人行通道施工组织设计
地下人行通道 施工方案

目录一、工程概况1二、工程数量1三、编制依据1四、施工进度计划2五、施工准备21.技术准备22.人员配置23.机械设备配置44.材料准备4六、通道施工方案5(一)总体施工方案5(二)施工工艺5(三)施工方法61.基坑开挖62.碎石垫层63.混凝土垫层64.箱涵底板及部分墙身:65.墙身及顶板施工97.箱涵附属(泵房、人行梯道、涵内通道)118.沉降缝填塞119.台背台顶防水及台背回填11七、质量保证措施121、组织保证措施122、技术保证措施123、防止质量通病的措施13八、环境保护措施15九、安全保证措施15十、文明施工17(一)文明施工管理措施17(二)文明施工技术措施18地下人行通道施工方案一、工程概况罗田收费站地下通道供收费广场收费人员进出收费亭使用,共设置3处,分别位于YK23+410(右幅)、LK0+100(左幅)、ZK24+242(左幅)处。
通道采用1-3mX3.2m 闭合框架式结构(箱型通道),通道为供收费广场收费人员进出收费亭使用,故设置下行梯道进出通道,每个岛均设置。
通道排水沟设在人行道板下,YK23+410通道采用自然排水,通过涵管排到边坡,LK0+100及ZK24+242通道在低端设置泵站。
二、工程数量通道主要工程数量见下表三、编制依据(1)合同文件、交通部现行施工技术规范、工程质量检验评定标准、规则、规程。
业主交付的两阶段施工图设计及其它设计文件。
(2)现场踏勘、调查的结果及合同要求的工期要求。
(3)结合项目部现有的施工技术水平、施工机械(具)设备,综合比较后选定施工方案,力求做到管理人员、劳动力及材料供应满足施工方法和进度要求,机械设备匹配合理,努力提高机械化程度,持续加快施工进度。
(4)保证安全、质量、环保、工期的措施切实可行、可靠。
(5)相关法律、法规对水土保持、环境保护、安全管理的规定。
(6)罗田收费站施工组织设计。
四、施工进度计划结合总体施工工期和施工节点安排,通道结构物施工计划安排,计划开始、完工时间:2017年1月15日至2017年9月27日。
人行道工程施工方案(3篇)

第1篇一、工程概况本项目位于XX市XX区,主要内容包括人行道铺设、绿化带建设、照明设施安装等。
工程总长度为XX米,宽度为XX米,总面积为XX平方米。
施工期限为XX个月,确保在规定时间内高质量完成工程。
二、施工准备1. 组织准备- 组建施工团队,明确项目经理、技术负责人、安全员等岗位责任。
- 对施工人员进行岗前培训,确保其熟悉施工图纸、操作规程和安全注意事项。
2. 材料准备- 人行道砖:根据设计要求选择合适规格的砖材,确保质量合格。
- 沥青混凝土:选择符合国家标准的高强度沥青混凝土。
- 绿化材料:选择适宜的植物种类,确保成活率。
- 照明设施:选用节能、安全的照明设备。
3. 机械设备准备- 摊铺机、压路机、切割机等设备,确保施工过程中顺利进行。
4. 施工场地准备- 清理施工场地,确保场地平整、排水畅通。
- 设置安全警示标志,保障施工安全。
三、施工工艺1. 基础处理- 对原有路面进行清理,确保无杂草、杂物。
- 按设计要求进行地基处理,确保地基坚实、稳定。
2. 人行道铺设- 按照施工图纸进行放样,确定人行道边线。
- 铺设人行道砖,注意砖面平整、缝隙均匀。
- 对铺设完毕的人行道进行压实,确保稳固。
3. 绿化带建设- 根据设计要求进行绿化带规划,确保植物种类、布局合理。
- 挖掘绿化带,确保土壤疏松、排水良好。
- 种植植物,并进行浇水、施肥等养护工作。
4. 照明设施安装- 按照设计要求进行照明设施安装,确保灯光亮度和均匀性。
- 对照明设施进行调试,确保其正常运行。
四、质量控制1. 材料质量- 严格筛选材料,确保符合国家标准。
- 对进场材料进行验收,确保质量合格。
2. 施工质量- 严格按照施工规范进行施工,确保工程质量。
- 定期对施工过程进行监督检查,及时发现并解决问题。
3. 安全质量- 严格执行安全操作规程,确保施工安全。
- 加强安全教育培训,提高施工人员安全意识。
五、进度安排1. 基础处理:XX天2. 人行道铺设:XX天3. 绿化带建设:XX天4. 照明设施安装:XX天5. 验收:XX天六、施工总结工程完成后,对施工过程进行总结,分析施工中存在的问题,为今后类似工程提供借鉴。
施工现场上下人通道搭设方案

目录一、编制依据 (1)二、工程概况 (1)三、施工任务 (1)四、施工准备 (2)五、施工工艺流程 (3)六、施工方法 (3)七、安全文明施工 (5)一、编制依据《建筑施工高处作业安全技术规范》(JGJ80-91);本工程施工组织设计;《建筑施工脚手架实用手册》;业主提供的施工图纸;《建筑结构荷载规范》;《建筑工程施工质量验收统一标准》;《建筑施工手册》第四版;二、工程概况变电站附属设施工程楼,工程建设单位为公司,工程位于侧,性质为变电设施的附属建筑。
