2018年版《广东省市政定额说明及计算规则》D.5 排水工程

2018年版《广东省市政定额说明及计算规则》D.5 排水工程
广东省建设工程计价依据
广东省 市政工程综合定额
2018
第五册 排水工程
主编单位:广东省建设工程标准定额站 广东省工程造价协会
批准部门:广东省住房和城乡建设厅 执行日期:2019 年 3 月 1 日
目录
总说明························································································································· 1 册说明························································································································· 7
(1)平基·········································································································· 24 (2)负拱基础····································································································· 27 (3)混凝土枕基、管座··························································································· 28 (4)满包混凝土加固····························································································· 29

2018新定额说明与计算规则

2018新定额说明与计算规则

A.1.1土石方工程一、本章定额包括土方工程、石方工程、回填方及其他,共三节。

二、规定1.土石方工程土壤及岩石类别的划分,依照工程勘测资料与《土壤分类表》、《岩石分类表》对照后确定。

2干土、湿土的划分:首先应以地质勘测资料为准,含水率<25%为干土,含水率≥25%且小于液限为湿土:或以地下常水位为准划分,地下常水位以上为干土,以下为湿土,如采用降水措施的,应以降水后的水位为地下常水位,降水措施费用应另行计算。

3.平整场地、沟槽、基坑、一般土石方划分规定:场地厚度≤士30cm的就地挖、填运、找平为平整场地:底宽≤7m且底长>3倍底宽为沟槽,底长≤3倍底宽且底面积≤150m为基坑:超出上述范围则为一般土石方。

4.本章末包括现场障碍物清除、地下水位以下施工的排(降)水、地表水排除及边坡支护,发生时应另行计算5.本章土石方运输子目适用于运距在30km以内的运输,运距超过30km(但不超过50km)部分按每增加1km相应定额子目乘以系数0.65计算,运超过50km 的按相关管理部门的规定计算。

6.本章土石方运输子目是按每天8小时的运輸作业时间综合考虑的,如各市对土石方场外运输有时间限制,作业时间不足8小时的可计算工效损失费,每减少1小时按土石方机械运输子目中的机具费乘以4.2%让算。

7.推土机土、推石渣,铲运机铲运土,重车上坡时,如果坡度大于5%,其运距按坡度区段斜长乘以下表系数计算三、土方1.土方定额子目是按干土编制的。

人工挖湿土时,相应定额子目人工费乘以系数1.18,机械挖湿土时,相应定额子目人工费、机具费乘以系数1.10。

2.桩间土不扣除桩芯直径60cm以内或类似尺尺寸桩体所占体积。

人工挖桩间土方,相应定额子目人工费乘以系数1.30:机械挖桩间土方,相应定额子目人工费、机具费乘以系数1.103.在挡土板支撑下人工挖沟槽、基坑土方时,相应定额子目人工费乘以系数1.204.挖掘机在垫板上进行作业,相应定额子目的人工费、机具费乘以系数1.25,搭拆垫板的费用另行计算。

2018年版《广东省市政定额说明及计算规则》D.5 排水工程

2018年版《广东省市政定额说明及计算规则》D.5 排水工程
1 预制··················································································································· 36 2 安装··················································································································· 39
D.5.1.7 闭水试验·······································································································49
1 管道闭水试验······································································································· 49 2 沟渠闭水试验······································································································· 54
(1)渠道盖板····································································································· 39 (2)井室盖板····································································································· 41 (3)检查井过梁···································································································43

广东省安装工程综合定额说明及计算规则(年版)

广东省安装工程综合定额说明及计算规则(年版)

广东省安装工程综合定额说明及计算规则(年版)部门: xxx时间: xxx制作人:xxx整理范文,仅供参考,可下载自行修改广东2018安装工程综合定额编制说明及计算规则总说明一、《广东省安装工程综合定额<2018)》(以下简称本综合定额>是在《全国统一安装工程预算定额》(第一~十一册、十三册>(GYD-201-2000~GYD-211-2000、GYD-213-2003>和《广东省安装工程综合定额(2006>》基础上,结合我省设计、施工、招投标的实际情况,根据现行国家产品标准、设计规范和施工验收规范、质量评定标准、安全操作规程编制的,共分十二册。

b5E2RGbCAP二、本综合定额是编审设计概算、施工图预算、招标控制价、竣工结算,调解处理工程造价纠纷,鉴定工程造价的依据;是合理确定和有效控制工程造价和衡量投标报价合理性的基础;也作为投标报价,加强企业内部管理和核算的参考。

p1EanqFDPw三、本综合定额适用于全省行政区域内新建、扩建和改建的工业与民用安装工程。

四、本综合定额是完成单位工程量所需的人工、材料、机械、管理费和必要的施工措施费的计量标准,它反映了社会平均消耗水平。

DXDiTa9E3d五、本综合定额的工作内容简单扼要说明主要的施工工序,次要的工序虽然没有具体说明,但已经综合考虑在内。

六、本综合定额中是按下列正常的施工条件以及目前我省企业的施工机械装备程度、合理的施工工期、施工工艺、劳动组织为基础综合确定的:RTCrpUDGiT1. 设备、材料、成品、半成品、构件完整无损,符合质量标准和设计要求,附有合格证书和实验记录。

2. 各专业工程之间的交叉作业正常。

3. 安装地点、建筑物、设备基础、预留孔洞等均符合安装要求。

4. 水、电供应均满足施工正常使用。

5. 正常的气候、地理条件和施工环境。

七、关于人工:1. 本综合定额的人工不分工种和技术等级,采用综合用工形式,工日数已包括基本用工、辅助用工、人工幅度差、现场运输及清理现场等用工。

XX广东省市政工程定额说明

XX广东省市政工程定额说明

XX广东省市政工程定额说明编制讲明及计算规则(2018年版)广东省市政工程综合定额第1册总讲明二本综合定额是编审设计概算、施工图预算、招标操纵价、竣工结算,调解处理工程造价纠纷,鉴定工程造价的依据;是合理确定和有效操纵工程造价及衡量投标报价合理性的基础;也作为投标报价,加强企业内部治理和核算的参考。

