作业规程内容
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
目录
目录```````````````````````````````````````````````````````````````````````````````1
一、本规程编制依据``````````````````````````````````````````````````````````````````2
二、概况``````````````````````````````````````````````````````````````````3
三、地质``````````````````````````````````````````````````````````````````4
四、工作面特征和储量````````````````````````````````````````````````````````````6
五、采煤方法及工艺```````````````````````````````````````````````````````````````````7
六、循环作业组织形式及设备配备表````````````````````12
七、主要技术经济指标```````````````````````````````````````````````````````````14
八、通风 ```````````````````````````````````````````````````````````````````15
九、运输 ````````````````````````````````````````````````````````````````````17
十、供电 ````````````````````````````````````````````````````````````````````18 十一、通讯 ````````````````````````````````````````````````````````````````20 十二、防尘 ````````````````````````````````````````````````````````````````20 十三、安全措施和组织措施`````````````````````````````````````````````````21
一、本规程编制依据
本规程根据《矿井开采方案》、《矿井地质说明书》、《小煤矿安全规程》以及本矿其它规程及措施所编制。
二、概况
三、地质
四、工作面特征和储量
五、采煤方法及工艺
1、采煤方法选择
(1)选择依据:
根据煤层地质赋存条件,我矿的资金、技术和井下实际情况,采用走向长壁式采煤方法。用单体夜压支柱支护,工作面用刮板运输机运输,进风巷用矿车运输。
(2)采高的确定:
因煤层最大厚度2.8米,伪顶厚0.5~1.5米,目前我矿采用最大高度为3.15米的单体支护,一次采全高。
2、回采工艺
①、落煤:
a、落煤方法:人工钻眼,放炮落煤。
b、打眼工具:127V电煤钻
c、炮眼布置示意图:
d、装药结构图:
e、爆破说明书:
f、一次起爆长度的确定:
工作面长为115米,每日进一档,即一个班必须起爆38米。但每一次起爆长度不得超于10米。炮眼深1.2m,一次爆破进度为1.2~1.3m。
②、装运煤
a、装煤:人工装煤;
b、运输机型号选择及移置方法:
工作面用SG-420/30N型刮板输送机一台,运输巷用SG-420/30N输送机一台。SG-420/30N型刮板输送机用单体支柱移动
c、运输流程:
19101工作面 19101运输巷下山运输巷井底
车场
主提升巷 地面 ③、采场支护:
a 、工作面支架及顶板管理方法
对采场顶板管理最大为四排支柱管理法,最小为三排支柱管理法,即见四回一支柱管理方法。最大控顶距为5米、最小控顶距为3.6米。 支架采用单体液压支柱、绞接顶梁接顶的支护方式。
b 、初次放顶
对采空区管理:用密集支柱截顶,当截顶无效时,强制放顶,初次放顶步距8~
12米时进行。
强制放顶由准备班人员在密集支柱边打一排2米深的孔装药放炮,给顶板形成一个垮落面。
强制放顶前,根据矿井实际回采经验总结,必须将支护方式缩小为最小控顶距,确定为“两、三排”管理,待顶板稳定后再恢复“三、四排”管理
3、采面工程平面布置示意图:
六、循环作业组织形式及
设备配备表
1、循环作业组织形式:二采一准;即二班采煤,一班为采煤作准备。
2、循环作业图表
3、劳动组织
4、主要设备工具配备表
七、主要技术经济指标
八、通风
1、风量计算
(1)按沼气涌出量计算:
Q采=100¬Q绝¬K采通
100¬1.5¬2.0=300m3/min;(2)按工作面温度计算:
Q采=60¬V采¬S采
60¬0.8¬6.0=288m3/min (3)按一次起爆最多炸药量计算:
Q采=25A
25¬12.0=300m3/min
(4)按工作面同时工作最多人数计算:
Q采=4N
4¬25=100m3/min
(5)按风速进行验算:
a、工作面最低风量:
Q采小≥0.25¬60S采
300m3/min≥15¬10.92=163.8m3/min
b、工作面最高风量:
Q采大≤4¬60S采
626.25m3/min≤240¬13.52=844.8m3/min