Project Management Homework
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
Case : Anntas Ltd is an organisation which provides inflatable toys to childrens retailers. These products include: beach balls, rubber boats, and an extensive range of swimming aids. As part of your job as the Anntas Ltd Special Projects Manager, you have produced a list of activities that need to be addressed to develop a new toy (non inflatable) for the retail industry . The details are shown in the table provided. Please note: You must use the methodology detailed above table 1 headed“essential meth odology”.
Task
1)Draw the network diagram (use activity on the node).
2)Explain how you determined the timing of activities and the total
float.
3)Explain how you determined the project duration and the critical
path.
4)If the project starts on the 11 January 2010 , what is the earliest
date it can be completed using a 5 day working week? Assume no
other holidays (explain how you calculated the figure).
5)If the following happened what would be the effect on the
duration of the whole project? Explain the reasons.
a)A 1 day delay during activity P.
b)Activity N is completed 1 day before schedule.
c)A 2 day delay during activity I .
6)Explain and discuss the purpose of network diagrams.
Table 1
要求:
1、字号:四号字体:Times New Roman 行间距:单倍行距;
2、段首不空两格,段与段之间空一行;
3、小组作业全部用英文来完成,总字数至少1000字;
4、每部分的分工要明确,写清楚每个部分是由哪位小组成员完成的;
5、每个问题之间是互相有关联的,自己完成自己那部分的同时要注意检查其他同学完成的对不对;
6、截止到17周交上。