三本综合定额适用于全省行政区域内新建、扩建和改建的市政工程。

四本综合定额是完成单位工程量所需的人工、材料、机械、治理费和必要的施工措施费的计量标准,它反映了社会平均消耗水平。

五本综合定额的工作内容简单扼要讲明要紧的施工工序,次要的工序尽管没有具体讲明,但差不多综合考虑在内。

六本综合定额是按下列正常的施工条件以及目前我省企业的施工机械装备程度、合理的施工工期、施工工艺、劳动组织为基础综合确定的:1.设备、材料、成品、半成品、构件完整无损,符合质量标准和设计要求,附有合格证书和试验记录。

2.各专业工程之间的交叉作业正常。

3.水、电供应均满足施工正常使用。

4.正常的气候、地理条件和施工环境。

七关于人工:1.本综合定额的人工不分工种和技术等级,采纳综合用工形式,工日数已包括差不多用工、辅助用工、人工幅度差、现场运输及清理现场等用工。

2.本综合定额中的人工费为直截了当从事工程施工的生产工人开支的各项费用,内容包括:(1)差不多工资:是指发放给生产工人的差不多工资。

(2)工资性补贴:是指按规定标准发放的物价补贴,煤、燃气补贴,交通补贴,住房补贴,流淌施工津贴等。

(3)生产工人辅助工资:是指生产工人年有效施工天数以外非作业天数的工资,包括职工学习、培训期间的工资,调动工作、探亲、休假期间的工资,因气候阻碍的停工工资,女工哺乳时刻的工资,病假在六个月以内的工资及产、婚、丧假期的工资。

(4)职工福利费:是指按规定标准计提的职工福利费。

(5)生产工人劳动爱护费:是指按规定标准发放的劳动爱护用品的购置费及修理费,徒工服装补贴,防暑降温费,在有碍躯体健康环境中施工的保健费用等。

广东省房屋建筑与装饰工程综合定额(2018)

广东省房屋建筑与装饰工程综合定额(2018)

广东省建设工程计价依据广东省房屋建筑与装饰工程综合定额2018广东省住房和城乡建设厅总说明一、《广东省房屋建筑与装饰工程综合定额(2018)》(以下简称本综合定额)是在国家标准《建设工程工程量清单计价规范》GB50500-2013、《建设工程劳动定额》、《房屋建筑与装饰工程消耗量定额》TY01-31-2015及《广东省建设工程计价依据》(2010年)的基础上,结合我省实际,根据现行国家产品标准、设计规范和施工验收规范、质量评定标准、安全操作规程、绿色施工评价标准等编制的。

二、本综合定额适用于全省行政区域内采用绿色施工标准新建、扩建和改建的房屋建筑与装饰工程。

三、本综合定额是我省房屋建筑与装饰工程合理确定和有效控制工程造价、衡量工程造价合理性的基础,是编审设计概算、施工图预算、招标控制价、竣工结算的依据,是处理工程造价纠纷、鉴定工程造价的依据,也作为企业投标报价、加强内部管理和核算的参考。

四、本综合定额是完成单位工程量所需的人工费用、材料、机具等消耗量及管理费标准,该消耗量及费用标准是按正常的施工条件,以我省建筑企业的施工机械装备程度、合理的施工工期、采用绿色施工标准的施工工艺、劳动组织为基础综合确定的,反映了社会平均水平。

五、本综合定额由分部分项工程项目、措施项目、其他项目、税金、附录共五部分组成。

子目基价及其组项价格均不包含增值税可抵扣进项税额。

六、本综合定额按章、节、项目、子目排列,各章均有章说明、工程量计算规则,项目由工作内容和定额表格组成,有的加上必要的附注。

工作内容简单扼要地说明主要施工工序,次要施工工序虽未具体说明,但均已综合考虑在内。

七、关于人工费1.本综合定额的人工费是指直接从事施工作业的生产工人的薪酬,包括了基本用工、辅助用工、人工幅度差、现场运输及清理现场等用工费用,已经综合考虑了不同工种、不同技术等级等因素,内容包括工资性收入、社会保险费、住房公积金、工会经费、职工教育经费、职工福利费及特殊情况下支付的工资等。

广东省2018通用安装工程综合定额!!

广东省2018通用安装工程综合定额!!

广东省广东省通用安装工程综合定额(说明)-(整理自ChrisL)2018总说明一、《广东省通用安装工程综合定额(2018)》(以下简称本综合定额)是在国家标准<建设工程工程量清单计价规范》GB50500-2013、《建设工程劳动定额》LD/T75.1-2008、《通用安装工程消耗量定额》TY02-31-2015和《广东省建设工程计价依据》(2010年)的基础上,结合我省实际,根据现行国家产品标准、设计规范和施工验收规范、质量评定标准、安全操作规程、绿色施工评价标准等编制的。

二、本综合定额适用于全省行政区域内采用绿色施工标准新建、扩建和改建的工业与民用建筑通用安装工程。

三、本综合定额是我省通用安装工程合理确定和有效控制工程造价、衡量工程造价合理性的基础,是编审设计概算、施工图预算、招标控制价、竣工结算的依据,是处理工程造价纠纷、鉴定工程造价的依据,也作为企业投标报价、加强内部管理和核算的参考。

四、本综合定额是完成单位工程量所需的人工费用,材料,机具等消耗量以及管理费标准。

该消耗量及费用标准是按正常的施工条件,以我省建筑企业的施工机械装备程度、合理的施工工期、采用绿色施工标准的施工工艺、劳动组织为基础综合确定的,反映了社会平均水平。

