计算实例: (作业 )
M.V. "Brodie"
Arrived 0600 Hrs Wednesday 9th June
N.O.R. Tendered 1100 Hrs Wednesday 9th June
Loading Commenced 0700 Hrs Thursday 10th June
Loading Completed 1200 Hrs Tuesday 15th June
Vessel sailed 2100 Hrs Tuesday 15th June
Cargo loaded 20,000 metric Tonnes Grain in Bulk
"Lay time to commence at 1300 Hrs if notice given before noon. At 0700 Hrs next working day if given after noon, notice to be given in ordinary working hours (0900-1700 Hrs Monday to Friday)".
"Cargo to be loaded at the rate of 5,000 metric Tonnes per weather working day of 24 consecutive hours".
Time from 1700 Hrs Friday or the day preceding a holiday to 0800 Hrs Monday, or next working day not to count unless used, but only actual time used to count, unless vessel already on demurrage.
Demurrage rate $5,000 per day pro rata/despatch rate at half demurrage rate on lay time saved.
Other salient notes: Normal port working hours 0700-1700 Monday to Friday. Working outside aforementioned normal hours is available on overtime basis.
On Monday 14th June rain stopped work in the port from 0900-1000 Hrs.
The vesselsowners agreed an overtime shift from 0700-1600 Hrs on Saturday 12th June.
The vessels saili ng was delayed due to an engine problem on 15th June. 答案:
编号 ___________________
日期Date _________________
递交装卸准备就绪通知书时间
Notice of Readi ness Ten dered: 1100 Hrs Wed nesday 9th June
单位名称
Messr _______________
船名
M.V._Brodie
Load ing/Dischar ging 20,000 metric
tons of Grain in Bulk
时间
日期
星期
Time
Date
Day
装/卸货种及吨数
接受装卸准备就绪通知书时间
Notice of Readi ness Accepted:
装卸时间起算时间
Laytime Comme need to Cou nt: 1300 Hrs Wed nesday 9th June 开始装卸时间
Load in g/Discharg ing Comme need: 0700 Hrs Thursday 10th June 装/卸货完毕时间Load in g/Discharg ing Completed: 1200 Hrs Tuesday 15th June 货物装/卸率
Rate of Loadi ng/Dischargi ng: 5,000 MT per W.W.D. of 24 con secutive hours
日期Date
星期
Day of the
Week
时间Hours 说明
Descripti on
可用时间
Laytime allowed D
H M
实用时间
Laytime used D
H M
节省/滞期时间
Time
saved/lost
D H M
From to
9th June Wedn esday O600 Arrived 0 0 0
9th June Wedn esday 1100
N.O.R.
Ten dered
0 0 0
9th June Wedn esday 1300
Laytime
comme nee
0 0 0 9th June Wedn esday 1300 2400 Laytime cou nt 11 11 0
10th June Thursday O000 2400 Laytime cou nt
24 24 0
11th June Friday O000 1700 LOADING 17 17 0 11th June Friday 1700 2400 not to cou nt 0 0 0
12th June Saturday O000 O700 not to cou nt
0 0 0
12th June Saturday O700 1600 overtime
work
9 9 0
12th June Saturday 1600 2400 not to cou nt 0 0 0 13th June Sunday O000 2400 not to cou nt 0 0 0