自动化专业英语论文(附译文)(华北电力大学)

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

分数: ___________

任课教师签字:___________ 华北电力大学本科生结课作业

学年学期:2011-2012学年第二学期

课程名称:专业外语阅读(自动化)

学生姓名:

学号:

提交时间:2012年6月19 日

The Major Component Assembly Line of an

Aircraft

Every Boeing commercial is airplane is customized for a specific customer. Manufacturing processes of some major component are desirable to follow the FMS concept in a customized manufacturing environment. In the case study that follows,a wing assembly process is examined by means of discrete simulation modeling. There are more than thirty complex processes applied to more than fifteen machine classes in this example .Most processes require a different number of labor entities from various labor classes.The overall pace of the whole system is desired to be a variable that impacts the process time of all related processes,as well as the number of assigned laborers.The modular approach to MCM system design not only benefits the overall performance of flexible MCMsystem,but also enhances simulation-modeling exercises.

Discrete event simulation technology in this study employs the same platform concept as in modeling highly flexible and rapid reconfigurable production lines.such modeling methods reflect manufacturing processes according to the every-changing customized demands.Many fundamental manufacturing process parameters,such as layout reconfigurations, and resource re-allocations, can be derived ahead of time from the simulation models.

A high-level process flow of this simulation model is shown below in Figure 5-4-1, where sourcel1 generates incoming parts according to the system takt time with optional statistical distributions. Buffer S receives incoming parts via the only crane resource in the system. The part will then be lifted by the crane to the machine

B where multiple processes will be performed by multiple resources. The part then continues to move from the machine B to the machine P, the end of the process line. Multiple processes are assigned throughout this line on each machine. An additional process is needed in the middle of the line where the part will be transferred to the buffer A followed by a couple of external processes. Afterwards, buffer A receives the part and calls for the overhead crane to transfer the part back to buffer T where the part will continue through the rest of the process. At the end of the line, the part goes from the machine P to the buffer A then to the sink, which is the final destination of all parts in the simulation model.

Two different part-carrying platforms are involved in the system. The “high

相关文档
最新文档