五、本综合定额由《机械设备安装工程》、《热力设备安装工程》、《静置设备与工艺金属结构制作安装工程》、《电气设备安装工程》、《建筑智能化工程》、《自动化控制仪表安装工程》、《通风空调工程》、《工业管道工程》、《消防工程》、《给排水、采暖、燃气工程》、《通信设备及线路工程》和《刷油、防腐蚀、绝热工程》共十二册组成,子目基价及其组项价格均不包含增值税可抵扣进项税额。

六、本综合定额各专业册按章、节、项目、子目排列,各册均有总说明、册说明、章说明、工程量计算规则、分部分项工程项目、措施项目、其他项目、税金、附录,项目由工作内容和定额表格组成,有的加上必要的附注。

工作内容简单扼要说明主要施工工序,次要施工工序虽未具体说明,但均已综合考虑在内。

2018年版《广东省市政定额说明及计算规则》D.2 道路工程

2018年版《广东省市政定额说明及计算规则》D.2 道路工程
1
3 中砂嵌缝············································································································ 34
D.2.2.9 山皮石底层··································································································· 35 D.2.2.10 沥青稳定碎石······························································································ 36
1 碎石嵌缝············································································································· 32 2 碎石、中砂嵌缝···································································································· 33
D.2.3 道路面层
说明··························································································································· 39 工程量计算规则·········································································································· 41 D.2.3.1 泥结碎石路面································································································43 D.2.3.2 级配碎石路面································································································44 D.2.3.3 沥青表面处治································································································45 D.2.3.4 沥青贯入式路面···························································································· 47 D.2.3.5 加工沥青混凝土、沥青砂、黑色碎石及沥青·················································· 48 D.2.3.6 黑色碎石路面································································································50 D.2.3.7 沥青粘层、透层···························································································· 51 D.2.3.8 沥青封层·······································································································52 D.2.3.9 自卸汽车运输沥青混凝土混合料····································································53 D.2.3.10 铺筑沥青混凝土路面··················································································· 54 D.2.3.11 水泥混凝土路面·························································································· 56 D.2.3.12 伸缝············································································································57 D.2.3.13 缩缝············································································································58 D.2.3.14 水泥混凝土路面养生··················································································· 59 D.2.3.15 水泥混凝土路面钢筋··················································································· 61 D.2.3.16 道路传力杆套筒·························································································· 62 D.2.3.17 旧路裂缝处理······························································································ 63 D.2.3.18 铺设土工材料······························································································ 64

广东省房屋建筑与装饰工程定额(2018版)

广东省房屋建筑与装饰工程定额(2018版)

总说明曾一玻制作于2020年3月10日星期二一、《省房屋建筑与装饰工程综合定额(2018)》(以下简称本综合定额)是在国家标准《建设工程工程量清单计价规》GB50500-2013、《建设工程劳动定额》、《房屋建筑与装饰工程消耗量定额》TY01-31-2015及《省建设工程计价依据》(2010年)的基础上,结合我省实际,根据现行国家产品标准、设计规和施工验收规、质量评定标准、安全操作规程、绿色施工评价标准等编制的。

二、本综合定额适用于全省行政区域采用绿色施工标准新建、扩建和改建的房屋建筑与装饰工程。

三、本综合定额是我省房屋建筑与装饰工程合理确定和有效控制工程造价、衡量工程造价合理性的基础,是编审设计概算、施工图预算、招标控制价、竣工结算的依据,是处理工程造价纠纷、鉴定工程造价的依据,也作为企业投标报价、加强部管理和核算的参考。

四、本综合定额是完成单位工程量所需的人工费用、材料、机具等消耗量及管理费标准,该消耗量及费用标准是按正常的施工条件,以我省建筑企业的施工机械装备程度、合理的施工工期、采用绿色施工标准的施工工艺、劳动组织为基础综合确定的,反映了社会平均水平。

五、本综合定额由分部分项工程项目、措施项目、其他项目、税金、附录共五部分组成。

子目基价及其组项价格均不包含增值税可抵扣进项税额。

六、本综合定额按章、节、项目、子目排列,各章均有章说明、工程量计算规则,项目由工作容和定额表格组成,有的加上必要的附注。

工作容简单扼要地说明主要施工工序,次要施工工序虽未具体说明,但均已综合考虑在。

七、关于人工费1.本综合定额的人工费是指直接从事施工作业的生产工人的薪酬,包括了基本用工、辅助用工、人工幅度差、现场运输及清理现场等用工费用,已经综合考虑了不同工种、不同技术等级等因素,容包括工资性收入、社会保险费、住房公积金、工会经费、职工教育经费、职工福利费及特殊情况下支付的工资等。