工程用地东侧为,西侧为附属设施工程1#楼,南侧为绿化用地,景观较好。
本工程建成后作为停车楼使用(开敞、错层式);总停车数量:电力检修车45,小型车(微型车)285,合计330辆;本工程结构形式为钢框架结构,建筑结构的类别为丙类;设计使用年限为50年,抗震设防烈度8度。
建筑面积10088m²,其中停车楼面积9998㎡,连廊面积90㎡,2#楼地上5层,耐火等级Ⅱ级。
砼屋面防水等级为Ⅱ级,钢结构屋面防水等级为Ⅱ级。
本工程±0.00标高相当于绝对标高42.75米,室内外高差0.15米。
三、施工任务为更好组织不同结构层之间的竖向交通,方便施工,本工程考虑在草桥变电站附属设施工程2#南侧附近搭设“之字”形临时马道一座,具体搭设位置见下图:四、施工准备4.1 技术准备4.1.1 熟悉本施工方案。
4.1.2 施工人员用工手续齐全,架子工必须持特殊工种上岗操作证及培训证书。
4.1.3 进行逐级技术交底:专业工长以书面形式向各班组进行交底,班组长再向工人进行交底,交底要有针对性,要针对关键部位提出具体安全措施和技术要求。
技术交底要有符合性和实用性,既要符合规范、标准的要求,又要符合施工现场实际情况,便于操作,便于贯彻执行。
技术交底内容一定要便于操作者易懂易通。
4.2 材料准备4.2.1 本工程采用扣件式钢管脚手架,须准备:Φ48壁厚3.5的钢管,接点用十字扣、回转扣和筒扣以及相应的螺栓、铅丝等;脚手板、垫木、安全网、密目网和安全带。
人行道工程施工方案(1)

人行道工程施工方案(1)
一、前言
随着城市化进程的不断加快,人行道的建设越发重要,保障行人的安全和方便。
因此,本文将探讨人行道工程的施工方案,以确保工程质量和安全。
二、施工前准备
2.1 环境调查
在施工前,需要进行现场环境调查,了解地形地貌、交通情况等情况,为后续
施工做好准备。
2.2 资源调配
确保施工所需人力、物力、材料齐备,保证施工的顺利进行。
2.3 设计审查
对人行道工程设计进行审查,确保施工符合设计要求,减少后期变更的可能性。
三、施工过程
3.1 地面准备
清理施工区域,确保地面平整,并进行必要的地基处理,为人行道的铺设做好
准备。
3.2 铺设人行道
根据设计要求,进行人行道的铺设工作,确保铺设的平整、牢固,提高行人的
通行舒适度。
3.3 设施安装
在人行道上安装必要的设施,如路灯、座椅等,提升人行道的实用性和舒适度。
四、质量控制
4.1 工艺控制
严格按照施工工艺进行操作,确保每个环节符合标准要求,避免施工质量问题。
4.2 质量检验
定期对施工过程进行质量检验,及时发现问题并进行整改,确保施工质量达标。
五、安全措施
5.1 安全防护
设置施工区域的安全警示标识,为施工人员和路人提供安全保障。
5.2 现场管理
严格管理施工现场,确保施工过程中的安全,避免事故的发生。
结语
通过上述施工方案,可以有效地提高人行道工程的施工质量和安全水平,为城
市交通发展和市民出行提供更好的保障。
市政人行道铺装工程施工组织设计方案

市政人行道铺装工程施工组织设计方案第一章编制说明、依据及目标承诺第一节编制说明本工程**XX人行道铺装工程,通过认真阅读和研究了招标文件、设计图纸、施工现场,结合自身情况,进行反复研讨,充分吸收各方的意见建议,我公司编制了本工程的施工组织设计,施工组织设计中涵盖了招标文件中所包括的全部工程内容。
根据本工程的特点,结合本工程的施工难点,并充分考虑到本工程的重要性,在本施工组织设计的方案中,重点介绍了人行道拆除、人行道基础、花砖铺装工程的施工方案、合理化建议、通病的防治措施;详细阐述了施工组织保证、劳动力安排、机械设备的投入计划,以及工程质量、安全生产与文明施工及总体协调管理的各种措施,同时对工程回访和维修服务等方面作出了承诺。
我公司能荣幸中标承建本工程,将委派具有丰富的工程施工、组织、管理经验的团队担任本工程项目管理班子,在施工过程中,公司相关部门对现场工作进行跟踪考核,以确保本工程施工的管理水平。
为确保实行“建一项工程,树一座丰碑”的战略目标,严格依照 ISO9001 质量体系、ISO14001 环境管理体系、GB/T28001 职业健康安全管理体系的控制程序进行组织管理,使项目受控于公司内部体系标准。
第二节编制依据1、本工程招标文件;2、本工程工程量清单、说明;3、《城市道路路面、路基及其他设施》;4、《中华人民共和国工程建设标准强制性条文》;5、《现行施工规范大全》相关部分;6、《城镇道路工程施工与质量验收标准》;7、《建筑施工安全检查标准、实施细则》8、《施工现场安全生产文明施工管理办法》;9、现行各相关技术标准、规程和规定、通知;10、我公司的《程序文件》及规章制度;11、其他国家和地方有关建筑行业的有关法律、法规、政策、规范、制度等。
