Beijing Jin Maofu elementary schoolMechanical commissioning contract Part A:Sinochem

FangXing Properties

(Beijing)

part B:ZhongZi engineering construction supervision company

Protocol address:Beijig

The agreement time:2011.7.8

Project name: Beijing Jin Maofu elementary school

Beijing Jin Maofu Beijing Jin Maofu elementary school primary energy system debugging and strengthen debuggingprimary energy system fundamental commissioning and enhanced commissioning Agreement period: according to the requirements of the party awarding the contract, the contractor within 5 days after receiving notice of the party to the scene, Technical standards and requirements

The contract price Method of payment Engineering settlement

there is no service fees for the project's owner, because of the long-term cooperative relation between the two sides

Commissioning

Agent : xinyue jia administrator

Party A's work Party B's work Review design documents, Preparation of commissioning plan and the relevant

commissioning file During the

period of

constructio

n site supervision

, timely

report to

the owner

if have any

questions

installation and

running test

system

performance test

Submit testing record on a regular basis

compile mechanical and electrical operation and maintenance manuals , on property management personnel training

after the project put

into operation,

continuous monitoring

equipment performance

for 10 months, time

limit for a project is

terminated