(1)工资性收入:按计时工资标准和工作时间或对已工作按计件单价支付给个人的劳动报酬。

2018年版《广东省市政定额说明及计算规则》D.5 排水工程

2018年版《广东省市政定额说明及计算规则》D.5 排水工程
2019第一部分分部分项工程项目d51管道基础及其他说明13工程量计算规则15d511定型混凝土管道基础17钢筋混凝土管90混凝土基础17钢筋混凝土管120混凝土基础18钢筋混凝土管180混凝土基础19d512非定型渠管道垫层及基础20垫层20渠管道基础24242负拱基础273混凝土枕基管座284满包混凝土加固29d513非定型渠道抹灰与勾缝30抹灰3032d514渠道沉降缝34d515混凝土盖板过梁的预制安装36预制36安装391渠道盖板392井室盖板413检查井过梁43d516混凝土管截断4448d517闭水试验49管道闭水试验49沟渠闭水试验54d52管道铺设说明57工程量计算规则61d521混凝土管铺设63承插式150300076d522混凝土管管道接口85平企接口851水泥砂浆接口120管基852水泥砂浆接口180管基873钢丝网水泥砂浆接口120管基894钢丝网水泥砂浆接口180管基945膨胀水泥砂浆接口99预制混凝土外套环接口1031柔性接口平口1032柔性接口企口107现浇混凝土套环接口1081现浇混凝土套环接口120管基1082现浇混凝土套环接口180管基113cp250型橡胶止水带接口06ms2011第3537承插接口1231水泥砂浆接口1232沥青油接口125橡胶圈接口1271承插口企口1271323双插口135d523玻璃钢夹砂管铺设承插式胶圈接口138d524塑料管铺设141中空壁缠绕结构管安装电热熔带接口141双壁波纹管安装pvcu或hdpe承插式胶圈接口146d525泥水平衡顶管机械及附属设施安拆151泥水平衡顶进160混凝土管顶进165挤压顶进1711钢管1712铸铁管1731752接口176混凝土顶管平口管沥青麻丝膨胀水泥接口17710混凝土管顶管企口管接口1801沥青麻丝膨胀水泥接口1802橡胶垫板膨胀水泥接口18311顶管接口外套环18612顶管接口内套环18819113顶管钢板套环制作193d526现浇混凝土方沟194d527砌筑渠道195砌筑墙帽197d528现浇混凝土渠道198d53管道附属构筑物说明201工程量计算规则203砖砌圆形雨水检查井205砖砌圆形污水检查井208砖砌竖槽式跌水井2111砖砌竖槽式跌水井收口式直线外跌2112砖砌竖槽式跌水井直线外跌2133砖砌竖槽式跌水井支线外跌215砖砌阶梯式跌水井217砖砌污水闸槽井220砖砌矩形直线雨水检查井223砖砌矩

2018年版《广东省市政定额说明及计算规则》D.5 排水工程

2018年版《广东省市政定额说明及计算规则》D.5 排水工程
2
(4)钢丝网水泥砂浆接口(180°管基)······································································· 94 (5)膨胀水泥砂浆接口·········································································································99 2 预制混凝土外套环接口························································································· 103 (1)柔性接口(平口)························································································· 103 (2)柔性接口(企口)························································································· 107 3 现浇混凝土套环接口···························································································· 108 (1)现浇混凝土套环接口(120°管基)······································································ 108 (2)现浇混凝土套环接口(180°管基)······································································ 113 4 CP250 型橡胶止水带接口(06MS201-1 第 35-37 页)··················································· 118 5 承插接口············································································································123 (1)水泥砂浆接口·······························································································123 (2)沥青油接口································································································· 125 6 橡胶圈接口·········································································································127 (1)承插口、企口·······························································································127 (2)钢承口······································································································ 132 (3)双插口······································································································ 135

2018广东建筑定额脚手架工程说明及计算规则

2018广东建筑定额脚手架工程说明及计算规则

2018广东建筑定额脚手架工程说明及计算规则一、引言脚手架工程在广东建筑行业中扮演着重要的角色。

本文将详细介绍2018年广东建筑定额脚手架工程的说明及计算规则。

二、脚手架概述脚手架是用于支撑工人和材料的临时结构,在建筑施工和维修过程中起到关键的作用。

脚手架的质量和安全性对于工程的顺利进行至关重要。

2.1脚手架的定义脚手架是指用各种材料搭建、安全、稳定的结构,为施工人员提供工作平台和安全通道的设施。

2.2脚手架的分类根据使用方式和搭建材料的不同,脚手架可分为悬挑式脚手架、支撑式脚手架、特殊脚手架等多种类型。

三、2018广东建筑定额脚手架工程说明根据广东建筑定额,脚手架工程应遵循以下规定:3.1脚手架的设计和选择脚手架工程应根据具体项目的需求进行设计和选择,包括脚手架的类型、高度、荷载等。

设计和选择应遵循相关标准和规范。

3.2脚手架的搭建和拆除脚手架的搭建和拆除应由经验丰富、熟悉相关技术规范的人员进行,并严格按照设计方案进行操作。

搭建和拆除过程中应注意安全,确保脚手架的稳定性。

3.3脚手架的维护和检查脚手架工程在使用过程中需要进行定期维护和检查,确保其安全可靠。

维护内容包括脚手架的防锈、防腐、防震、防滑等。

3.4脚手架的使用限制脚手架的使用限制应符合相关法律法规和技术标准。

禁止在脚手架上进行超负荷作业和违规操作。

四、2018广东建筑定额脚手架工程计算规则在进行脚手架工程的计算时,需要遵循以下规则:4.1荷载计算脚手架的荷载计算应根据实际需求进行,包括人员、材料、设备等荷载的计算。

4.2结构计算脚手架的结构计算应遵循相关工程力学原理和设计规范,保证结构的安全可靠。

4.3材料计算脚手架的各种材料应符合相关标准和规范,计算时应考虑材料的强度、稳定性等因素。

五、脚手架工程质量安全控制脚手架工程质量和安全控制是保证工程顺利进行的关键。

在脚手架工程中,应注意以下方面:5.1质量控制脚手架工程的搭建和拆除等操作应按照相关标准和规范执行,保证质量可靠。

广东省2018定额说明

广东省2018定额说明

广东省2018定额章节说明A.1.1 土石方工程说明一、本章定额包括土方工程、石方工程、回填方及其他,共三节。

二、一般规定1.土石方工程土壤及岩石类别的划分,依照工程勘测资料与《土壤分类表》、《岩石分类表》对照后确定。

土壤分类表注:除表中四种类别的土壤外,本章还考虑淤泥、流砂两种特殊土:1.淤泥为在静水或缓慢的流水环境中沉积,并经生物化学作用形成,其天然含水量>液限、天然孔隙比≥1.5的粘性土,外观上呈流塑状态。

2.流砂为含水饱和,因受动水压力影响而呈流动状态的细砂、微粒砂、亚砂土。

岩石分类表2.干土、湿土的划分:首先应以地质勘测资料为准,含水率<25%为干土,含水率≥25%且小于液限为湿土;或以地下常水位为准划分,地下常水位以上为干土,以下为湿土,如采用降水措施的,应以降水后的水位为地下常水位,降水措施费用应另行计算。