第三节目标承诺1. 工程质量目标:符合国家质量验收标准。
验收合格,争创优质工程。
2. 工程进度目标:响应招标文件要求,确保按期完成本工程。
3. 安全生产、文明施工管理目标:力争达到市级安全生产、文明施工标化工地标准,确保安全生产无事故。
人行通道闸基础工程施工(3篇)

第1篇一、施工准备1. 工程勘察:在施工前,对施工现场进行详细勘察,了解地质条件、地下管线分布、周围环境等因素,为后续施工提供依据。
2. 施工方案编制:根据勘察结果,编制详细的施工方案,明确施工顺序、施工方法、施工材料、施工设备等。
3. 施工队伍组织:组建专业的施工队伍,包括施工管理人员、技术人员、施工人员等,确保施工顺利进行。
4. 材料设备准备:准备施工所需的材料,如钢筋、混凝土、模板、防水材料等,确保材料质量符合规范要求。
二、施工过程1. 基坑开挖:根据设计要求,进行基坑开挖,确保基坑尺寸满足基础施工需求。
同时,对开挖过程中发现的地下管线进行保护。
2. 基坑支护:根据地质条件和施工要求,选择合适的基坑支护方式,如桩基础、地下连续墙等,确保基坑稳定性。
3. 钢筋绑扎:按照设计图纸要求,进行钢筋绑扎。
确保钢筋间距、锚固长度、保护层厚度等符合规范要求。
4. 模板安装:根据设计图纸和施工要求,安装模板。
模板应牢固、平整,确保混凝土浇筑质量。
5. 混凝土浇筑:混凝土浇筑前,对模板、钢筋进行检查,确保符合要求。
混凝土浇筑过程中,控制浇筑速度和振捣频率,确保混凝土密实。
6. 防水施工:在混凝土浇筑完成后,进行防水施工。
根据设计要求,选择合适的防水材料和施工方法,确保防水效果。
7. 基础养护:混凝土浇筑完成后,进行养护。
养护期间,保持混凝土湿润,防止裂缝产生。
8. 基础验收:基础施工完成后,进行验收。
验收合格后,进行下一道工序施工。
三、质量控制1. 材料质量:确保施工材料质量符合规范要求,对进场材料进行严格检验。
2. 施工过程:严格按照施工方案进行施工,确保施工质量。
3. 检测与验收:对施工过程中的关键工序进行检测,确保质量符合要求。
4. 施工记录:详细记录施工过程中的各项数据,为后续工程提供依据。
四、施工安全1. 安全教育培训:对施工人员进行安全教育培训,提高安全意识。
2. 施工现场管理:加强施工现场管理,确保施工安全。
江东门地下人行过街通道工程施工组织设计

2.1 工程概况 ·························································································11
2.2 工程地质及水文地质条件····································································12 2.2.1 工程地质条件·············································································12 2.2.2 水文地质条件·············································································14 2.2.3 不良地质现象及特殊岩土条件 ·······················································14 2.2.4 工程特点···················································································14 2.2.5 施工重难点及针对措施·································································15
ZKD850-3 ·························· 1
