ABC成本分析法

相关主题
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

Designing an ABC System
Cost Objects (e.g., products and customers)
19
Activities
Consumption of Resources
Cost
Designing an ABC System
Steps for Implementing ABC
1
Activity-Based Costing
Evolution of ABC
Conventional costing systems use a two-
2
stage allocation process: 1. service department costs are allocated to production departments. 2. production department overhead costs are allocated to products using a volume-based predetermined overhead rate.
Activity Based Costing Departmental Overhead Rates
Plantwide Overhead Rate
17
Overhead Allocation
Activity-based costing
is a way of measuring both the cost of
The Key Question: Does the amount of the activity cost pool increase with the number of units produced?
Output Unit-Level Costs...
are resources sacrificed on activities
22
performed on each individual unit of product or service e.g.
Energy used by machines Machine depreciation or repairs
20
Identifying and Defining Activities 21
Unit-Level Activities Batch-Level Activities
An ACTIVITY is a part of the production process for which management wants a separate reporting of costs. Product-sustaining Activities Facility-sustaining Activities
Departmental Overhead Rates
Indirect Labor Indirect Materials Other Overhead
6
Stage One: Costs assigned to pools Cost pools
Department 1
Department 2
Department 3
Erosion of company profits
Price cuts produce increased sales in
11
units but decreased total revenue High mark-ups on specialty products didn’t offset the fall in profit margins of high volume products
Departmental Overhead Rates
Indirect Labor
Indirect Materials
7
Stage One: Costs assigned to pools Cost pools Stage Two: Costs applied to products
Other Overhead
Questionable profit margins
To compete in the marketplace, some
10
companies have had to cut the prices of high volume popular items. But They have been able to achieve high mark-ups on low volume specialty products.
Activity Based Costing (ABC)
The objective of activity-based costing is to understand the causes of overhead costs and to identify the real profitability of products and customers.
4
Departmental Overhead Rates
5
wk.baidu.com
Finishing Department Painting Department
Shipping Department
A two stage process is necessary because costs are allocated to departments and then to products.
Plantwide Overhead Rates
Companies have tended to use direct labour as the overhead application base.
However direct labour is now a relatively minor part of total manufacturing cost. Many tasks that used to be done by hand are now done by automated equipment.
Department 1
Direct Labour Hours
Department 2
Machine Hours
Department 3
Raw Materials Cost
Products
Departmental Allocation Bases
Cost Distortions caused by 2-stage allocations
ABC is a good supplement to our traditional cost system
15
I agree!
Activity Based Costing (ABC)
Activity-Based Costing
16
There are a number Both manufacturing of cost pools, each of and nonmanufacturing which is allocated costs may be using a unique assigned to measure of activity. products. Some manufacturing costs may be excluded from product costs.
1. Identify and define activities and activity pools. 2. Where possible, directly trace costs to activities and cost objects. 3. Assign costs to activity cost pools. 4. Calculate activity rates. 5. Assign costs to cost objects. 6. Prepare management reports.
Product costs don’t make sense
Problem: There may be no relationship
3
between the overhead application base and the way that different products cause overhead costs The result: High-volume simple products are overcosted and over-priced Low-volume complex products are under-costed and under-priced
Solution: Activity Based Costing
ABC uses cost drivers that directly link
13
activities performed to products made. cost drivers are selected which measure the average demand placed on each activity by each product. activity cost pools are assigned to products in proportion to the way that they consume each activity.
Causes of problems
Increased product diversity changing cost structures
12
use of volume-based cost drivers
Have resulted in:
distorted product costs
Allocation bases often differ from traditional costing systems. Overhead rates may be based on activity at capacity.
How Costs are Treated Under Activity-Based Costing
Solution: Activity Based Costing
ACTIVITIES CONSUME RESOURCES PRODUCTS CONSUME ACTIVITIES
14
Activities are used to link resource costs
to products
18
cost objects and the performance of activities can help solve problems such as distorted product costs poor cost control the form of ABC adopted depends on the problems that need to be addressed
Department 1
Department 2
Department 3
Products
Departmental Overhead Rates
Indirect Labor Indirect Materials Other Overhead
8
Stage One: Costs assigned to pools Cost pools Stage Two: Costs applied to products
There is a no link between the cause of
9
support activity costs and the basis for assigning these costs to products Why? 1. Allocations are based on unit or volume related measures. 2. Different products consume different amounts of support activities.
相关文档
最新文档