3.平整场地、沟槽、基坑、一般土石方划分规定:场地厚度≤±30c m的就地挖、填、运、找平为平整场地;底宽≤7m 且底长>3倍底宽为沟槽;底长≤3倍底宽且底面积≤150m2为基坑;超出上述范围则为一般土石方。

4.本章未包括现场障碍物清除、地下水位以下施工的排(降)水、边坡支护,发生时应另行计算。

5.本章土石方运输子目适用于运距在30k m以内的运输,运距超过30k m(但不超过50k m)部分按每增加1k m相应定额子目乘以系数0.65计算,运距超过50k m的按相关管理部门的规定计算,运输之外的消纳费用等其他费用未包含在定额中。

6.本章土石方运输子目是按每天8小时的运输作业时间综合考虑的,如各市对土石方场外运输有时间限制,作业时间不足8小时的可计算工效损失费,每减少1小时按土石方机械运输子目中的机具费乘以 4.2%计算。

7.推土机土、推石渣,铲运机铲运土,重车上坡时,如果坡度大于5%,其运距按坡度区段斜长乘以下表系数计算:三、土方1.土方定额子目是按干土编制的。

广东省2018定额说明

广东省2018定额说明

广东省2018定额章节说明土石方工程说明一、本章定额包括土方工程、石方工程、回填方及其他,共三节。

二、一般规定1.土石方工程土壤及岩石类别的划分,依照工程勘测资料与《土壤分类表》、《岩石分类表》对照后确定。

土壤分类表注:除表中四种类别的土壤外,本章还考虑淤泥、流砂两种特殊土:1.淤泥为在静水或缓慢的流水环境中沉积,并经生物化学作用形成,其天然含水量>液限、天然孔隙比≥的粘性土,外观上呈流塑状态。

2.流砂为含水饱和,因受动水压力影响而呈流动状态的细砂、微粒砂、亚砂土。

岩石分类表2.干土、湿土的划分:首先应以地质勘测资料为准,含水率<25%为干土,含水率≥25%且小于液限为湿土;或以地下常水位为准划分,地下常水位以上为干土,以下为湿土,如采用降水措施的,应以降水后的水位为地下常水位,降水措施费用应另行计算。

3.平整场地、沟槽、基坑、一般土石方划分规定:场地厚度≤±30c m的就地挖、填、运、找平为平整场地;底宽≤7m 且底长>3倍底宽为沟槽;底长≤3倍底宽且底面积≤150m2为基坑;超出上述范围则为一般土石方。

4.本章未包括现场障碍物清除、地下水位以下施工的排(降)水、边坡支护,发生时应另行计算。

5.本章土石方运输子目适用于运距在30k m以内的运输,运距超过30k m(但不超过50k m)部分按每增加1k m相应定额子目乘以系数计算,运距超过50k m的按相关管理部门的规定计算,运输之外的消纳费用等其他费用未包含在定额中。

6.本章土石方运输子目是按每天8小时的运输作业时间综合考虑的,如各市对土石方场外运输有时间限制,作业时间不足8小时的可计算工效损失费,每减少1小时按土石方机械运输子目中的机具费乘以%计算。

7.推土机土、推石渣,铲运机铲运土,重车上坡时,如果坡度大于5%,其运距按坡度区段斜长乘以下表系数计算:三、土方1.土方定额子目是按干土编制的。

人工挖湿土时,相应定额子目人工费乘以系数;机械挖湿土时,相应定额子目人工费、机具费乘以系数。

广东省2018综合定额(房屋建筑)

广东省2018综合定额(房屋建筑)

广东省房屋建筑与装饰工程综合定额(说明整合-ChrisL)2018执行日期:2019 年3 月1 日还有其他便捷造价工具(广东省咨询费自动计算表、个人设计工程量计算表、129个图集汇总、水泥砂浆计算表)的推荐。

总说明一、《广东省房屋建筑与装饰工程综合定额(2018)》(以下简称本综合定额)是在国家标准<建设工程工程量清单计价规范》GB50500-2013、《建设工程劳动定额》、《房屋建筑与装饰工程消耗量定额》TY01-31-2015及《广东省建设工程计价依据》(2010年)的基础上,结合我省实际,根据现行国家产品标准、设计规范和施工验收规范、质量评定标准、安全操作规程、绿色施工评价标准等编制的。

二、本综合定额适用于全省行政区域内采用绿色施工标准新建、扩建和改建的房屋建筑与装饰工程。

三、本综合定额是我省房屋建筑与装饰工程合理确定和有效控制工程造价、衡量工程造价合理性的基础,是编审设计概算、施工图预算、招标控制价、竣工结算的依据,是处理工程造价纠纷、鉴定工程造价的依据,也作为企业投标报价、加强内部管理和核算的参考。

四、本综合定额是完成单位工程量所需的人工费用、材料、机具等消耗量及管理费标准,该消耗量及费用标准是按正常的施工条件,以我省建筑企业的施工机械装备程度、合理的施工工期、采用绿色施工标准的施工工艺、劳动组织为基础综合确定的,反映了社会平均水平。

五、本综合定额由分部分项工程项目、措施项目、其他项目、税金、附录共五部分组成。

子目基价及其组项价格均不包含增值税可抵扣进项税额。

六、本综合定额按章、节、项目、子目排列,各章均有章说明、工程量计算规则,项目由工作内容和定额表格组成,有的加上必要的附注。

工作内容简单扼要地说明主要施工工序,次要施工工序虽未具体说明,但均已综合考虑在内。

七、关于人工费1.本综合定额的人工费是指直接从事施工作业的生产工人的薪酬,包括了基本用工、辅助用工、人工幅度差、现场运输及清理现场等用工费用,已经综合考虑了不同工种、不同技术等级等因素,内容包括工资性收入、社会保险费、住房公积金、工会经费、职工教育经费、职工福利费及特殊情况下支付的工资等。

