XXX项目机电项目设备吊装方案

XXX公司

Contens

目录

3. PROJECT EXECUTION PROCEDURES施工方案3 3.1 Large Scale Equipment Lifting Plan大型设备吊装方案3

3.1.1 General编制说明3

3.1.2 Applicable Codes and Standards引用的标准和规范3

3.1.3 Lifting Overall Design吊装总体设计4

3.1.4 Heavy Lifting Table大型设备吊装清单5

3.1.5 Lifting Plan of DG workshop 甲类厂房设备吊装7

3.1.6 Lifting Plan of AT workshop丙类厂房设备吊装13 3.1.6.1 General总体说明13

3.1.6.2 M020304 lifting plan 设备吊装13

3.1.6.3M020212C Lifting Plan设备吊装21

3.1.7Lifting Device List吊装机具一览表27

3.1.8 Safety Technology Requirements安全技术措施27

3. Project execution procedures施工方案

3.1 Large Scale Equipment Lifting Plan大型设备吊装方案

3.1.1 General编制说明

XXX Project Phase Ⅱhas 363 equipments.

xxx项目二期工程,共有设备363台。

The equipments which are more than 10T are about 13 sets. The workshop is the concrete framework structure and the equipments are heavy so we need to prepare the Lifting Plan to guide the project equipment lifting and all project coordination.

超过10吨的重型设备有13台。由于车间属于混凝土框架结构,并且设备重量较大,必须编制吊装方案,用于指导项目的设备吊装工作和整个工程的施工协调。

3.1.2 Applicable Codes and Standards引用的标准和规范

Construction technical drawings supplied by OWNER

业主提供的施工技术图纸

Equipment plot plan layout设备平面布置图

Construction standard for large-size equipment hoisting engineering

大型设备吊装工程施工工艺标准SH/T 3515-2003

Safety specification for hoisting installation

起重机械安全规程GB6067.1-2011

Lifting construction specification for petrochemical engineering

石油化工工程起重施工规范SH/T3536-2002

Specification for hoisting of installation project of construction engineering

工程建设安装工程起重施工规范HG20201-2000

Technical code for safety of working on higher in construction

建筑施工高处作业安全技术规范JGJ80-91

Technical code for safety of steel tubular scaffold with couplers in construction

建筑施工扣件式钢管脚手架安全技术规范JGJ130-2011

Site construction condition现场施工条件

Capacity diagram for relative cranes吊车性能表

3.1.3 Lifting Overall Design吊装总体设计

The normal equipment weighs above 20Tand under 30T. The 100T track crane can lift it. Even though the speed is not fast, it suit for the lift alone. When the goods arrived and installed immediately. The cost is low. The equipment weigh under 20T, the 50T track crane can lift it. The unloading and transportation are very convenient. Due to the numbers the track are large, the equipments can be lift concentrated.Crane and a scooter to focus to use, can maximize labor efficiency, saving construction cost.

一般30吨以下20吨以上的设备,属于100吨以上汽车吊的能力范围,吊装过程比较慢,单台吊装比较适宜,到货后立即安装,可以节省二次运输费用。20吨以下的设备,是50吨以下汽车吊的能力范围,卸车和运输都比较方便,由于台数比较多,适合于多台设备一起吊装。吊车和板车集中使用,可以最大限度地提高工人的劳动效率,节约施工成本。

This scheme gives all heavy equipment (> 10t) of the lifting scheme, need crane are listed in the large scale equipment lifting list. After that, he painted out of the 13 sets of equipment assembly drawings, are representative.

本方案给出了全部重型设备(>10吨)的吊装方案,所需要的吊车均列在大型设备吊装清单里。在此之后,还画出了13台设备的吊装图纸,均具有代表性。