水利工程毕业设计外文翻译---三峡水利枢纽工程

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

The Three Gorges Projects

First. The dam site and basic pivot disposal

The Three Gorges Projects is select to be fixed on San Dou Ping in Yichang, located in about 40 kilometers of the upper reaches of key water control project of Ge Zhou Ba which was built. River valley, district of dam site, is widen, slope, the two sidesof the bank is relatively gentlely. In the central plains have one island (island, fort of China,), possess the good phased construction water conservancy diversion condition. The foundation of pivot building is the hard and intact body of granite. Have built Yichang and gone to stride bridge that place of 4 kilometers in the about 28 -km-long special-purpose expressway of building site and dam low reaches --West Yangtze Bridge of imperial tomb. Have also built the quay of district of a batch of dams. The dam district possesses the good traffic condition.

Two. Important water conservancy project buildings

1. dam

The dam is a concrete gravity dam, which is 2309 meters long, it’s height is 185 meters , the dam is 181 meters high the most. Release floodwater dam section lie riverbed, 483 of the total length, consist of 22 form hole and 23 release floodwater in the deep hole, among them deep hole is imported 90 meters , the mouth size of hole is 7*9 meters; Form hole mouth is 8 meter wide, overflow weir is 158 meters, form hole and deep hole adopt nose bank choose, flow way go on and can disappear. Dam section lies in and releases floodwater on a section of both sides of the dam in the hydropower station, there are hydropower stations that enter water mouth. Enter water mouth baseplate height 108 meters. Pressure input water pipeline for carry person who in charge of, interior diameter 12.40, adopt the armored concrete to receive the strength structure. Make and let out flow of 102500 cubic meters per second the most largely in the dam site while checking the flood.

2. power stations

The power stations adopt the type after the dam to assign the scheme, consist of two groups of factory buildings on left, right and underground factory building altogether. Install 32 sets of hydroelectric generating set together, 14 factory buildings of left bank among them, 12 factory buildings of right bank, 6 underground factory

buildings. The hydraulic turbine, in order to mix the flowing type, the specified capacity of the unit of the unit is 700,000 kilowatts.

3. open up to navigation building

The open up to navigation buildings include permanent lock and ship lift (of the the technological public relations, the steel cable that plans to be replaced with spiral pole technology in the original plan promotes technology), lie in the left bank. Permanent lock double-line five continuous chain of locks. Single grades of floodgate room effective size for 280*34*5, can pass the 10,000 ton-class fleet. The promoting type for single track first grade vertically of the ship lift is designed, it is 120*18*3.5 meters to bear the effective size of design of railway carriage or compartment of ship, can pass a combination vessel of 3000 tons once. Total weight is 11800 tons to bear the design of railway carriage or compartment of ship when operating, it is 6000 newtons to always promote strength.

Three.The major project amount and arranges in time limit The subject building of the project and major project amount of the water conservancy diversion project are: Excavate 102,830,000 cubic meters in cubic metre of earth and stone, fill out and build 31,980,000 cubic meters in cubic metre of earth and stone, concrete builds 27,940,000 cubic meters, 463,000 tons of reinforcing bars, make and fit 32 with hydroelectric generating set. All project construction tasks were divided into three stages and finished, all time limit was 17 years. The first stage (1993-1997 year) is preparation of construction and the first stage of the project, it takes 5 years to construct, regard realizing damming in the great river as the sign. The second stage (1998-2003 year) is the second stage, it takes 6 years to construct, lock as initial conservation storage of the reservoir, the first batch of aircrews generate electricity and is open up to navigation with the permanent lock as. The third stage (2004-2009 year) is the third stage of the project, it takes 6 years to construct, regard realizing the sign all aircrews generate electricity and finish building with all of multi-purpose project as. One, two project finish as scheduled already, the third stage of the project in inside the plan to construct too, ship lift tackle key problems of not going on intensely.

Four. Enormous benefit of the Three Gorges Projects

相关文档
最新文档