广东2018建筑与装饰定额

广东2018建筑与装饰定额

广东2018建筑与装饰定额
广东省2018年建筑与装饰定额是指广东省在2018年制定的建筑和装饰工程施工定额标准。

这些定额包括了建筑和装饰工程所需的各项指标和规范,涉及到施工材料的使用、工程量的计算、施工工艺的要求等内容。

这些定额的制定旨在规范工程建设行为,保障工程质量,提高工程施工效率。

具体的定额内容可能包括建筑结构设计规范、建筑工程造价定额、建筑装饰装修工程定额等方面的内容。

这些定额的制定对于规范广东省的建筑和装饰工程施工具有重要意义,有利于提高工程质量和施工效率。

广东省2018定额说明

广东省2018定额说明

广东省2018定额章节说明A.1.1 土石方工程说明一、本章定额包括土方工程、石方工程、回填方及其他,共三节。

二、一般规定1.土石方工程土壤及岩石类别的划分,依照工程勘测资料与《土壤分类表》、《岩石分类表》对照后确定。

土壤分类表注:除表中四种类别的土壤外,本章还考虑淤泥、流砂两种特殊土:1.淤泥为在静水或缓慢的流水环境中沉积,并经生物化学作用形成,其天然含水量>液限、天然孔隙比≥1.5的粘性土,外观上呈流塑状态。

2.流砂为含水饱和,因受动水压力影响而呈流动状态的细砂、微粒砂、亚砂土。

岩石分类表2.干土、湿土的划分:首先应以地质勘测资料为准,含水率<25%为干土,含水率≥25%且小于液限为湿土;或以地下常水位为准划分,地下常水位以上为干土,以下为湿土,如采用降水措施的,应以降水后的水位为地下常水位,降水措施费用应另行计算。

3.平整场地、沟槽、基坑、一般土石方划分规定:场地厚度≤±30c m的就地挖、填、运、找平为平整场地;底宽≤7m且底长>3倍底宽为沟槽;底长≤3倍底宽且底面积≤150m2为基坑;超出上述范围则为一般土石方。

4.本章未包括现场障碍物清除、地下水位以下施工的排(降)水、边坡支护,发生时应另行计算。

5.本章土石方运输子目适用于运距在30k m以内的运输,运距超过30k m(但不超过50k m)部分按每增加1k m相应定额子目乘以系数0.65计算,运距超过50k m的按相关管理部门的规定计算,运输之外的消纳费用等其他费用未包含在定额中。

6.本章土石方运输子目是按每天8小时的运输作业时间综合考虑的,如各市对土石方场外运输有时间限制,作业时间不足8小时的可计算工效损失费,每减少1小时按土石方机械运输子目中的机具费乘以 4.2%计算。

7.推土机土、推石渣,铲运机铲运土,重车上坡时,如果坡度大于5%,其运距按坡度区段斜长乘以下表系数计算:三、土方1.土方定额子目是按干土编制的。

18序列定额章节说明

18序列定额章节说明

《xx 房屋建筑与装饰工程消耗量定额及全费用基价表总说明一、 xx 房屋建筑与装饰工程消耗量定额及全费用基价表》(2018)(以 下简称本定额)是按照国家标准《建设工程工程量清单计价规范》 (GB50500-2013)的有关要求,在全国统一《房屋建筑与装饰工程消耗 量定额》(2015 年)及《xx 房屋建筑与装饰工程消耗量定额及基价表》 (2013 年)的基础上,结合本省实际情况进行修编的。

二、本定额适用于 xx 境内工业与民用建筑的 xx 、扩建、改建工程。

三、本定额既是实行工程量清单计价时配套的消耗量定额,也是实行定额计价时的全费用基价表。

本定额是编制招标控制价、xx 预算、工程竣工结算、设计概算及投资估算的依据;是企业投标报价、 内部管理和核算的重要参考。

四、本定额以全费用表示。

全费用是完成规定计量单位的分部分项工程所需人工费、材料费、机械费、费用、增值税之和。

1.人工费、材料费、机械费是以定额编制期确定的人工、材料、机械 xx 单价和对应的定额消耗量计算的。

2.费用包括总价措施项目费、企业管理费、利润、规费。

3.增值税是在一般计税法下按规定计算的销项税。

五、本定额以国家和有关部门发布的现行设计规范、施工验收规范、技术操作规程、质量评定标准、产品标准和安全操作规程,现行工程量清单计价规范、计算规范和有关定额为依据编制。

并参考了有关地区和行业标准、定额,以及典型工程设计、施工和其他资料。

六、本定额消耗量是完成规定计量单位的合格产品所需的人工、材料、机械xx的数量标准。

是按正常施工条件,省内大多数施工企业采用的施工方法、机械化程度和合理的劳动组织及工期进行编制的,反映了社会平均消耗量水平。

七、本定额的工作内容中,已说明了主要施工工序,次要工序虽未说明,均已包含在消耗量内。

八、关于人工消耗量和价格的确定。

1.本定额的人工工日消耗量不分工种,分为xx工、技工、高级技工三个技术等级。

2.本定额的人工包括基本用工、超运距用工、辅助用工和人工幅度差。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

省2018定额章节说明A.1.1 土石方工程说明一、本章定额包括土方工程、石方工程、回填方及其他,共三节。

二、一般规定1.土石方工程土壤及岩石类别的划分,依照工程勘测资料与《土壤分类表》、《岩石分类表》对照后确定。

土壤分类表注:除表中四种类别的土壤外,本章还考虑淤泥、流砂两种特殊土:1.淤泥为在静水或缓慢的流水环境中沉积,并经生物化学作用形成,其天然含水量>液限、天然孔隙比≥1.5的粘性土,外观上呈流塑状态。