4.3.2.9 涂刷减摩剂。············································································4 4.3.2.10 H 型钢回收············································································4 4.3.3 工程技术质量控制制度···································································5 4.3.3.1 技术控制措施·········································································5 4.3.3.2 施工质量控制措施······································································5 4.3.4 安全文明施工保证措施···································································7 4.3.4.1 施工安全技术措施:···································································7 4.3.4.2 文明施工保证措施。···································································8
施工组织设计方案(自动扶梯、人行道)

电梯安装施工组织设计方案(自动扶梯、自动人行道)用户名称:施工地址:方案编制人:年月日方案审批人:年月日项目负责人:年月日-------------------------------------------------------------------**电梯股份有限公司说明本施工方案根据双方签订的《安装合同》约定项目及要求,引用如下相关标准制定:1:电梯制造与安装安全规范:GB7588-2003 ;2:电梯工程施工质量验收规范:GB50310-2002 ;3:电梯监督检验和定期检验规则(液压电梯):SGT7004-2012 ;4:自动扶梯和自动人行道制造与安装安全规范:GB16899-2011 ;5:电梯监督检验和定期检验规则(消防员电梯):TSGT7002-2011 ;6:电梯监督检验和定期检验规则(曳引与强制驱动电梯):TSGT7001-2009 ;7:杂物电梯制造与安装安全规范:GB25194-2010 ;8:家用电梯制造与安装安全规范:GB/T21739-2008 .目录目录 (3)一、工程概况…………………………………………………………4~5二、施工组织管理及施工设备计划 (5)三、现场安全及文明施工措施……………………………………… 5~6四、对工期的保证措施………………………………………………6~7五、施工各阶段用户及相关施工队配合的要求 (7)六、施工技术标准,质量检验标准及工程质量保证措施………… 7~8七、主要施工方法、计划和流程…………………………………… 8~11八、运输、吊装、搭棚计划……………………………………… 12~13九、自动扶梯、人行道调试、检验作业流程…………………… 13~14十、供需双方约定事项备忘录 (15)十一、现场施工管理及作业人员情况明细表 (16)十二、安装施工进度计划(扶梯/人行道) (17)一、工程概况1、本工程共有自动扶梯(人行道)台(见下表),□安装、□改造、□维修工程全部由 **电梯股份有限公司2、对此工程我司将投入一定的工程管理人员(负责工程协调,工程技术及施工质量、施工现场安全管理等工作),保证工程的施工质量及工期。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
本施工组织设计得编制就是在深刻领会得工程招标书得技术要求与设计图纸得意图,结合本公司多年施工大型建筑工程得经验与教训,从公司现有技术装备、人力资源出发,对项目部得组成、施工部署、计划安排、主要施工方法得确定、技术措施得规定、机械设备与周转材料得投入等方面得工程施工方案。力求具体实际、规划合理,措施得当,在施工中具有较强得可操作性与过程控制作用,确保本工程能如期保质得完成。
(6)混凝土结构工程施工质量验收规范(0B50204)
(7)混凝土质量控制标准(GB50164)
(8)建筑工程施工质量验收统一标准(6B50300)
(9)地下工程防水技术规范(CB50108)
6.重庆市有关建筑施工技术、质量、安全等得规程与规定。
7.本公司长期从事类似工程施工所积累得技术经验,管理制度与办法。
A.在项目技术负责人得领导下,负责施工技术管理工作,接受公司工程部得监督与指导。参加项目经理组织得每月二次质量、安全与文明施工得检查评比。
B.负责图纸会审、施工组织设计,特殊关键工序得施工方法及技术措施、施工技术交底、安全技术交底、成品得半成品保护措施得编制。
C.负责新技术、新工艺、新材料得推广应用,参加新材料、特殊物资、大型机械设备得进货验收。
D.负责项目质量计划得编制、隐蔽验收、中间验收与竣工验收工作。
E.参加对不合格项评审、处置、监督纠正与预防措施得实施。
