柜组装质量检验记录29 、J325 ——干式气柜试验记录30、J326 ——火炬塔架和管筒安装检验记录31 、J327 ——隔热耐磨衬里质量检验记录 32 、 J328 ——换热设备耐压和严密性试验记录33 、 J329 ——设备耐压 / 严密性试验记录34 、 J330 ——常压设备热处理报告35、 J331 ——管式炉炉体钢结构安装检验记录36 、 J332 ——炉管通球试验记录37、 J333 ——管式炉附件安装质量检验记录 38 、 J334 ——耐火砖砌筑炉衬质量检验记录 39 、 J335 ——耐火浇筑料炉衬质量检验记录 40 、 J336 ——耐火纤维模块炉衬质量检验记录5《第四册》三、交工技术文件管道安装工程用表( 共 16 张)(3503-J401~J413) 1、J401——管道组成件验证性和系统性检验记录 2 、 J402 ——阀门试验确认表3、 J403 ——弹簧支 / 吊架安装检验记录4、 J404 ——滑动 / 固定管托安装检验记录5、J405 ——管道补偿器安装检验记录6、J406-1——管道系统耐压试验条件确认与试验记录(一)7、J406-2——管道系统耐压试验条件确认与试验记录( 二 ) 8 、 J407 ——管道系统泄漏性 / 真空试验条件确认与试验记录9 、 J408 ——管道吹扫 / 清洗检验记录10、 J409 ——给排水压力管道耐压试验条件确认与试验记录11 、 J410 ——给排水无压力管道闭水试验条件确认与试验记录12、J411-1——管道焊接接头热处理报告(一) 13、J411-2——管道焊接接头热处理报告(二)14、J412-1——管道焊接接头射线检测比例确认表(一)15、J412-2 ——管道焊接接头射线检测比例确认表(二) 16、 J413 ——管道静电接地测试记录6《第五册》五、交工技术文件电气安装工程用表( 共 8 张)(3503-J501~J508)1、J501——电气设备试验项目确认表2、J502——交流电动机安装检验与空载运行记录3、J503——变压器安装检验记录4、J504——高 / 压开关柜安装检验记录5、J505——保护 / 控制盘 ( 屏 ) 安装检验记录6、J506——直流系统 / 不间断电源 (UPS)安装检验记录7、J507——电缆铺设与绝缘检测记录8、J508——火灾自动报警系统安装检验记录7《第六册》六、交工技术文件仪表安装工程用表( 共 9 张)(3503-J601~J609)1、J601—— DCS机柜 / 仪表盘 / 操作台安装检验记录2、J602——综合控制系统基本功能检测记录3、J603——报警 / 联锁系统与可编程序控制系统调试记录4、J604—— DCS/SIS送电条件确认表5、J605——仪表设备校验项目确认表6、J606——联校试验条件确认表7、J607——联校调试记录8、J608——仪表管道耐压 / 严密性试验记录9、J608——仪表管道泄漏性 / 真空度试验条件确认与试验记录8。
《石油化工建设工程项目交工技术文
《石油化工建设工程项目交工技术文件规定》SH T3503-2017交工资料表格目录清单.doc 2007版SH/T3503石油 化工建设工程项目交工建设文件汇总表格目录《第一册》一、交工技术文件通用表(共45张)(3503-J101A~J131-2) 1、 J101A— —封面 2、 J101B ——封面 3、 J101C ——封面 4、 J101D ——封面 5、 J102——交工技术文件总目录 6、 J103——交工技术文件目录 7、 J104——交工技术文件说明 8、J105B — —开工报告9、J106A — —工程中间交接证书 10、 J106B ——工程中间交接证书 11、 J107A ——工程交工证书 12、 J107B ——工程交工证书 13、 J108A ——交工技术文件移交证书 14、 J108B ——交工技术文件移交证书 15、 J109——重大质量事故处理报告16、J110工程变更一览表17、J111——隐蔽工程记录18、J112——工程联络单19、J113——合格焊工登记表20、J114——无损检测人员登记表121、J115A开箱检验记录(一)22、J115B开箱检验记录(二)23、J116防腐工程质量验收记录24、J117隔热工程质量验收记录25、J118——接地电阻测量记录26、J119安全阀调整试验记录27、J120——安全附件安装检验记录28、J121――射线检测结果确认表29、J122-1――射线检测报告(一)30、J122-2- —射线检测报告(二)31、J123-1――焊缝超声检测报告(一)32、J123-2焊缝超声检测报告(二)33、J124-1――材料超声检测报告(一)34、J124-2材料超声检测报告(一)35、J125-1――超声测厚报告(一)36、J125-2超声测厚报告(一)37、J126-1磁粉检测报告(一)38、J126-2磁粉检测报告(二)39、J127-1——渗透检测报告(一)40、J127-2渗透检测报告(二) 41、J128金属材料化学成分分析检验报告42、J129硬度检验报告43、J130 ---- 垫铁隐蔽记录44、J 1 3 1 - 1——设备/材料质量证明文件一览表(一)45、J132-2设备/材料质量证明文件一览表(一)2《第二册》二、交工技术文件土建工程用表(共11张)(3503-J201~J210)1、J201——地基验槽(土方)记录2、 J202—— 地基处理记录3、 J203—— 工程定位测量记录4、 J204—— 设备基础复测记录5、 J205—— 快体式设备基础允许偏差项目复测记录6、 J206—— 