2.流砂为含水饱和,因受动水压力影响而呈流动状态的细砂、微粒砂、亚砂土。

岩石分类表2.干土、湿土的划分:首先应以地质勘测资料为准,含水率<25%为干土,含水率≥25%且小于液限为湿土;或以地下常水位为准划分,地下常水位以上为干土,以下为湿土,如采用降水措施的,应以降水后的水位为地下常水位,降水措施费用应另行计算。

3.平整场地、沟槽、基坑、一般土石方划分规定:场地厚度≤±30c m的就地挖、填、运、找平为平整场地;底宽≤7m 且底长>3倍底宽为沟槽;底长≤3倍底宽且底面积≤150m2为基坑;超出上述围则为一般土石方。

4.本章未包括现场障碍物清除、地下水位以下施工的排(降)水、边坡支护,发生时应另行计算。

5.本章土石方运输子目适用于运距在30k m以的运输,运距超过30k m(但不超过50k m)部分按每增加1k m相应定额子目乘以系数0.65计算,运距超过50k m的按相关管理部门的规定计算,运输之外的消纳费用等其他费用未包含在定额中。

6.本章土石方运输子目是按每天8小时的运输作业时间综合考虑的,如各市对土石方场外运输有时间限制,作业时间不足8小时的可计算工效损失费,每减少1小时按土石方机械运输子目中的机具费乘以 4.2%计算。

7.推土机土、推石渣,铲运机铲运土,重车上坡时,如果坡度大于5%,其运距按坡度区段斜长乘以下表系数计算:三、土方1.土方定额子目是按干土编制的。

人工挖湿土时,相应定额子目人工费乘以系数 1.18;机械挖湿土时,相应定额子目人工费、机具费乘以系数 1.10。

2.桩间土不扣除桩芯直径60c m以或类似尺寸桩体所占体积。

人工挖桩间土方,相应定额子目人工费乘以系数 1.30;机械挖桩间土方,相应定额子目人工费、机具费乘以系数1.10。

3.在挡土板支撑下人工挖沟槽、基坑土方时,相应定额子目人工费乘以系数 1.20。

4.挖掘机在垫板上进行作业,相应定额子目的人工费、机具费乘以系数 1.25,搭拆垫板的费用另行计算。

5.推土机推土、铲运机铲土的平均土层厚度小于30c m时,推土机台班消耗量乘以 1.25,铲运机台班消耗量乘以系数1.17。

6.机械挖土方需人工辅助开挖时,按施工组织设计的规定分别计算机械、人工挖土工程量,如施工组织设计无规定的,按机械挖土方95%、人工挖土方5%计算。

7.淤泥、流砂运输定额按即挖即运考虑。

对没有即时运走的,经晾晒后的淤泥、流砂按装运土方子目计算。

8.地下室土方大开挖后再挖地槽、地坑,其深度按大开挖后土面至槽、坑底标高计算,加垂直运输和水平运输。

四、石方1.石方爆破子目是按炮眼法松动爆破编制的,不分明炮、闷炮,但闷炮的覆盖材料(除石方控制爆破子目外)另行计算。

2.定额中的爆破子目是按炮孔中无地下渗水、积水编制的,炮孔中若出现地下渗水、积水时,其处理费用另行计算。

3.定额中的爆破子目(石方控制爆破子目除外)未计爆破所需覆盖的安全设施、架设安全屏障等,发生时另行计算。

五、支挡土板定额子目分为密板和疏板,密板是指满支挡土板,板距不大于30c m;疏板是指间隔支挡土板,板距不大于150c m,实际间距不同时,不作调整。

六、盖挖法1.盖挖法挖土方,按室实际净面积乘以挖土方深度以体积计算。

2.全部采用人工开挖土方时,按人工挖土方相应项目的人工费乘以系数 1.80。

机械开挖土方为主、人工开挖土方为辅时,人工挖土方按相应项目的人工费乘以系数 1.60;机械挖土方按相应项目的人工费、机具费乘以系数 1.30。

机械挖土方人工配合挖土时,有施工组织设计规定时,按规定计算。

施工组织设计无规定时,机械挖土方按总土方量的95%计算,人工挖土方按总土方量的5%计算。

3.以上系数未考虑洞、暗室施工及土方的垂直提土运输、水平运输。

工程量计算规则一、一般计算规则(一)本章土石方的挖、推、铲、装、运体积均以天然密实度体积计算,回填方按设计的回填体积计算。

不同状态的土石方体积,按土石方体积换算系数表相关系数换算。

土石方体积换算系数表(二)挖土方工程量,按设计图示尺寸(包括基础工作面、放坡)以“m3”计算。

设计或经批准的施工组织设计(当设计未明确时)对基础施工工作面、放坡没有明确规定的,分别按下表(表一、表二)取定。

表一:基础施工所需工作面宽度计算表注:1、表中基础材料多个并存时,工作面宽度按其中规定的最大宽度计算。

2、挖基础土方需支挡土板时.按槽、坑底宽每侧另增加工作面100m m。

3、砖胎模不计工作面。

表二:放坡系数表注:1、基础土方支挡土板时,不得计算放坡。

2、计算放坡时,在交接处的重复工程量不予扣除。

3、基础土方含不同类别的土壤时,其放坡的起点深度和放坡坡度,按不同土方类别厚度加权平均计算。

4、基础垫层不做模板时,放坡自垫层上表面开始计算;基础垫层有模板时,放坡自垫层底面开始计算。

1.土方开挖平均厚度应按自然地面测量标高至设计地坪标高间的平均厚度确定。

基础土方开挖深度,应按基础(含垫层)底标高至交付施工场地标高确定,无交付施工场地标高时,应按自然地面标高或设计室外地坪标高确定。

2.土方开挖宽度,按基础垫层底宽度加工作面宽度确定。

3.挖沟槽土方长度按下列情况确定:外墙沟槽按设计图示中心线长度计算;墙沟槽按图示基础底面之间净长线(即基础垫层底之间净长度)计算;外突出部分(垛、附墙烟囱等)体积并入沟槽土方工程量计算。

