广联达培训楼工程量计算

1、建筑面积:m2

首层:11.6×6.5=75.4m2

二层:11.6×6.5=75.4m2

阳台:4.56×1.2×1÷2=2.736 m2

建筑总面积:75.4+75.4+2.736=153.536 m2

2、平整场地面积:m2

11.6×6.5=75.4 m2

3、土方量:m3

H=(-0.45)-(-1.6)=1.15m

垫层长:11.6+0.35×2=12.3m

垫层宽:6.5+0.35×2=7.2 m

V=(a+2c)(b+2c)h

=(12.3+0.3×2)×(7.2+0.3×2)×1.15=115.7m3

4、C10砼垫层:m3

V=垫层长×垫层宽×垫层厚=(11.6+0.35×2)×(6.5+0.35×2)0.1=8.856 m3垫层模板m2

S=(11.6+0.35×2+6.5+0.35×2)×2×0.1=3.9 m2

5、C25满堂基础(有梁式):m3

V□= (11.6+0.25×2)(6.5+×2)0.3=25.41

=1/2×0.15×0.1×[11.6+(0.1+0.075)×2+6.5+(0.1+0.075)×2] ×2=0.282 V

m3

V=25.41-0.282=25.128 m3

基础梁砼体积:m3

①④2JL2(1):(6-0.25×2)×0.5×0.12×2=1.1 m3

②③2JL3(2):[(3.3-0.25-0.2)+(2.1-0.25-0.2)] ×0.4×0.2×2=0.816 m3

AC2JL1(3):[(3.3-0.25-0.2)×2(4.5-0.2-0.2)] ×0.5×0.2×2=1.96 m3 BJL4(4.5-0.2-0.2)×0.4×0.2=0.328 m3

V梁=1.1+0.816+1.936+0.328=4.204 m3

V总25.128+4.204=29.332 m3

基础模板:m2

V=(11.6+0.25×2+6.5+0.25×2)×2×0.2=7.64 m2

梁的模板:m2

①④2JL2(1):(6-0.25×2)×0.2×2×2=4.4m2

②③2JL3(2):[(3.3-0.25-0.2)+(2.1-0.25-0.2)] ×0.2×2×2=4.08 m2

AC2JL1(3):[(3.3-0.25-0.2)×2(4.5-0.2-0.2)] ×0.2×2×2=7.84 m2

BJL4(4.5-0.2-0.2)×0.2×2=1.64 m2

梁的模板:S=4.4+4.08+7.84+1.64=17.96 m2

C30砼框架柱(-1.2~±0.00):m3

4Z1=0.5×0.5×1.2×4=1.2 m3

4Z2=0.5×0.4×1.2×4=0.96 m3

2Z3=0.4×0.4×1.2×2=0.384 m3

C30砼框架柱的总体积=1.2+0.96+0.384=2.544 m3

C25砼框架柱(±0.00~7.17):m3

4Z1=0.5×0.5×7.17×4=7.17 m3

4Z2=0.5×0.4×7.17×4=5.736 m3

2Z3=0.4×0.4×7.17×2=2.2944 m3

C25砼框架柱的总体积=7.17+5.736+2.2944=15.2004 m3

框架柱的模板(-1.2~7.17):m2

4Z1=0.5×4×(1.2+7.17)×4=66.96 m2

4Z2=(0.5+0.4)×2×(1.2+7.17)×4=60.264 m2

2Z3=0.4×4×(1.2+7.17)×2=26.784 m2

小计:66.96+60.264+26.784=154.008

首层梁与柱交叉部分模板的面积:m2

4Z1=0.37×0.5×2×4=1.48 m2

4Z2=(0.37×0.5×2+0.24×0.5)×4=1.96 m2

2Z3=0.24×0.5×3×2=0.72 m2

小计:1.48+1.96+0.72=4.16 m2

二层梁与柱交叉部分模板的面积:m2

4Z1=0.37×0.65×2×4=1.924 m2

4Z2=(0.37×0.65×2+0.24×0.5)×4=2.404 m2

2Z3=0.24×0.5×3×4=0.72 m2

小计:1.924+2.404+0.72=5.048 m2

框架柱的模板=154.008-4.16-5.048=144.8 m2

C25砼女儿墙构造柱:m3

4Z–=(0.24×0.24×0.54+0.24×0.03×0.54×2)×4=0.156 m3

4Z∟=(0.24×0.24×0.54+0.24×0.03×0.54×2)×4=0.156 m3

V总=0.156+0.156=0.312 m3

模板的面积:m2

4Z–=(0.24+0.006×2)×0.54×2×4=1.555 m2

4Z∟=(0.24+0.006)×0.54×2×4+0.006×0.54×2×4=1.555 m2

S总=1.555+1.555=3.11 m2

3.57mC25砼框架梁m3

①④2KL2(1):(6-0.25×2)×0.37×0.4×2=1.628 m3

②③2KL4(2):(6-0.25×2-0.4)×0.24×0.4×2=0.979m3

A2KL3(3):(11.1-0.25×2-0.4×2)×0.37×0.4=1.4504 m3

C2KL1(3):(11.1-0.25×2-0.4×2)×0.37×0.4=1.4504 m3

BKL5(1):(4.5-0.2×2)×0.24×0.4=0.394 m3

小计:1.628+0.979+1.4504+1.4504+0.394=5.901 m3

模板:m2

①④2KL2(1):(0.5+0.4+0.37)×(6-0.25×2)×2=13.97 m2

②③2KL4(2):(0.4+0.4+0.24)×(6-0.25×2-0.4)×2=10.608 m2 A2KL3(3):(0.5+0.4+0.37)×(11.1-0.25×2-0.4×2)=12.446 m2 C2KL1(3):(0.5+0.4+0.37)×(11.1-0.25×2-0.4×2)=12.446 m2 BKL5(1)(0.4+0.4+0.24)×(4.5-0.2×2)=4.264 m2

小计:13.97+10.608+12.446+12.446+4.264=53.734 m2

7.17mC25砼框架梁:m3