F.负责施工预算,施工图纸、技术资料、文件与质量记录以及标准化工作得管理、竣工文件编制。
G.负责计量管理与工程材料、半成品得检验与试验得控制。
H、协助项目经理做好大型项目得第二级技术交底与安全交底。
C.负责贯彻技术交底、安全交底与质量、安全以及文明施工措施并组织实施,管生产必须管安全。
D.主持或参与工程质量、施工安全与文明施工过程中出现不合格项得评审,对不合格品得处理与按规定实施工纠正及项防措施。
E.负责监督,检查施工过程得检验与试验及工程质量记录。
F.负责组织对成品、半成品得保护工作。
2.2技术组
D.参加对施工机械、脚手架得护收并实施监督,先验收后使用。
2.4材料机械组
A.负责物资采购、验收、运输、储存、保管与工程材料进货取样送试验室做材质检验。
B.负责对物资供应商得考察与选择,建立与合格供应商得联系,确保从合格供应商处采购物资,按设计图纸与招标书要求得牌号采购,保证物资得按时供货与质量符合要求。
工程项目部设技术负责人兼项目主管工程师负责技术质量管理与安全技术措施得编制。
2.项目部分工职责
2.1生产组
A.在项目经理领导下负责生产指挥、调度、根据项目总进度计划编制月、旬施工作业计划,经审批后负责贯彻实施,按月、旬提出材料、设备、工具供应计划与劳动力调整计划。
B.负责生产安排、生产过程控制及项目内得资源调度、负责联系协调各专业工程(包括甲方分负项目)穿插得配合与作业调节器整,确保按计划实施。
项目部管理机构见附表
二、工程项目部及项目负责人
1.工程项目负责人具有项目经理资质,曾组织过类似工程得施工、有丰富得施工经验,较强得组织协调能力与与业主、监理等单位得沟通能力,全面负责本项目得管理工作。
工程项目部设生产负责人,负责整个工程得生产与计划,调度与施工过程得协调工作,监督、控制各施工工长对施工组织管理与安全管理。
2.国家现行得有关施工及验收规范,质量评定标准与有关操作规程,主要包括:
(1)工程测量规范(CB50026)
(2)城市人行天桥与办日人行地道技术规范(CJJ 69-95)
(3)钢筋混凝土用热轧带肋钢筋(GB1449-1)
(4)钢筋混凝土热轧光圆钢筋(GB13013-91)
(5)地基与基础工程施工及验收规范(GB50202)
4#人行地下通道施工组织设计方案
第一章工程概况
1、通道概况
本工程位于606#路口东侧K4+850人行地下通道,长39M,宽4、5M。
2、工程地质
场地地表西高东低,北高南低,属低山地貌,、
人行通道结构主要位于杂填土(砾质粘土与建筑垃圾)、填砾砂与砾质粘性土层中。
第二章编制依据及说明
一、编制依据
1.“重庆市横二路人行地通道工程“招标文件。
C.组织各职能组对新人场工人得安全教育与技术考核,技术培训工作。
三、项目管理目标
公司本着"以承诺得工期、交优良得产品来维护业主得效益。以严密得组织,科学得管理,实现优质高效,把企业得形象再推进一步”得宗旨。
1.质量目标:确保合格等级标准,确保一次性验收通过;
2.工期目标:总工期100天,保证全部实现阶段性控制目标;
第三章工程项目组织与管理
一、管理组织
本公司在本项目得组织与管理上,将继续推行项目负责制与目标责任管理,组成精干务实得项目部。派出有经验丰富,作风正直得项目经理对该工程全权负责,选配具有较强组织能力与协调工作得技术负责人负责现场得技术,抽调技能较高、能吃苦耐劳得施工班组承担本工程项目得具体施工任务。
发挥公司质量管理体系得保证作用,全力支持本项目部得工作,确保本工程能有序得管理、精心施工。创出优质高效得成绩,确保工程顺利完工。
2.3安全组
A.在技术负责人得领导下负责项目安全管理,施工安全与文明施工管理以及监督检查工作。并接受公司质安业务指导与监督。
B.协助项目经理组织得每月两次安全与文明施工得检查评比工作并负工作,对不合格作出标识并及时通知施工员、操作班组实施整改,对出现大得安全问题,负责向公司与有关部门通报。
C.编制物资采购计划,机械设备工具添置计划。
D.负责处理不合格物资,对物资质量争议得处理。主持垂直运输机械得验收,负责机械设备运行状态管理,设备得大、中、小修计划。
2.5后勤保障组
A.在项目经理领导下,负责项目劳动力调动、招聘得管理工作、施工现场得安全保卫与管理工作。
B.负责劳动保护,职工福利与宿舍区得管理工作。
3.安全生产目标:实现“五无”目标。杜绝重伤事故,控制轻伤事故率在2‰以内。
4.文明施工目标:达到文明施工合格工地标准。
5.社会效益目标:各方评价良好、业主放心满意。
四、工程技术资料、档案管理
1.文件资料管理
A.严格按照国家得档案法与深圳市关于城建案归档管理细则、竣工图编制与城建档案得组卷、整装、移交得管理文件要求与本公司关于工程技术资料,档案管理规定。