(三)土石方运输工程量,按挖、填土方结合施工组织设计按实以“m3”计算。

土石方运输距离按施工组织设计以挖方区重心至填土区重心或弃土区重心之间最短运输距离确定。

1.铲运机铲运土运距,按挖方区重心至卸方区重心加转向距离45m计算;2.采用人力垂直运土石方运距折合水平运距7倍计算。

二、土方工程(一)平整场地、原土打夯1.平整场地工程量按设计图示尺寸以建筑物按首层外墙外边线面积(没有围护结构时以首层结构外围投影面积)计算,包括落地阳台、地下室出入口、采光井和通风竖井所占面积。

建筑物地下室结构外边线突出首层结构外边线时,其突出部分的面积合并计算。

2.原土打夯、碾压工程量按设计图示尺寸以“m2”计算。

(二)人工土方人工挖一般土方、人工挖淤泥流砂、人工挖沟槽土方、人工挖基坑土方工程量按设计图示尺寸(包括基础工作面、放坡)以“m3”计算。

(三)机械土方挖掘机挖一般土方、挖掘机挖淤泥流砂、挖掘机挖沟槽、基坑土方、挖掘机挖装土方、挖掘机挖装淤泥流砂工程量按设计图示尺寸(包括基础工作面、放坡)以“m3”计算。

三、石方工程开凿、破碎、爆破石方工程量按设计图示尺寸以“m3”计算,允许超挖量并入岩石挖方量计算。

平基、沟槽、基坑开凿或爆破岩石,其开凿和爆破宽度及深度允许超挖量为:较软岩和较硬岩为200m m、坚硬岩为150m m。

四、回填方及其他(一)回填土石方工程量按设计图示尺寸以“m3”计算,其中:1.场地回填:按回填面积乘以平均回填厚度以“m3”计算;2.室回填:按主墙间净面积乘以回填厚度以“m3”计算;3.基础回填工程量区分以下两种情况分别计算:(1)交付施工场地标高高于设计室外地坪时,按设计室外地坪以下挖方体积减去埋设的基础体积以“m3”计算(包括基础垫层及其他构筑物);(2)交付施工场地标高低于设计室外地坪时,按高差填方体积与挖方体积之和减去埋设基础体积(包括基础垫层及其他构筑物)以“m3”计算。

4.余(取)土工程量按公式计算:余(取)土体积=挖土总体积-回填土总体积,公式中回填土总体积应折算为天然密实体积,计算结果为正值时为余土外运体积,负值时为需取土体积。

(二)支挡土板工程量按槽、坑垂直支撑面以“m2”计算。

A.1.2 围护及支护工程说明一、本章定额包括打拔钢板桩、高压旋喷桩、深层搅拌桩、地下连续墙、锚杆土钉、高压定喷防渗墙、大型钢支撑安拆、喷射混凝土,共八节。

二、打拔钢板桩1.打拔钢板桩土质类别按综合土类考虑。

2.打拔槽型钢板桩子目已包含支撑安拆,打拔拉森钢板桩子目均不包含支撑安拆。

3.沟槽和基坑按土石方工程章说明中的规定划分。

4.打拔钢板桩子目已包含了30天、60天、180天摊销使用期,非施工方原因导致实际支护时间(经验收合格之日起计算)超出摊销使用期,可按下表调整:5.如实际的打拔钢板桩机械与定额所含的机械有不同时,不作换算;当实际支护或支撑的型钢种类不同时可按实换算,但消耗量不变。

三、高压旋喷桩1.高压旋喷桩定额已综合接头处的复喷工料,单位长度设计水泥用量不同时可以换算。

2.桩上部空孔部分套用空桩子目计算。

3.本章打桩工程除高压水平旋喷桩外,均按打直桩编制,设计要求打斜桩时,斜率小于1:6时,相应定额人工费、机具费乘以系数 1.25;斜率大于1:6时,相应定额人工费、机具费乘以系数 1.43。

四、喷浆(粉)桩(深层搅拌桩)1.深层搅拌水泥桩项目按一喷二搅或二喷二搅施工综合考虑编制,实际施工为二喷四搅或四喷四搅时,定额人工费和机具费乘以系数 1.43计算。

2.深层搅拌水泥桩定额水泥损耗率按4%考虑,如设计水泥投放量与定额用量不同,根据设计要求进行调整。

3.深层搅拌水泥桩定额已综合了正常施工工艺需要的重复喷浆(粉)和搅拌。

4.S M W工法搅拌桩水泥掺入量按加固土重(1800k g/m3)的20%考虑,如设计不同时按实调整;定额子目按2喷2搅施工编制,设计不同时,每增(减)1搅1喷按相应子目人工费和机具费增(减)40%计算。

空搅部分按相应定额的人工费和机具费乘以系数0.50计算,并扣除水泥和水的含量。

5.S M W工法搅拌桩设计要求全断面套打时,相应子目的人工费及机具费乘以系数 1.50,其余不变。

五、地下连续墙1.本节定额包括成槽、钢筋网片制作吊装、地下连续墙工字形钢板封口、入岩增加费、锁口管吊拔、浇捣连续墙混凝土等容。

2.本节成槽子目是以连续墙厚80c m编制,当墙厚为60c m 时,子目乘以系数 1.10,当墙厚为100c m时,子目乘以系数0.95计算。

3.如有发生导墙修筑时,导墙土方开挖可套用土石方中的沟槽开挖定额子目;导墙模板套用“独立基础模板”子目、导墙浇捣套用“其他混凝土基础”子目、制安钢筋套用A.1.5.5节中的的定额子目;如在实际中导墙需要拆除时,可套“拆除工程”相应子目。

4.地下连续墙成槽的泥浆池砌筑和拆除可根据设计或施工方案套用“砌筑工程”和“拆除工程”的相应子目在措施费中计列,竣工结算时应按实结算。