1.The main tasks and the subtasks for ICT’s survey project
Task Name
1 Survey Planning
1.1 Identify the objective
1.2 Drafts the questionnaire
1.3 To pre-test the questionnaire
1.4 Produce the final questionnaire
2 Survey the cities
2.1 Survey in Edinburgh
2.2 Survey in Glasgow
2.3 Survey in Paisley
2.4 Survey in Stirling
2.5 Return Questionnaires to Headquarters
3 Analyze the questionnaires
3.1 Analyze the Survey from Edinburgh
3.2 Analyze the Survey from Glasgow
3.3 Analyze the Survey from Paisley
3.4 Analyze the Survey from Stirling
3.5 Compare Survey Result
3.6 Identify the Key Trend
4 Produce a survey report
4.1 Draft the report
4.2 Edit The Report
4.3 Produce The Final Report
4.4 Executive Summary
4.5 Completed Report
5 Produce a presentation of the survey report
5.1 Create Presentation
5.2 Review Presentation
6 Present Presentation
5.3 To present to senior managers
5.4 To present to branch managers
5.5 To present to team leaders
5.6 Presentation Complete
2. The duration of each of the subtasks
Task Name
1 Survey Planning
1.1 Identify the objective 1 day
1.2 Drafts the questionnaire 5 days
1.3 To pre-test the questionnaire 6 days
1.4 Produce the final questionnaire 2 days
2 Survey the cities 34 days
2.1 Survey in Edinburgh 10 days
2.2 Survey in Glasgow 10
2.3 Survey in Paisley 9
2.4 Survey in Stirling 5
2.5 Return Questionnaires to Headquarters3 0 Analyze the questionnaires 38 days
3.1 Analyze the Survey from Edinburgh 9
3.2 Analyze the Survey from Glasgow 8
3.3 Analyze the Survey from Paisley 7
3.4 Analyze the Survey from Stirling 4
3.5 Compare Survey Result 5
3.6 Identify the Key Trend 5
4 Produce a survey report 2
5 days
4.1 Draft the report 11
4.2 Edit The Report 5
4.3 Produce The Final Report 6
4.4 Executive Summary 1
4.5 Completed Report 0
5 Produce a presentation of the survey report 6
5.1 Create Presentation 5
5.2 Review Presentation 1
6 Present Presentation 3
5.3 To present to senior managers 1
5.4 To present to branch managers 1
5.5 To present to team leaders 1
5.6 Presentation Complete 0
3. The project milestones
Milestones are: Important events during the duration of the project when reviews of time, cost and quality are carried out. Milestones are activities that must take place by a certain date. Milestones are set so you can measure your performance against your objective.
4. The milestones in ICT’s survey project
The milesto nes in ICT’s survey project are that:
2.5 Return Questionnaires to Headquarters3
4.5 Completed Report
5.6 Presentation Complete
5. The dependencies between tasks
ID Task Name Predecessor