整体框架式设备基础允许偏差项目复测记录7、 J207-1— —储罐基础允许偏差项目复测记录 (一)8、 J207-2— —储罐基础允许偏差项目复测记录 (二)9、 J208—— 球形储罐基础允许偏差项目复测记录 10、 J209— —基础沉降观测记录 11、 J210——水池 xx 试验记录 3 《第三册》二、交工技术文件设备安装工程用表 (共 40 张 )(3503-J301~J336)1、J301 机器安装检验记录2、J302— —轴对 xx 记录3、J303— —机组轴对 xx 记录 4、 J304— —空冷式换热器风机安装检验记录 5、 J305-机器组装质量确认 记录 6、 J306— —机器单机试车记录7、 J307— —机组试车条件确认记录 8、 J308-1— —往复式压缩机试车记录 (一)9、J308-往复式压缩机试车记录(二)10、J309-1——离心式压缩机试车 记录(一)11、J309-2离心式压缩机试车记录(二)12、J309-3离心式压缩机 试车记录(三)13、J310-1――气轮机/燃气轮机试车记录(一)14、J310-2—— 轮 机/燃气轮机试车记录(二)15、J311――电动机试车记录16、J31 变速器试车记录17、J313 ---- 釜类设备安装检验记录18、J314 ------ 立式设备安装检验记录19、J315 ---- 卧式设备安装检验记录420、J316 塔式安装检验记录21、J317设备填充检验记录22、J318催化反应/沉降器附件安装检验记录23、J319催化再生器附件安装检验记录24、J320立式圆通形储罐组装质量检验记录25、J321- —立式圆筒形储罐试验记录26、J322湿式气柜组装质量检验记录27、J323湿式气柜检验记录28、J324干式气柜组装质量检验记录29、J325式气柜试验记录30、J326火炬塔架和管筒安装检验记录31、J327隔热耐磨衬里质量检验记录32、J328换热设备耐压和严密性试验记录33、J329设备耐压/严密性试验记录34、J330常压设备热处理报告35、J331管式炉炉体钢结构安装检验记录36、J332炉管通球试验记录37、J333 管式炉附件安装质量检验记录38、J334 耐火砖砌筑炉衬质量检验记录39、J335 耐火浇筑料炉衬质量检验记录40、J336 耐火纤维模块炉衬质量检验记录5《第四册》三、交工技术文件管道安装工程用表(共16张)(3503-J401~J413) 1J401―- 管道组成件验证性和系统性检验记录2、J402阀门试验确认表3、J403 弹簧支/吊架安装检验记录4、J404滑动/固定管托安装检验记录5、J405 ---- 管道补偿器安装检验记录6、J406-1——管道系统耐压试验条件确认与试验记录(一)7、J406-2管道系统耐压试验条件确认与试验记录(二)8 J407管道系统泄漏性/真空试验条件确认与试验记录9、J408 --------------- 管道吹扫/清洗检验记录10、J409给排水压力管道耐压试验条件确认与试验记录11、J410给排水无压力管道闭水试验条件确认与试验记录12、J411-1管道焊接接头热处理报告(一)13、J411-2管道焊接接头热处理报告(二)14、J412-1――管道焊接接头射线检测比例确认表(一)15、J412-2- —管道焊接接头射线检测比例确认表(二)16、J413管道静电接地测试记录6《第五册》五、交工技术文件电气安装工程用表(共8张)(3503-J501~J508)1 J501——电气设备试验项目确认表2、J502——交流电动机安装检验与空载运行记录3、J503——变压器安装检验记录4、J504——高/压开关柜安装检验记录5、J505——保护/控制盘(屏)安装检验记录6、J506——直流系统/不间断电源(UPS安装检验记录7、J507——电缆铺设与绝缘检测记录8、J508——火灾自动报警系统安装检验记录7第六册》六、交工技术文件仪表安装工程用表(共9张)(3503-J601~J609)1 J601 DCS机柜/仪表盘/操作台安装检验记录2、J602——综合控制系统基本功能检测记录3、J603——报警/联锁系统与可编程序控制系统调试记录4、J604—DCS/SIS送电条件确认表5、J605——仪表设备校验项目确认表6、J606——联校试验条件确认表7、J607——联校调试记录8、J608——仪表管道耐压/严密性试验记录9、J608——仪表管道泄漏性/真空度试验条件确认与试验记录8。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
石油化工建设工程项目交工技术文件
工程名称:
卷名:
建设单位监理单位承包单位
(项目部章)(项目部章)(项目部章)
项目经理:项目总监:项目经理:年月日年月日年月日
I —f
案卷号:
SH/T 3503-J101B
石油化工建设工程项目交工技术文件
卷 名:
建设单位
(项目部章)
监理单位
(项目部章)
总承包单位
(项目部章)
承包单位
(项目部章)
项目经理: 项目总监:
项目经理: 项目经理: 年 月
日
年
月
日
年 月
工程名称: 日
SH/T 3503-J108A 交工技术文件移交证书合同编号:
按《石油化工建设工程项目交工技术文件规定》(SH/T 3503- 2017)向
___________________________ 办理工程建设交工技术文件移交手续,共计文字资料___________________________ 卷,竣工图____ 卷,电子文件 _________ 盘。
附:交工技术文件移交清单。
工程名称:SH/T 3503-J122接地电阻测量记录单位工程名称:。