塔架施工方案

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

Erection Program For

the 443-3P1preheater tower

Name of the document:The Erection program of the

443-3P1 preheater tower

No. of the document:GU3-方案-M-010

Editing department:The Engineering department of CBMI

Edited by:Liu Li Da Date:2013-11-20 Verified by:Date:

Approved by:Date:

Version 0

目录

contents

一.工程概述 Summary------------------------------------3

二.方案编制依据Compilation basis ---------------------3

三.吊装机具的选择The choice of Lifting instrument-----6

四.质量安全保证体系流程图

The flow chart of quality safety guarantee system-----11 五.施工工艺过程 The construction process----------------12

六.安全及文明施工Safe and civilized construction--------16

一.工程概述Summary:

HOLCIM(ECUADOR)GU3水泥厂是一条日产4500吨的水泥熟料生产线。窑尾预热器塔架是整个熟料生产线的关键部位,因其系统复杂,安装高度高,构件数量多,单件重量重而成为安装难度最大的一个子项之一。预热器塔架采用钢结构和预热器相结合的安装方式,其中钢结构的的作用是支撑整个预热器系统,提供生产操作,检修操作的平台。整个钢结构主体系统共7层,高96.4m (15m-111.4m),构件共9根H型钢,,各层平面有连接梁,上铺花纹钢板,钢结构总重约2500吨。预热器在熟料生产中主要起生料预热和物料分解的作用,整个系统分别由五级旋风筒、分解炉、三次风管、喂料室等组成,设备安装分别从喂料室开始至C1旋风筒结束。预热器系统还配备有提升机、喂料机、风机、收尘器,电梯等辅助设备。

HOLCIM (ECUADOR) GU3 Cement is a 4500 t/d clinker cement production line. Preheater tower is the key component of clinker production line, because of its complexity, the installation height is high, the number of multi-component, one-piece heavy weight and become difficult to install one of the largest one child. Preheater tower using a combination of steel and installation, which is the role of steel structures to support the entire preheater system, providing

production operations, maintenance operations platform.

Entire steel body system of 7 storey, 96.4m (15m-111.4m), member of 9 H-beam, the beam is connected planar layers, upper tread plate, steel structure weighing about 2,500 tons.

Preheater in the clinker production mainly from the decomposition of raw material preheating and the role of the entire system respectively, by five cyclone, calciner, tertiary air duct, feed room and other components, equipment installation separately from the feed chamber begins - C1 cyclone ends. Preheater system is also equipped with bucket elevator, feeder, fan, dust collector, elevators and other auxiliary equipments.

二.编制依据Compilation basis

1.HOLCIM(ECUADOR)GU3水泥厂烧成窑尾工艺布置图。

HOLCIM(ECUADOR)GU3 PROJECT PREHEATER TOWER GENERAL ARRANGEMENT DRAWING

文件编号:GU3-方案-M-010

工艺布置图

General arrangement drawing

5

2.HOLCIM(ECUADOR)GU3水泥厂窑尾塔架钢结构制作、安装图。HOLCIM(ECUADOR)GU3 preheater tower steel structure fabrication, installation drawings

3.HOLCIM(ECUADOR)GU3水泥厂预热器制作、安装图。

HOLCIM(ECUADOR)GU3 preheater fabrication, installation drawings

4.钢结构施工验收规范Steel construction and acceptance。

5.机械设备安装验收规范Mechanical equipment installation acceptance。

三.吊装机具的选择The choice of Lifting instrument:

窑尾预热器塔架的安装主要包括预热器的地面组对工作和钢结构预热器的高空安装工作。钢结构、预热器的安装工作由于构件安装高度高,整个安装面积大,如使用大型可移动吊车将存在吊装高度不够,吊装性能小的问题,并且施工速度也很慢。所以我们将采用STT403-24T型塔吊。地面预热器的组对将使用一台50吨吊车。下面是STT403-24T塔吊的性能表和预热器塔塔吊的布置图。

Preheater tower installation includes preheater ground group work and steel preheater aerial installation work. Steel structure and the installation of the preheater components mounting height is high, the entire installation area, if using the large mobile crane, the lifting will be not high enough and

相关文档
最新文档